Section
01300
CONTRACTOR'S
CONSTRUCTION SCHEDULE AND REPORTS
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. It is expressly
understood and agreed that the rate of progress and the time of
completion of the Work are of the essence for this Contract. The Work
shall be executed with such progress as required to prevent any
delay to this Contract and to other CONTRACTOR’s working on
other contracts at the site. This includes Contract Milestone dates
and constraints, time requirements, and the general completion of the
Work as defined in the Contract Documents;
B. The Work specified
in this Specification section includes preparation, submittal, and
use of a Construction Schedule as a portion of the CONTRACTOR’s
mobilization. Its subsequent updates and revisions, as reviewed and
allowed by the ENGINEER, shall be a required part of each Progress
Payment Application submitted by the CONTRACTOR as provided in the
Contract Documents.
C. The CONTRACTOR shall
prepare and submit all required Construction Schedules in accordance
with the requirements of this Specification section. By preparing and
submitting the schedules and progress period updates, the CONTRACTOR
represents that it can, and intends to, safely execute the contracted
Work and all portions thereof including all activities of
Subcontractors, equipment vendors, and suppliers including submittals
and re-submittals within the specified times and constraints and that
its Bid Price includes all costs associated with execution of the
Work described in the Contract Documents and as represented in the
Construction Schedules.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following sections and divisions apply to the Work of this
section. Other sections and divisions of the Specifications, not
referenced below, shall also apply to the extent required for proper
performance of this Work.
1. Section 01140, Work
Restrictions
2. Section 01155,
Measurement and Payment
3. Section 01810,
Commissioning
B. Comply with the
requirements of the General Conditions, Special Provisions, and
General Requirements.
1.3
REFERENCE
SPECIFICATIONS, CODES AND STANDARDS
A. The CONTRACTOR shall
comply with the reference Specifications of the General
Requirements.
B. The following
publications are cited as references for the Critical Path Method
(CPM)
scheduling technique
described in this Contract:
1. O’Brien, J., CPM
in Construction Management, the latest edition, McGraw-Hill.
2. Association for
the Advancement of Cost Engineering International (AACE), latest
editions of Recommended Practices as applicable for
Engineering, Procurement and Construction.
1.4
PURPOSE
OF THE SCHEDULE
A. This Specification
section specifies requirements and procedures for the CONTRACTOR to
use in preparation of construction schedules, cost-loaded schedules,
resource-loaded schedules, cash flow projections, manpower
projections, and cost and schedule reports. The purpose of the
schedules and reports shall be to:
1. Ensure adequate
planning and timely execution of the Work by the
CONTRACTOR;
2. Facilitate
coordination and interfacing of the CONTRACTOR’s work with others
as needed;
3. Establish a
Baseline Construction Schedule to which subsequent periodic
schedule updates will be compared to determine overall progress and
performance toward satisfactory completion of the Contract;
4. Periodically record
the “As-Built” condition of the Contract;
5. Assist the ENGINEER
in monitoring progress;
6. Establish the
amount of the progress period payment to be made to the
CONTRACTOR;
7. Establish the
amount of daily manpower required to complete the Contract within
the Contract Duration;
8. Evaluate proposed
changes to the Contract and resultant impacts to the construction
schedule;
9. Effectively
determine time impacts on overall Contract completion.
1.5
MOBILIZATION
AND PROGRESS PAYMENTS
A. OCSD’s
administration of the Contract, its construction program, internal
resource coordination, and operations planning may be severely
impeded if adoption of the schedule is delayed. Consequently ten
percent of the CONTRACTOR’s mobilization payment, as allowed
pursuant to the Contract Documents, shall be retained and allocated
for payment as follows:
1. The CONTRACTOR may
request and be paid twenty percent of the retained mobilization in
its payment application that follows submittal and acceptance of the
Interim Construction Schedule.
2. The CONTRACTOR may
request and be paid the balance of the retained
mobilization in its payment application that follows submittal and
acceptance of the Baseline Construction Schedule.
B. The CONTRACTOR’s
progress payment applications may be deemed improper and may not be
accepted and processed for payment by OCSD without periodic
Construction Schedule updates submitted in the time and manner
required by this Specification section and subsequently accepted
by the ENGINEER.
1.6
CONTRACTOR
SUBMITTALS
A. Certifications and
other submittal documentation in compliance with Article entitled
“Contactor
Qualifications” of this Specification.
B. The CONTRACTOR
shall submit all items as required by Appendix G of this
Specification section in the time, quantities, and manner stipulated
therein and in accordance with the Contract Documents for submittals
unless noted otherwise herein.
1.7
QUALITY
ASSURANCE
A. CONTRACTOR
Qualifications
1. The CONTRACTOR
shall provide a full-time, onsite construction scheduler,
proficient in the use of Primavera®
Project
Management software, who shall have a minimum of ten years
verifiable experience in construction work sequencing,
productivity,
preparation and maintenance of detailed construction schedules for
individual contracts of $50 Million and larger in constructed value.
a. Within seven days
after the effective date of the Notice to Proceed, the CONTRACTOR
shall submit the construction scheduler’s resume to the ENGINEER,
including personal references from at least two owner-
representatives familiar with the construction scheduler’s
work on previous similar contracts. The ENGINEER reserves the
right to reject the proposed scheduler based on poor references,
lack of qualifications as defined in this Specification section,
and/or poor performance history on previous OCSD contracts including
late schedule submittals, lack of responsiveness to requested
clarifications, corrections, re-submittals and/or time impact
analysis.
b. The CONTRACTOR’s
scheduler shall attend all meetings, including progress and special
meetings pertaining to scheduling of the Work. The scheduler, along
with the CONTRACTOR’s management team shall work closely with the
ENGINEER to comply with and deliver the requirements of this
Specification section.
c. It is the specific
intent of this Specification section that the CONTRACTOR and its
scheduler shall be wholly responsible for developing, maintaining,
updating, checking and providing an accurate and comprehensive
representation of the CONTRACTOR’s work plan in the required
software, related databases and reports to achieve the purposes set
forth in the Contract Documents.
1.8
ENGINEER’S
REVIEW
A. The ENGINEER
shall review schedule submittals in accordance with
this Specification section and the other Contract Documents for the
administrative purposes described herein. However the ENGINEER’s
review, comments or consent to use the CONTRACTOR’s schedule shall
not be construed as validation or endorsement of the CONTRACTOR’s
work plan and approach nor shall it relieve the CONTRACTOR of any
and all responsibility, liability or risk related to its work plan,
its work plan as represented by the schedule, or requirements of the
Contract.
1.9
GENERAL
SCHEDULE REQUIREMENTS
A. The CONTRACTOR
shall have sole responsibility for development, maintenance, update,
revision, checking and presentation of its work plan in the form of
a Critical Path Method (CPM) Construction Schedule for use by
the ENGINEER in meeting the purposes described in the Contract
Documents. The CONTRACTOR shall provide all information concerning
methods, means, sequencing, logic, and duration of all activities as
well as providing all CPM logic network diagram and tabular report
data.
B. The CONTRACTOR
shall use Primavera®
P6
Professional Project Management, release 8.0, submit electronic
files compatible with the required software and coordinate use of
subsequent releases with OCSD to ensure data compatibility. The
CONTRACTOR shall use a hardware system commensurate with the size of
the contract, capable of handling, processing, printing, and
plotting all data required to satisfy the requirements of this
Section.. The system shall be capable of handling, processing,
printing, and plotting all data required to satisfy the requirements
of this Specification
section. Electronic
files submitted to OCSD shall be compatible with Primavera®
Project
Management, latest
version.
C. Within fourteen
days following the effective date of the Notice to Proceed,
the ENGINEER shall schedule and conduct a Pre-Construction
Scheduling Conference to commence development of the required
construction schedules. At the meeting, the requirements of this
and related Specification sections will be reviewed with the
CONTRACTOR and the CONTRACTOR shall present its proposed:
1. Methodology for the
CPM Construction Schedule, illustrating sequence of operations,
cost, resource and quantity loading.
2. Work Breakdown
Structure (WBS), Activity Coding Structure and Activity
Identification numbering system for labeling all Work Activities,
correlated with the Contract Agreement Schedule of Prices. At a
minimum the CONTRACTOR shall provide the data detailed in Appendices
B and C of this Specification section.
D. The ENGINEER shall
review the WBS, the coding structure, and activity identification
system presented by the CONTRACTOR within ten days following the
Pre-Construction Scheduling Conference. The CONTRACTOR shall make
all modifications requested by the ENGINEER and, following
concurrence by the ENGINEER, shall employ the agreed to coding,
structure, and system in its Construction Schedule. In addition the
CONTRACTOR may be required to develop additional activity codes and
values to comply with reporting requirements listed in the Contract
Documents, and/or as directed by the ENGINEER.
E. The Work Activities
comprising the Construction Schedule shall be of sufficient detail
to assure adequate planning and execution of the Work such that, in
the judgment of the ENGINEER, it provides an appropriate basis for
predicting, monitoring, evaluating and recording the progress of
the Work. Work Activities shall conform to the following
requirements:
1. Describe Work
Activities using consistent terminology such that the Work is
readily identifiable for assessment of progress and completion.
2. Subdivide the Work
into activities of duration no longer than fifteen uninterrupted
work days each, except as to non-construction activities, such as
procurement and delivery of materials and equipment, and any
other activities for which the ENGINEER may accept a longer
duration in writing.
3. The construction
time, as determined by the schedule, from early start to late finish
for any sub-phase, phase, or the entire contract shall not exceed
the Contract Duration specified or shown in the Contract
Documents. One day shall be the smallest time unit shown unless
otherwise directed in writing by the ENGINEER.
4. Except as provided
for in Appendix B for milestones, activities labeled "start,"
"continue," or "completion" shall not be
allowed. Logic relationships between activities shall be limited
to finish-to-start (FS) type relationships and the use of lags or
durations between activities shall not be permitted unless accepted
in writing by the ENGINEER.
5. The CONTRACTOR
shall not constrain the schedule with artificial logic ties and/or
constraint dates and/or use any other scheduling techniques that may
distort the activity float and total float associated with the
critical path activities and the schedule in general. The only
allowable constraint shall be for Contract Milestone dates using a
“Finish On or Before” constraint, unless accepted in writing by
the ENGINEER.
6. Each Work
Activity shall contain the following information as
elaborated in
Appendix B of this
Specification section:
a. WBS coding,
activity coding and a unique activity identification number
consistent with the structure and system agreed to by the ENGINEER.
b. Performance
responsibility; General CONTRACTOR or Subcontractor trade code; GEN,
MECH, ELEC, CARP, PLAST, etc.
c. Work location code
and description of the physical plant area involved. d. Duration
in work days based on the appropriate Activity Calendar.
e. Cost Data as
mandated herein
f. Resource Data as
mandated herein
F. The ENGINEER may
require the CONTRACTOR, at any time during the Contract, to develop
a more detailed schedule and/or fragnet than depicted in the
Construction Schedule to clearly illustrate the effort needed to
complete a specific area or task.
G. The Construction
Schedule shall contain the following standard milestones; Notice to
Proceed; Mobilization; Construction Start; Specified Contract
Milestones for each phase of Work as identified in Contract
Documents; Beneficial Occupancy; Substantial Completion and Final
Completion
H. Activity Cost
Loading:
1. The schedule shall
incorporate cost-loaded activities equal to the Contract Total Price
and Sub-Totals set forth in Contract Agreement ‘Exhibit “A”
Schedule of Prices’ and as further detailed in the General
Conditions section entitled ‘PAYMENT – ITEMIZED BREAKDOWN OF
CONTRACT LUMP SUM PRICES’.
2. The CONTRACTOR
shall further divide its prices to determine and substantiate a fair
allocation of costs to each activity of Work in the schedule that is
physically incorporated into the facility.
3. The CONTRACTOR
shall not unbalance the activity cost loading and, except for
mobilization costs, shall prorate overhead and profit on all
activities for the entire contract term. The CONTRACTOR shall
furnish the minimum data required in Appendix G of this
Specification section to the ENGINEER for review and agreement prior
to integrating cost data into the schedule:
4. Procurement,
submittal preparation and submittal review activities shall not be
cost-loaded. Payment for material and equipment shall be made in
accordance with the Contract Documents.
5. The Payment
Application and all periodic payment requests shall be based upon,
but may not be limited to, the cost-loaded Construction
Schedule update; the Contract Agreement ‘Exhibit “A” Schedule
of Prices’; and the General Conditions section entitled ‘PAYMENT
– ITEMIZED BREAKDOWN OF CONTRACT LUMP SUM PRICES’.
6. Proposed changes to
the authorized Cost-loaded Construction Schedule may only be made
with the written acceptance by the ENGINEER.
I. Activity Resource
Loading:
1. The activities
contained in the Construction Schedule shall be resource-loaded to
show the number of work force employees needed on a work day basis
to complete the Work within the Contract Duration.
2. Resource activity
loading shall include, at a minimum, the composite crew, the
classification (e.g., foreman, journeyman, etc.) of the individuals
comprising the crew, materials, and equipment associated with each
activity shown on the schedule, plus any other information required
by ENGINEER.
3. Labor resources
shall be listed in the Resource Library of the Primavera®
Software
and the CONTRACTOR shall assign labor resource loading by trade for
each Work Activity of the schedule.
4. The CONTRACTOR may
use the Primavera®
Resource
Leveling function for its own internal analysis and planning, but
shall not use it in the contract record or submittal schedule
databases to avoid potential distortions resulting from the retained
logic function.
5. Proposed changes to
the authorized Resource-loaded Schedule may only be made with the
written acceptance by the ENGINEER.
J. The Construction
Schedule shall begin with the date of issuance of the Notice to
Proceed and not exceed the maximum Contract Duration provided in the
Contract. It shall include, but not be limited to, the following
items as appropriate to this Contract:
1. All administrative
tasks
2. Type of work to be
performed, sequences, and labor trades involved, including
performance responsibility and trade code.
3. Quantity loading
of activities showing, at a minimum, unit price bid items,
estimated quantities to be installed or removed as indicated in the
Contract Documents or as determined by the CONTRACTOR in preparation
of its Bid, and any additional information required by the ENGINEER.
4. All manufacturer
factory tests, material and equipment deliveries, field tests,
readiness tests, and installation activities that the CONTRACTOR
intends to seek payment for, including stored materials.
5. All submittal
preparation and reviews including ENGINEER reviews, and acceptance
of shop drawings and material samples shall provide a 25 day minimum
duration as specified for the ENGINEER’s review of submittals,
unless the submittal is of the type requiring a longer period of
time as specified in the Contract Documents for Shop Drawing
Submittals.
6. Delivery,
installation, check-out/testing, and startup of
OCSD-furnished equipment and/or materials in accordance with the
schedule dates set forth in the Specifications or as furnished by
the ENGINEER.
7. Approvals required
by regulatory agencies or other third parties, including
CONTRACTOR obtained
permits
8. Identification of
all subcontract Work and assignments of responsibility for
performing specific activities.
9. All temporary
utilities and construction required by the CONTRACTOR to perform the
Contract Work.
10. Access to and
availability of work areas including all anticipated plant
shutdowns, pump station shutdowns, flow diversions, or bypass
pumping.
11. All interruptions,
shut downs and connections to existing plant systems and equipment.
12. All start up,
testing, training, and assistance required under the Contract
Documents.
13. Timing of the phased
or total takeover of the Work by OCSD as may be required by the
CONTRACT.
14. Identification of
any work force, material, or equipment restrictions, as well as any
activity requiring unusual shift work, such as two shifts, six day
weeks, overtime, or work at times other than regular days or hours,
shall be clearly identified in the Construction Schedule. Normal
work hours are eight hours per day, five days a week, unless
specified otherwise in the Contract Documents.
15. CONTRACTOR
activities that will be coordinated with OCSD on-going activities.
16. Material and
Equipment Installation including installation, check-out, Operations
and Maintenance manuals submittal and acceptance, training
lesson plan(s) submittal and acceptance, and OCSD staff training.
17. CONTRACTOR-prepared
drawings
and diagrams such as shoring diagrams.
18. Clearly identify all
non-work days such as holidays, or other non-work periods in the
schedule,
19. Specific Work
Activities, including but not limited to, site work, underground
piping and electrical ductbanks, structural excavation, soil
testing, backfill, placement of sheeting, pile driving, formwork
erection, rebar placement, placing of concrete, stripping forms,
concrete curing, installation of process piping, electrical conduits
and wiring, instrumentation and controls conduits and wiring,
terminations, other materials and plant equipment, and cleanup.
20. The CONTRACTOR
shall provide an activity for Inclement Weather with a
duration that reflects the number of inclement weather days provided
for in the Contract Documents as follows:
a. The Inclement
Weather predecessor activity shall be the last construction activity
that occurs before Substantial Completion.
b. The Inclement
Weather successor activity shall be the Substantial
Completion milestone.
c. The CONTRACTOR
shall notify the ENGINEER in writing within seven days when a lost
work day has occurred due to inclement weather. The CONTRACTOR
shall correspondingly reduce the inclement weather activity
duration as weather days occur, are recognized and
accepted by the ENGINEER.
d. The CONTRACTOR
shall notify the ENGINEER in writing to request a non- compensable
extension of time if the number of actual inclement weather delay
days exceeds the number of inclement weather delay days identified
in the Contract Documents. Such delays shall not entitle the
CONTRACTOR to additional compensation.
21. Punchlists.
22. Final cleanup.
23. Specific information
required by the ENGINEER.
24. Required inspections
by the ENGINEER.
25. Progress period
updating of Contract Record Drawings and final submittal of As-
Built Drawings at contract completion, or as directed by the
ENGINEER.
1.10
INTERIM
CONSTRUCTION SCHEDULE REQUIREMENTS
A. Within 30 days
following Notice to Proceed the CONTRACTOR shall submit its detailed
written work plan for the first 150 days of operation and its
general approach to the remainder of the Work. The work plan and
approach to the remainder of the Work shall also be submitted in the
form of an Interim Construction Schedule that incorporates all
applicable elements of this Specification section and the other
Contract Documents sufficient to meet its purpose.
B. The ENGINEER shall
meet with the CONTRACTOR within ten days of the submittal to review
and agree on any necessary adjustments and revisions. When revised
and accepted by the ENGINEER the Interim Construction Schedule shall
illustrate the CONTRACTOR’s methods, means, logic, sequencing and
durations of the Work represented by cost-loaded and resource-loaded
activities for the first 150 days of the contract. It shall also
include cost loading and resource loading for the balance of all
contract Work to a summary level through the Final Completion
milestone as forecast by the CONTRACTOR.
C. The Interim
Construction Schedule shall be updated as provided in this
Specification section and used to monitor job progress during the
first 150 days of the contract or until acceptance of the Baseline
Construction Schedule by the ENGINEER.
1.11
BASELINE
CONSTRUCTION SCHEDULE REQUIREMENTS
A. Within 90 days
following Notice to Proceed the CONTRACTOR shall submit its detailed
written plan for the Work. The work plan shall also be submitted in
the form of a Baseline Construction Schedule that incorporates all
applicable elements of this Specification section and the other
Contract Documents sufficient to meet its purposes as described
therein. It shall demonstrate the final level of detail for each
activity, all required relationships completely identified, and the
duration of each activity correctly depicted. It shall be developed
as follows:
1. The activities
shown in the interim schedule shall be integrated into the Baseline
Construction Schedule without change to form a comprehensive
representation of the CONTRACTOR’s execution of the Work from
start to finish.
2. The Baseline
Construction Schedule submitted for review and acceptance by the
ENGINEER shall be un-statused and the data date shall be the
Contract Notice to Proceed date.
3. The Baseline
Construction Schedule shall clearly indicate the Longest Critical
Path of activities from
Notice to Proceed to the Contract Completion date.
4. The Baseline
Construction Schedule shall contain all cost information assigned to
each discrete activity at the final level of detail. Each activity
shall be cost-loaded to permit generation of cash flow curves
5. The Baseline
Construction Schedule shall contain all resource information
assigned to each discrete activity at the final level of detail.
Each activity shall be resource-loaded to permit generation of
resource curves.
6. The CONTRACTOR
shall collect data and information from Subcontractors,
suppliers, and equipment manufacturers for incorporation into the
Baseline Construction Schedule. The baseline schedule submittal
shall include signed certification letters from Subcontractors,
suppliers and vendors that they have reviewed, discussed and agreed
to the schedule as it relates to their work.
7. The Baseline
Construction Schedule shall contain no Contract changes or delays
which may have been incurred during the schedule development period.
These changes will be entered at the first update after the Baseline
Construction Schedule has been accepted by the ENGINEER and a change
to the Contract Duration made as part of an approved Change Order in
accordance with the Contract Documents.
8. Once the Baseline
Construction Schedule is agreed to and accepted by the ENGINEER it
shall become the schedule of record and shall be the basis for
future schedule updates.
9. After adoption of
the Baseline Construction Schedule, no changes shall be made
therein, including changes to logic, sequence and/or duration,
without the agreement of the ENGINEER.
B. The ENGINEER will
have up to 25 days to evaluate and prepare its comments to the
Baseline Construction Schedule submittal before scheduling a meeting
with the CONTRACTOR to discuss it.
C. Within ten days of
returning its submittal response, the ENGINEER will schedule a
meeting with the CONTRACTOR to review and discuss any adjustments
and revisions to the Baseline Construction Schedule required to make
it acceptable to the ENGINEER.
D. After acceptance by
the ENGINEER, the Baseline Construction Schedule shall represent the
CONTRACTOR’s methods, means, logic, sequencing and durations of
the Work and include the CONTRACTOR’s estimated costs and
resources for each discrete activity as required to meet the
purposes of this Specification section and the other Contract
Documents.
1.12
PROGRESS
OF THE WORK
A. Once the Baseline
Construction Schedule is adopted the CONTRACTOR shall be responsible
for preparing and submitting periodic progress update information in
the form of a progress report concurrent with the Progress Payment
Application cycle established for the contract. At a minimum the
progress report and schedule update shall include:
1. Narrative Progress
Report
2. Updated
Construction Schedule
3. Reports, tables and
diagrams ad described in Appendix G of this Specification section.
B. On a date
determined by the ENGINEER, the CONTRACTOR shall meet with the
ENGINEER to review the CONTRACTOR’s Progress Payment Application
and its required supporting documents, including its Narrative
Progress Report and its Construction Schedule Update.
1. Appendix E of this
Specification section outlines the update preparation and review
sequence to be used for preparation, submittal and review of the
Narrative Progress Report and Construction Schedule update.
2. The CONTRACTOR and
the ENGINEER will review the Draft submittal, discuss its content
and the ENGINEER will authorize modifications, as appropriate, to
facilitate approval of the Payment Application.
3. Following the
review meeting, only those revisions authorization by the
ENGINEER shall be incorporated into the electronic file entitled
“Update” which shall then be submitted as the record schedule
for the progress period update.
4. The ENGINEER shall
be allowed seven days after the meeting to review and determine the
acceptability of the Narrative Progress Report and Construction
Schedule update. This variance from the typical submittal review
period is made specifically to facilitate timely processing of the
CONTRACTOR’s Progress Payment Application.
5. Narrative Progress
Report and Construction Schedule updates returned to the CONTRACTOR
marked “Revise & Resubmit” or “Not Acceptable” shall
constitute a deficient payment application that will not be
processed for payment until the schedule report is acceptable to
the ENGINEER.
6. Narrative Progress
Report and Construction Schedule updates returned to the CONTRACTOR
marked “Revise & Resubmit” or “Not Acceptable” shall be
resubmitted to the ENGINEER within seven days, at which time a new
seven day review period will begin for the ENGINEER.
C. The Narrative
Progress Report shall summarize the schedule status and be
organized as follows:
1. The CONTRACTOR's
transmittal letter, containing the submittal number.
2. Contents Sheet
3. Identification of
the Update including the Data Date, Update Period and the
Schedule File Names as
defined in Appendix D to this Specification section.
4. Update Summary
including the variance between Contract Milestone dates and their
predicted completion dates; Contract Completion variance for the
reporting period; the number of days ahead or behind schedule;
weather days taken and remaining from the Contract allowance and
tables summarizing the status of Contract finances and time. At a
minimum the CONTRACTOR shall provide the data required by the
example in Appendix G of this Specification section.
5. Analysis of
Critical Path and each negative Float Path describing the nature of
the Critical Path, its impact and the impact of any negative float
path on other activities, milestones and completion dates:
6. All current and
anticipated time impacts describing the origin of each event;
corrective action and schedule adjustments to correct it;
recommendations to recover from it and the effect that it may have
on other activities, milestones and completion dates.
7. Pending status of
outstanding issues such as permits, if any; Contract modifications,
RFC’s and or RFP’s containing requests for time adjustment;
long-lead procurement items; safety reports and any code violations
or warnings.
8. Narrative
discussion of contract status including highlights of work by
area, progress, completion, impediments, changes to the Work plan,
issues and concerns accompanied by OCSD Activities and Schedule
Change Tables. At a minimum the CONTRACTOR shall provide the data
required in Appendix G of this Specification section.
D. Progress Period
Schedule Updates:
1. The CONTRACTOR
shall be responsible for preparing and submitting updated schedules,
related reports and diagrams, as part of its periodic update Report.
2. The Construction
Schedule update shall measure and record only those facts that have
occurred to the Work including physical percent complete type,
actual start and finish dates, and duration changes. Modifications
to logic, durations of activities not started or to actual dates
already recorded in previous updates shall not be allowed unless
authorized in writing by the ENGINEER. An electronic file shall be
created and entitled “Pure Progress” and included with the
update.
3. With each update
the CONTRACTOR shall identify any changes to the schedule, such as
Field Change Orders, accepted time adjustment requests, new
activities, constraint changes, deleted activities, activity
duration changes, activity description changes, and changes in logic
relationships between activities in a Schedule Change Table as
detailed in Appendix G of this Specification section. Logic changes
shall be described with an explanation of the rationale for the
change provided in the report. Such revisions may be incorporated
into an electronic file entitled “Draft Update” for target
comparison with the “Pure Progress” update. The
CONTRACTOR shall provide printed diagrams of the target comparisons
as part of its presentation to the review meeting.
4. All progress period
schedule updates shall be compared to the Baseline Construction
Schedule. In addition, each current progress period update shall be
compared to the previous period update. Each update shall be labeled
with the OCSD project number, data date and title abbreviation
identified on the hard copy and electronic file as described in
Appendix G of this Specification section.
5. The schedule shall
be updated with actual start and finish dates for every in- progress
or completed activity, as documented by the CONTRACTOR’s
Daily Reports and Three Week Look Ahead schedules. No other
basis, including automated software calculations or default
mechanisms shall be allowed. Failure of the CONTRACTOR to ensure
that documented dates as specified herein are incorporated into the
schedule update shall constitute cause for disapproval of the update
and the inability of the ENGINEER to accurately evaluate the
CONTRACTOR’s progress for payment purposes.
6. Activities that have
reported progress without predecessor activities being completed
such as Finish to Start (FS) Relationships with out of sequence
progress will not be allowed except on a case-by-case basis with the
written acceptance by the ENGINEER. A written explanation of each
such activity shall be included with each update in the Schedule
Change Table as detailed in Appendix G of this Specification
section. The ENGINEER may direct that changes in schedule logic be
made to correct any or all out-of-sequence Work.
7. Change order work
shall be identified in the schedule as a new activity inserted into
the affected schedule logic. The schedule activity shall only be
added after the Change Order is approved for payment by OCSD.
1.13
CONSTRUCTION
SCHEDULE REVISION
A. If the CONTRACTOR
decides to make major changes to the sequencing and logic of the
accepted work plan it shall prepare a schedule reflecting its
proposed changes for submittal to, and review by, the ENGINEER
separate and apart from the periodic schedule updates.
B. The CONTRACTOR’s
submittal shall be made in accordance with the requirements of the
Contract Documents and the ENGINEER will have a maximum 25 day
period for review before scheduling a meeting with the CONTRACTOR.
C. A Revised Schedule
that results in a predicted completion date later than the
Contract Completion date shall be rejected unless the delay is
deemed to be excusable or caused by OCSD and a time extension is
authorized in writing by the ENGINEER.
D. The ENGINEER will
then arrange a meeting with the CONTRACTOR to review the submittal,
discuss its content, and authorize modifications required to allow
its integration into the Construction Schedule.
1.14
AS-BUILT
CONSTRUCTION SCHEDULE
A. As a condition
precedent to release of any retention, the CONTRACTOR shall submit
its As-Built Construction Schedule. The As-Built Construction
Schedule shall reflect the manner in which the contract was actually
constructed including start and completion dates, and all
activities, sequences, and logic ties.
B. This schedule
submission shall be accompanied by a certification, signed by an
officer of the CONTRACTOR’s company, the CONTRACTOR’s Project
Manager and Construction Scheduler, stating “To the best of our
knowledge, the accompanying As- Built Construction Schedule
accurately reflects the actual start and completion dates and
logical relationships of all activities contained herein and
represents an accurate depiction of the way in which the contract
was constructed.”
1.15
WEEKLY
THREE WEEK LOOK AHEAD
A. The CONTRACTOR
shall submit an electronic copy of the Three Week Look Ahead
schedule to the ENGINEER no later than 48 hours prior to the weekly
construction progress meeting. The Three Week Look Ahead schedule
shall be developed maintained and provided using MS Excel®
software,
shall be in the form shown in Appendix G and
include at a minimum
actual performance for the previous week compared to the planned
work for the previous week, planned work for the current week and
planned work for the two weeks following the current week.
B. Each weekly Three
Week Look Ahead schedule shall be based on the current Construction
Schedule update Four Week Look Ahead Report and fully correlated to
the activities planned in its Primavera®
counterpart,
including submittal reviews, procurement, fabrication and delivery
of contract deliverables.
C. The CONTRACTOR shall
use the Three Week Look Ahead schedule actual performance record in
preparing its Construction Schedule update.
1.16
FLOAT
OWNERSHIP AND EARLY COMPLETION
A. Total float, free
float, independent float, near-critical float, critical path float,
slack time, or contingency within the overall Construction Schedule
is not for the exclusive use of either OCSD or the CONTRACTOR but is
jointly owned by both and is an expiring resource available to and
shared by both as needed to meet Contract Milestones and the
Contract Completion date.
B. Pursuant to the
float sharing requirements of the Contract, use of float suppression
techniques such as preferential sequencing, special lead/lag logic
restraints, extended activity times, or imposed dates shall be cause
for rejection of the Construction Schedule and any revisions or
updates thereto.
C. Within fifteen days
of Contract award, the CONTRACTOR shall formally notify OCSD in
writing of its intent to finish the Work earlier than the Contract
Completion date. Agreement between the ENGINEER and the CONTRACTOR
to adopt an early completion Baseline Construction Schedule shall
include agreement by both parties to amend the Contract Milestones,
completion dates, and associated liquidated damages, by Change
Order, to those completion dates contained in the agreed to
schedule.
1.17
TIME
ADJUSTMENT REQUESTS
A. Requests for time
adjustments shall be submitted in the time and manner specified in
the Contract Documents, as described herein and further elaborated
in Appendix F of this Specification section.
B. OCSD initiated
changes that extend or shorten the Contract Duration shall be the
sole basis to adjust the Contract Completion date. Delays in the
critical path not associated with proper requests for time
extensions in accordance with the Contract Documents shall be deemed
to be the responsibility of the CONTRACTOR.
1.18
REMEDIAL
MEASURES AND RECOVERY SCHEDULE
A. The CONTRACTOR
shall mitigate any potential delay to the Work as efficiently and
economically as possible regardless of cause. Where practical the
CONTRACTOR shall do so without added cost or adverse time impact.
Prior to initiating any action for which it expects OCSD to be
liable, the CONTRACTOR shall notify the ENGINEER in writing and
receive written authorization to proceed.
B. If the CONTRACTOR
believes the delay may result in a predicted completion date later
than the Contract Completion date, it shall review all uncompleted
activities on the critical and near critical paths to assess
mitigation options and, within seven days of discovering the
potential delay it shall submit a written statement to the ENGINEER
describing its plan to recover, including a statement that it has
verified the accuracy of all critical and near critical paths.
Following acceptance by the ENGINEER the CONTRACTOR shall
incorporate its recovery plan into the next schedule update.
C. Whenever it becomes
apparent to the ENGINEER that the current schedule update shows a
delay to the critical path, that these delays are through no fault
of OCSD and hence, the Contract completion date will not be
met, or when so directed by the ENGINEER, the CONTRACTOR shall
submit to the ENGINEER for review a written statement of the steps
it intends to take to remove or arrest the delay to the schedule and
the CONTRACTOR shall promptly provide the requisite level of effort
to bring the Work back on schedule. The CONTRACTOR shall then
incorporate its recovery plan into the next Construction Schedule
update.
D. A Recovery Schedule
that results in a predicted completion date later than the Contract
Completion date shall be rejected unless the ENGINEER determines
that the delay is the responsibility of OCSD, is excusable or that
it cannot be mitigated, and authorizes a time extension in writing.
E. The ENGINEER may
require the CONTRACTOR to provide reasonable additional resources to
recover from any schedule delay, however under no circumstances will
the addition of equipment or construction forces, increasing the
working hours or any other method, manner, or procedure to recover
from delays to the Schedule be considered justification for contract
modification for extra Work.
PART 2 - PRODUCTS
(NOT USED) PART 3 - EXECUTION
3.1
SUPPLEMENTS
A. The supplements
listed below are attached to and form a part of this Specification
section:
Appendix A - Definitions
Appendix B - Work
Breakdown and Activity Coding Structure
Appendix C - Activity ID
System Appendix D - Electronic File Naming Appendix E - Update
Preparation Sequence Appendix F - Time Adjustment Request Appendix G
- Contractor Deliverables
No comments:
Post a Comment