Section 11215
CENTRIFUGAL BOOSTER PUMPS
PART 1 - GENERAL
1.1 THE REQUIREMENT
A. The CONTRACTOR shall furnish and
install single stage, horizontal, end suction booster pumps with
enclosed electric motors, controls and all appurtenant Work,
complete and operable, in accordance with the requirements of the
Contract Documents. Each Pumping Unit shall be rated for continuous
duty in accordance with the operating conditions. Each unit shall be
furnished with pump, motor, horizontal pump/motor baseplate with
flexible coupling and guard.
1.2 RELATED WORK SPECIFIED
ELSEWHERE
A. The requirements of the following
sections and divisions apply to the Work of this section. Other
sections and divisions of the Specifications, not referenced below,
shall also apply to the extent required for proper performance of
this Work.
1. Division 01, Additional General
Requirements
2. Section 09800, Protective Coating
3. Section 11005, Equipment: Basic
Requirements
4. Section 11210, Pumps, General
5. Section 16418, VFDs Below 100 hp
6. Section 16220, Electric Motors
7. Division 16, Electrical,
applicable sections
8. Section 17300, Control Strategies
9. Section 17405, Process
Instrumentation and Control
1.3 REFERENCE SPECIFICATIONS,
CODES, AND STANDARDS
A. All Work specified herein shall
conform to or exceed the applicable requirements of the referenced
portions of the following publications to the extent that the
provisions thereof are not in conflict with other provisions of these
Specifications.
B. Comply with the applicable
editions of the following codes, regulations and standards.
1. Industry Standards:
ASTM International (ASTM)
ASTM A 48
Standard Specification for Gray Iron Castings
C. Comply with the applicable
reference Specifications as directed in the General
Requirements and the Additional
General Requirements.
1.4 CONTRACTOR SUBMITTALS
A. Submittals shall be made in
accordance with Section 11210, Pumps, General, and as specified
herein.
1.5 QUALITY ASSURANCE A.
General
1. Comply with the requirements
specified herein and the applicable reference
Specifications of the General
Requirements and Additional General Requirements.
2. Comply with applicable parts of
Section 11005, Equipment: Basic Requirements, and Section 11210,
Pumps, General.
1.6 WARRANTY
A. The pumps and all components
specified in this Section shall be warranted by the manufacturer for
a minimum one (1) year period after beneficial occupancy of the Work
pursuant to “Use Prior to Final Completion” of the General
Conditions, against defects in workmanship and materials.
PART 2 - PRODUCTS
2.1 PUMP NAME: 17BPMP410,
17BPMP420, 17BPMP430
A. General: Pumps shall conform to
the following requirements:
1. Number of Pumping Units: 3
2. Location: Thickening Dewatering
Building, Outdoors, North Side of Building
3. Operation: Intermittent and
continuous
B. Operating Conditions:
1. Design Capacity (gpm): 1000
2. Total Dynamic Head (TDH-ft): 161
at a full speed and flow with a minimum pump efficiency of 80%.
3. Secondary Conditions at Reduced
Speed: 600 gpm at 61 FT TDH at 1050 RPM,
750 gpm at 97 FT TDH at 1350 RPM
4. Minimum Shutoff Head (TDH-ft):
178
5. Maximum Suction Pressure (psi);
100
6. Minimum Suction Pressure (psi):
34
7. Liquid to be Pumped: Potable
water
8. Max Pump Speed (rpm): 1800
9. Max Motor Size (horsepower): 60
10. Sphere Size Passable, Minimum
(in): 1
11. Minimum Suction Size (inches): 6
12. Minimum Discharge Size (inches): 5
2.2 PUMP REQUIREMENTS
A. Construction: Construction of
pumps shall conform to the following requirements:
1. All major pump parts shall be
made of cast iron conforming to ASTM A 48, Class 30 or better. The
casing assembly and drive connection shall permit the removal of the
rotating element without disconnecting the piping. Casing parts
shall have registered fit to maintain alignment. The nozzle flanges
shall be flat faced, with ANSI/ASME B16.1, Class 125 diameter and
drilling. Pipe-tapped openings shall be provided for draining,
priming, and venting the casing. Cast iron casings shall be provided
with plugged gauge cock connections on the suction and discharge
nozzles. The pump shall contain no points of critical clearance nor
require periodic adjustment or replacement to maintain reasonable
pumping efficiency. All waterway passageways shall be free from
hollows, pinholes, cracks, fins, and projections that might cause
cavitation.
2. Impeller: The impeller shall be
a one-piece casting. The impeller shall be completely machined
on all exterior surfaces, except when high chrome alloy
material is specified. The interior water passages shall have
uniform sections and smooth surfaces and shall be free from cracks
and porosity. The impeller shall be securely locked to the shaft so
that it will not be loosened by reverse rotation, but shall be
easily removable. The impeller shall be of the enclosed type,
statically and hydraulically balanced, and keyed to the pump shaft.
3. Bearings: Regreasable
lubricated ball bearing type. Bearings shall have an ABMA L10
Life Rating of 40,000 hours at specified operating conditions. The
pump shaft speed shall not exceed the limits specified by the
bearing manufacturer.
4. Shaft: Steel, AISI 1045.
5. Seal: Mechanical seal, single or
double, internally cooled.
6. Wear Ring: Bronze
(ASTM-B584-932).
7. Hardware: All exposed nuts,
bolts, and miscellaneous hardware shall be Type
316 stainless steel if available as a
manufacturer’s standard option. Otherwise manufacturer’s
standard shall be supplied.
8. Mounting Method: Support foot
casing supports.
9. Pump Connection: Flanged with
dimensions conforming to ANSI B16.1, Class
125.
B. Drive: Each pump shall be driven
by a TEFC motor through a flexible coupling. The motor shall be
suitable for use with a variable frequency drive and meet the
requirements of Section 16220, Electric Motors. The motor shall be
furnished by the pump manufacturer and be coordinated with the
requirements of the VFD, and pump, sized to be non over loading
during operation at any point on the pump curve. The flexible
coupling shall have a horsepower rating 1.25 times the motor
nameplate horsepower when the misalignment is within the
manufacturer's tolerance limit. Coupling design shall permit
removal of the pump rotating element without disconnecting the
piping, moving the drive unit, or axial movement of the coupling
halves on the shaft. When the pump is installed in a classified
area, it shall be approved and labeled for such area. Refer to the
Drawings for area classification information.
C. Control: The Instrumentation and
controls shall be provided as indicated on the P&IDs,
elementary diagrams (control schematics) and shall be in
accordance with Divisions 16, Electrical, and 17, Instrumentation
and Control, of the Specifications. The design Drawings shall be
modified to support the selected over temperature switch
configuration used by the manufacturer for the motor.
D. Painting: Pumps and motors shall
be painted according to Section 09800, Protective
Coating, of these Specifications.
2.3 MANUFACTURERS
A. The manufacturer shall be one of
the following, Or Equal:
1. Bell and Gosset.
2. Taco.
3. Aurora.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Pumping equipment shall be
installed in accordance with approved procedures submitted with
the shop drawings and as shown, unless otherwise accepted by the
ENGINEER.
B. General installation requirements
shall be as specified for "Execution" in Section
11210, Pumps, General.
3.2 TESTING
A. The electrical system shall be
tested in accordance with Section 16080, Electrical
Testing.
3.3 MAINTENANCE OF INSTALLED
EQUIPMENT
A. Maintain the operability and
functionality of all installed equipment between the time of
installation and the commissioning period. See Specification
section 01660 for requirements.
3.4 MANUFACTURER’S FIELD
SERVICES
A. Furnish the services of authorized
technical representatives of the Manufacturer to assist/inspect the
installed equipment and to certify that the equipment has been
properly installed and is ready to operate, train OCSD personnel,
conduct pre-operational mechanical checkout of the equipment, place
equipment into operation, optimize the performances of the equipment
and perform the field performance testing.
B. At a minimum, conduct three
separate site visits as follows:
1. Inspection of equipment
installation (8 hours minimum)
2. Training of OCSD Personnel:
See Specification section 01820, Training of
OCSD Personnel, for requirements.
3. Commissioning. See Specification
section 01810, Commissioning, for requirements. Number of hours
shall be as required to meet all testing and commissioning
requirements, but shall not be less than 8 hours.