Wednesday, October 30, 2013

Section 01300 CONTRACTOR'S CONSTRUCTION SCHEDULE AND REPORTS

Section 01300

CONTRACTOR'S CONSTRUCTION SCHEDULE AND REPORTS

PART 1 - GENERAL

1.1 THE REQUIREMENT

A. It is expressly understood and agreed that the rate of progress and the time of completion of the Work are of the essence for this Contract. The Work shall be executed with such progress as required to prevent any delay to this Contract and to other CONTRACTOR’s working on other contracts at the site. This includes Contract Milestone dates and constraints, time requirements, and the general completion of the Work as defined in the Contract Documents;

B. The Work specified in this Specification section includes preparation, submittal, and use of a Construction Schedule as a portion of the CONTRACTOR’s mobilization. Its subsequent updates and revisions, as reviewed and allowed by the ENGINEER, shall be a required part of each Progress Payment Application submitted by the CONTRACTOR as provided in the Contract Documents.

C. The CONTRACTOR shall prepare and submit all required Construction Schedules in accordance with the requirements of this Specification section. By preparing and submitting the schedules and progress period updates, the CONTRACTOR represents that it can, and intends to, safely execute the contracted Work and all portions thereof including all activities of Subcontractors, equipment vendors, and suppliers including submittals and re-submittals within the specified times and constraints and that its Bid Price includes all costs associated with execution of the Work described in the Contract Documents and as represented in the Construction Schedules.

1.2 RELATED WORK SPECIFIED ELSEWHERE

A. The requirements of the following sections and divisions apply to the Work of this section. Other sections and divisions of the Specifications, not referenced below, shall also apply to the extent required for proper performance of this Work.

1. Section 01140, Work Restrictions

2. Section 01155, Measurement and Payment

3. Section 01810, Commissioning

B. Comply with the requirements of the General Conditions, Special Provisions, and
General Requirements.

1.3 REFERENCE SPECIFICATIONS, CODES AND STANDARDS

A. The CONTRACTOR shall comply with the reference Specifications of the General
Requirements.
B. The following publications are cited as references for the Critical Path Method (CPM)
scheduling technique described in this Contract:

1. O’Brien, J., CPM in Construction Management, the latest edition, McGraw-Hill.

2. Association for the Advancement of Cost Engineering International (AACE), latest editions of Recommended Practices as applicable for Engineering, Procurement and Construction.

1.4 PURPOSE OF THE SCHEDULE

A. This Specification section specifies requirements and procedures for the CONTRACTOR to use in preparation of construction schedules, cost-loaded schedules, resource-loaded schedules, cash flow projections, manpower projections, and cost and schedule reports. The purpose of the schedules and reports shall be to:

1. Ensure adequate planning and timely execution of the Work by the
CONTRACTOR;

2. Facilitate coordination and interfacing of the CONTRACTOR’s work with others as needed;

3. Establish a Baseline Construction Schedule to which subsequent periodic schedule updates will be compared to determine overall progress and performance toward satisfactory completion of the Contract;

4. Periodically record the “As-Built” condition of the Contract;

5. Assist the ENGINEER in monitoring progress;

6. Establish the amount of the progress period payment to be made to the
CONTRACTOR;

7. Establish the amount of daily manpower required to complete the Contract within the Contract Duration;

8. Evaluate proposed changes to the Contract and resultant impacts to the construction schedule;

9. Effectively determine time impacts on overall Contract completion.

1.5 MOBILIZATION AND PROGRESS PAYMENTS

A. OCSD’s administration of the Contract, its construction program, internal resource coordination, and operations planning may be severely impeded if adoption of the schedule is delayed. Consequently ten percent of the CONTRACTOR’s mobilization payment, as allowed pursuant to the Contract Documents, shall be retained and allocated for payment as follows:

1. The CONTRACTOR may request and be paid twenty percent of the retained mobilization in its payment application that follows submittal and acceptance of the Interim Construction Schedule.

2. The CONTRACTOR may request and be paid the balance of the retained mobilization in its payment application that follows submittal and acceptance of the Baseline Construction Schedule.
B. The CONTRACTOR’s progress payment applications may be deemed improper and may not be accepted and processed for payment by OCSD without periodic Construction Schedule updates submitted in the time and manner required by this Specification section and subsequently accepted by the ENGINEER.

1.6 CONTRACTOR SUBMITTALS

A. Certifications and other submittal documentation in compliance with Article entitled
Contactor Qualifications” of this Specification.

B. The CONTRACTOR shall submit all items as required by Appendix G of this Specification section in the time, quantities, and manner stipulated therein and in accordance with the Contract Documents for submittals unless noted otherwise herein.

1.7 QUALITY ASSURANCE

A. CONTRACTOR Qualifications

1. The CONTRACTOR shall provide a full-time, onsite construction scheduler, proficient in the use of Primavera® Project Management software, who shall have a minimum of ten years verifiable experience in construction work sequencing,
productivity, preparation and maintenance of detailed construction schedules for individual contracts of $50 Million and larger in constructed value.

a. Within seven days after the effective date of the Notice to Proceed, the CONTRACTOR shall submit the construction scheduler’s resume to the ENGINEER, including personal references from at least two owner- representatives familiar with the construction scheduler’s work on previous similar contracts. The ENGINEER reserves the right to reject the proposed scheduler based on poor references, lack of qualifications as defined in this Specification section, and/or poor performance history on previous OCSD contracts including late schedule submittals, lack of responsiveness to requested clarifications, corrections, re-submittals and/or time impact analysis.

b. The CONTRACTOR’s scheduler shall attend all meetings, including progress and special meetings pertaining to scheduling of the Work. The scheduler, along with the CONTRACTOR’s management team shall work closely with the ENGINEER to comply with and deliver the requirements of this Specification section.

c. It is the specific intent of this Specification section that the CONTRACTOR and its scheduler shall be wholly responsible for developing, maintaining, updating, checking and providing an accurate and comprehensive representation of the CONTRACTOR’s work plan in the required software, related databases and reports to achieve the purposes set forth in the Contract Documents.

1.8 ENGINEER’S REVIEW

A. The ENGINEER shall review schedule submittals in accordance with this Specification section and the other Contract Documents for the administrative purposes described herein. However the ENGINEER’s review, comments or consent to use the CONTRACTOR’s schedule shall not be construed as validation or endorsement of the CONTRACTOR’s work plan and approach nor shall it relieve the CONTRACTOR of any and all responsibility, liability or risk related to its work plan, its work plan as represented by the schedule, or requirements of the Contract.
1.9 GENERAL SCHEDULE REQUIREMENTS

A. The CONTRACTOR shall have sole responsibility for development, maintenance, update, revision, checking and presentation of its work plan in the form of a Critical Path Method (CPM) Construction Schedule for use by the ENGINEER in meeting the purposes described in the Contract Documents. The CONTRACTOR shall provide all information concerning methods, means, sequencing, logic, and duration of all activities as well as providing all CPM logic network diagram and tabular report data.

B. The CONTRACTOR shall use Primavera® P6 Professional Project Management, release 8.0, submit electronic files compatible with the required software and coordinate use of subsequent releases with OCSD to ensure data compatibility. The CONTRACTOR shall use a hardware system commensurate with the size of the contract, capable of handling, processing, printing, and plotting all data required to satisfy the requirements of this Section.. The system shall be capable of handling, processing, printing, and plotting all data required to satisfy the requirements of this Specification
section. Electronic files submitted to OCSD shall be compatible with Primavera® Project
Management, latest version.

C. Within fourteen days following the effective date of the Notice to Proceed, the ENGINEER shall schedule and conduct a Pre-Construction Scheduling Conference to commence development of the required construction schedules. At the meeting, the requirements of this and related Specification sections will be reviewed with the CONTRACTOR and the CONTRACTOR shall present its proposed:

1. Methodology for the CPM Construction Schedule, illustrating sequence of operations, cost, resource and quantity loading.

2. Work Breakdown Structure (WBS), Activity Coding Structure and Activity Identification numbering system for labeling all Work Activities, correlated with the Contract Agreement Schedule of Prices. At a minimum the CONTRACTOR shall provide the data detailed in Appendices B and C of this Specification section.

D. The ENGINEER shall review the WBS, the coding structure, and activity identification system presented by the CONTRACTOR within ten days following the Pre-Construction Scheduling Conference. The CONTRACTOR shall make all modifications requested by the ENGINEER and, following concurrence by the ENGINEER, shall employ the agreed to coding, structure, and system in its Construction Schedule. In addition the CONTRACTOR may be required to develop additional activity codes and values to comply with reporting requirements listed in the Contract Documents, and/or as directed by the ENGINEER.

E. The Work Activities comprising the Construction Schedule shall be of sufficient detail to assure adequate planning and execution of the Work such that, in the judgment of the ENGINEER, it provides an appropriate basis for predicting, monitoring, evaluating and recording the progress of the Work. Work Activities shall conform to the following requirements:

1. Describe Work Activities using consistent terminology such that the Work is readily identifiable for assessment of progress and completion.

2. Subdivide the Work into activities of duration no longer than fifteen uninterrupted work days each, except as to non-construction activities, such as procurement and delivery of materials and equipment, and any other activities for which the ENGINEER may accept a longer duration in writing.
3. The construction time, as determined by the schedule, from early start to late finish for any sub-phase, phase, or the entire contract shall not exceed the Contract Duration specified or shown in the Contract Documents. One day shall be the smallest time unit shown unless otherwise directed in writing by the ENGINEER.

4. Except as provided for in Appendix B for milestones, activities labeled "start," "continue," or "completion" shall not be allowed. Logic relationships between activities shall be limited to finish-to-start (FS) type relationships and the use of lags or durations between activities shall not be permitted unless accepted in writing by the ENGINEER.

5. The CONTRACTOR shall not constrain the schedule with artificial logic ties and/or constraint dates and/or use any other scheduling techniques that may distort the activity float and total float associated with the critical path activities and the schedule in general. The only allowable constraint shall be for Contract Milestone dates using a “Finish On or Before” constraint, unless accepted in writing by the ENGINEER.

6. Each Work Activity shall contain the following information as elaborated in
Appendix B of this Specification section:

a. WBS coding, activity coding and a unique activity identification number consistent with the structure and system agreed to by the ENGINEER.

b. Performance responsibility; General CONTRACTOR or Subcontractor trade code; GEN, MECH, ELEC, CARP, PLAST, etc.

c. Work location code and description of the physical plant area involved. d. Duration in work days based on the appropriate Activity Calendar.
e. Cost Data as mandated herein

f. Resource Data as mandated herein

F. The ENGINEER may require the CONTRACTOR, at any time during the Contract, to develop a more detailed schedule and/or fragnet than depicted in the Construction Schedule to clearly illustrate the effort needed to complete a specific area or task.

G. The Construction Schedule shall contain the following standard milestones; Notice to Proceed; Mobilization; Construction Start; Specified Contract Milestones for each phase of Work as identified in Contract Documents; Beneficial Occupancy; Substantial Completion and Final Completion

H. Activity Cost Loading:

1. The schedule shall incorporate cost-loaded activities equal to the Contract Total Price and Sub-Totals set forth in Contract Agreement ‘Exhibit “A” Schedule of Prices’ and as further detailed in the General Conditions section entitled ‘PAYMENT – ITEMIZED BREAKDOWN OF CONTRACT LUMP SUM PRICES’.

2. The CONTRACTOR shall further divide its prices to determine and substantiate a fair allocation of costs to each activity of Work in the schedule that is physically incorporated into the facility.
3. The CONTRACTOR shall not unbalance the activity cost loading and, except for mobilization costs, shall prorate overhead and profit on all activities for the entire contract term. The CONTRACTOR shall furnish the minimum data required in Appendix G of this Specification section to the ENGINEER for review and agreement prior to integrating cost data into the schedule:

4. Procurement, submittal preparation and submittal review activities shall not be cost-loaded. Payment for material and equipment shall be made in accordance with the Contract Documents.

5. The Payment Application and all periodic payment requests shall be based upon, but may not be limited to, the cost-loaded Construction Schedule update; the Contract Agreement ‘Exhibit “A” Schedule of Prices’; and the General Conditions section entitled ‘PAYMENT – ITEMIZED BREAKDOWN OF CONTRACT LUMP SUM PRICES’.

6. Proposed changes to the authorized Cost-loaded Construction Schedule may only be made with the written acceptance by the ENGINEER.

I. Activity Resource Loading:

1. The activities contained in the Construction Schedule shall be resource-loaded to show the number of work force employees needed on a work day basis to complete the Work within the Contract Duration.

2. Resource activity loading shall include, at a minimum, the composite crew, the classification (e.g., foreman, journeyman, etc.) of the individuals comprising the crew, materials, and equipment associated with each activity shown on the schedule, plus any other information required by ENGINEER.

3. Labor resources shall be listed in the Resource Library of the Primavera® Software and the CONTRACTOR shall assign labor resource loading by trade for each Work Activity of the schedule.

4. The CONTRACTOR may use the Primavera® Resource Leveling function for its own internal analysis and planning, but shall not use it in the contract record or submittal schedule databases to avoid potential distortions resulting from the retained logic function.

5. Proposed changes to the authorized Resource-loaded Schedule may only be made with the written acceptance by the ENGINEER.

J. The Construction Schedule shall begin with the date of issuance of the Notice to Proceed and not exceed the maximum Contract Duration provided in the Contract. It shall include, but not be limited to, the following items as appropriate to this Contract:

1. All administrative tasks

2. Type of work to be performed, sequences, and labor trades involved, including performance responsibility and trade code.

3. Quantity loading of activities showing, at a minimum, unit price bid items, estimated quantities to be installed or removed as indicated in the Contract Documents or as determined by the CONTRACTOR in preparation of its Bid, and any additional information required by the ENGINEER.
4. All manufacturer factory tests, material and equipment deliveries, field tests, readiness tests, and installation activities that the CONTRACTOR intends to seek payment for, including stored materials.

5. All submittal preparation and reviews including ENGINEER reviews, and acceptance of shop drawings and material samples shall provide a 25 day minimum duration as specified for the ENGINEER’s review of submittals, unless the submittal is of the type requiring a longer period of time as specified in the Contract Documents for Shop Drawing Submittals.

6. Delivery, installation, check-out/testing, and startup of OCSD-furnished equipment and/or materials in accordance with the schedule dates set forth in the Specifications or as furnished by the ENGINEER.

7. Approvals required by regulatory agencies or other third parties, including
CONTRACTOR obtained permits

8. Identification of all subcontract Work and assignments of responsibility for performing specific activities.

9. All temporary utilities and construction required by the CONTRACTOR to perform the Contract Work.

10. Access to and availability of work areas including all anticipated plant shutdowns, pump station shutdowns, flow diversions, or bypass pumping.

11. All interruptions, shut downs and connections to existing plant systems and equipment.

12. All start up, testing, training, and assistance required under the Contract
Documents.

13. Timing of the phased or total takeover of the Work by OCSD as may be required by the CONTRACT.

14. Identification of any work force, material, or equipment restrictions, as well as any activity requiring unusual shift work, such as two shifts, six day weeks, overtime, or work at times other than regular days or hours, shall be clearly identified in the Construction Schedule. Normal work hours are eight hours per day, five days a week, unless specified otherwise in the Contract Documents.

15. CONTRACTOR activities that will be coordinated with OCSD on-going activities.

16. Material and Equipment Installation including installation, check-out, Operations and Maintenance manuals submittal and acceptance, training lesson plan(s) submittal and acceptance, and OCSD staff training.

17. CONTRACTOR-prepared drawings and diagrams such as shoring diagrams.

18. Clearly identify all non-work days such as holidays, or other non-work periods in the schedule,
19. Specific Work Activities, including but not limited to, site work, underground piping and electrical ductbanks, structural excavation, soil testing, backfill, placement of sheeting, pile driving, formwork erection, rebar placement, placing of concrete, stripping forms, concrete curing, installation of process piping, electrical conduits and wiring, instrumentation and controls conduits and wiring, terminations, other materials and plant equipment, and cleanup.

20. The CONTRACTOR shall provide an activity for Inclement Weather with a duration that reflects the number of inclement weather days provided for in the Contract Documents as follows:

a. The Inclement Weather predecessor activity shall be the last construction activity that occurs before Substantial Completion.

b. The Inclement Weather successor activity shall be the Substantial
Completion milestone.

c. The CONTRACTOR shall notify the ENGINEER in writing within seven days when a lost work day has occurred due to inclement weather. The CONTRACTOR shall correspondingly reduce the inclement weather activity duration as weather days occur, are recognized and accepted by the ENGINEER.

d. The CONTRACTOR shall notify the ENGINEER in writing to request a non- compensable extension of time if the number of actual inclement weather delay days exceeds the number of inclement weather delay days identified in the Contract Documents. Such delays shall not entitle the CONTRACTOR to additional compensation.

21. Punchlists.

22. Final cleanup.

23. Specific information required by the ENGINEER.

24. Required inspections by the ENGINEER.

25. Progress period updating of Contract Record Drawings and final submittal of As- Built Drawings at contract completion, or as directed by the ENGINEER.

1.10 INTERIM CONSTRUCTION SCHEDULE REQUIREMENTS

A. Within 30 days following Notice to Proceed the CONTRACTOR shall submit its detailed written work plan for the first 150 days of operation and its general approach to the remainder of the Work. The work plan and approach to the remainder of the Work shall also be submitted in the form of an Interim Construction Schedule that incorporates all applicable elements of this Specification section and the other Contract Documents sufficient to meet its purpose.
B. The ENGINEER shall meet with the CONTRACTOR within ten days of the submittal to review and agree on any necessary adjustments and revisions. When revised and accepted by the ENGINEER the Interim Construction Schedule shall illustrate the CONTRACTOR’s methods, means, logic, sequencing and durations of the Work represented by cost-loaded and resource-loaded activities for the first 150 days of the contract. It shall also include cost loading and resource loading for the balance of all contract Work to a summary level through the Final Completion milestone as forecast by the CONTRACTOR.

C. The Interim Construction Schedule shall be updated as provided in this Specification section and used to monitor job progress during the first 150 days of the contract or until acceptance of the Baseline Construction Schedule by the ENGINEER.

1.11 BASELINE CONSTRUCTION SCHEDULE REQUIREMENTS

A. Within 90 days following Notice to Proceed the CONTRACTOR shall submit its detailed written plan for the Work. The work plan shall also be submitted in the form of a Baseline Construction Schedule that incorporates all applicable elements of this Specification section and the other Contract Documents sufficient to meet its purposes as described therein. It shall demonstrate the final level of detail for each activity, all required relationships completely identified, and the duration of each activity correctly depicted. It shall be developed as follows:

1. The activities shown in the interim schedule shall be integrated into the Baseline Construction Schedule without change to form a comprehensive representation of the CONTRACTOR’s execution of the Work from start to finish.

2. The Baseline Construction Schedule submitted for review and acceptance by the ENGINEER shall be un-statused and the data date shall be the Contract Notice to Proceed date.

3. The Baseline Construction Schedule shall clearly indicate the Longest Critical
Path of activities from Notice to Proceed to the Contract Completion date.

4. The Baseline Construction Schedule shall contain all cost information assigned to each discrete activity at the final level of detail. Each activity shall be cost-loaded to permit generation of cash flow curves

5. The Baseline Construction Schedule shall contain all resource information assigned to each discrete activity at the final level of detail. Each activity shall be resource-loaded to permit generation of resource curves.

6. The CONTRACTOR shall collect data and information from Subcontractors, suppliers, and equipment manufacturers for incorporation into the Baseline Construction Schedule. The baseline schedule submittal shall include signed certification letters from Subcontractors, suppliers and vendors that they have reviewed, discussed and agreed to the schedule as it relates to their work.

7. The Baseline Construction Schedule shall contain no Contract changes or delays which may have been incurred during the schedule development period. These changes will be entered at the first update after the Baseline Construction Schedule has been accepted by the ENGINEER and a change to the Contract Duration made as part of an approved Change Order in accordance with the Contract Documents.
8. Once the Baseline Construction Schedule is agreed to and accepted by the ENGINEER it shall become the schedule of record and shall be the basis for future schedule updates.

9. After adoption of the Baseline Construction Schedule, no changes shall be made therein, including changes to logic, sequence and/or duration, without the agreement of the ENGINEER.

B. The ENGINEER will have up to 25 days to evaluate and prepare its comments to the Baseline Construction Schedule submittal before scheduling a meeting with the CONTRACTOR to discuss it.

C. Within ten days of returning its submittal response, the ENGINEER will schedule a meeting with the CONTRACTOR to review and discuss any adjustments and revisions to the Baseline Construction Schedule required to make it acceptable to the ENGINEER.

D. After acceptance by the ENGINEER, the Baseline Construction Schedule shall represent the CONTRACTOR’s methods, means, logic, sequencing and durations of the Work and include the CONTRACTOR’s estimated costs and resources for each discrete activity as required to meet the purposes of this Specification section and the other Contract Documents.

1.12 PROGRESS OF THE WORK

A. Once the Baseline Construction Schedule is adopted the CONTRACTOR shall be responsible for preparing and submitting periodic progress update information in the form of a progress report concurrent with the Progress Payment Application cycle established for the contract. At a minimum the progress report and schedule update shall include:

1. Narrative Progress Report

2. Updated Construction Schedule

3. Reports, tables and diagrams ad described in Appendix G of this Specification section.

B. On a date determined by the ENGINEER, the CONTRACTOR shall meet with the ENGINEER to review the CONTRACTOR’s Progress Payment Application and its required supporting documents, including its Narrative Progress Report and its Construction Schedule Update.

1. Appendix E of this Specification section outlines the update preparation and review sequence to be used for preparation, submittal and review of the Narrative Progress Report and Construction Schedule update.

2. The CONTRACTOR and the ENGINEER will review the Draft submittal, discuss its content and the ENGINEER will authorize modifications, as appropriate, to facilitate approval of the Payment Application.

3. Following the review meeting, only those revisions authorization by the ENGINEER shall be incorporated into the electronic file entitled “Update” which shall then be submitted as the record schedule for the progress period update.
4. The ENGINEER shall be allowed seven days after the meeting to review and determine the acceptability of the Narrative Progress Report and Construction Schedule update. This variance from the typical submittal review period is made specifically to facilitate timely processing of the CONTRACTOR’s Progress Payment Application.

5. Narrative Progress Report and Construction Schedule updates returned to the CONTRACTOR marked “Revise & Resubmit” or “Not Acceptable” shall constitute a deficient payment application that will not be processed for payment until the schedule report is acceptable to the ENGINEER.

6. Narrative Progress Report and Construction Schedule updates returned to the CONTRACTOR marked “Revise & Resubmit” or “Not Acceptable” shall be resubmitted to the ENGINEER within seven days, at which time a new seven day review period will begin for the ENGINEER.

C. The Narrative Progress Report shall summarize the schedule status and be organized as follows:

1. The CONTRACTOR's transmittal letter, containing the submittal number.

2. Contents Sheet

3. Identification of the Update including the Data Date, Update Period and the
Schedule File Names as defined in Appendix D to this Specification section.

4. Update Summary including the variance between Contract Milestone dates and their predicted completion dates; Contract Completion variance for the reporting period; the number of days ahead or behind schedule; weather days taken and remaining from the Contract allowance and tables summarizing the status of Contract finances and time. At a minimum the CONTRACTOR shall provide the data required by the example in Appendix G of this Specification section.

5. Analysis of Critical Path and each negative Float Path describing the nature of the Critical Path, its impact and the impact of any negative float path on other activities, milestones and completion dates:

6. All current and anticipated time impacts describing the origin of each event; corrective action and schedule adjustments to correct it; recommendations to recover from it and the effect that it may have on other activities, milestones and completion dates.

7. Pending status of outstanding issues such as permits, if any; Contract modifications, RFC’s and or RFP’s containing requests for time adjustment; long-lead procurement items; safety reports and any code violations or warnings.

8. Narrative discussion of contract status including highlights of work by area, progress, completion, impediments, changes to the Work plan, issues and concerns accompanied by OCSD Activities and Schedule Change Tables. At a minimum the CONTRACTOR shall provide the data required in Appendix G of this Specification section.

D. Progress Period Schedule Updates:

1. The CONTRACTOR shall be responsible for preparing and submitting updated schedules, related reports and diagrams, as part of its periodic update Report.
2. The Construction Schedule update shall measure and record only those facts that have occurred to the Work including physical percent complete type, actual start and finish dates, and duration changes. Modifications to logic, durations of activities not started or to actual dates already recorded in previous updates shall not be allowed unless authorized in writing by the ENGINEER. An electronic file shall be created and entitled “Pure Progress” and included with the update.

3. With each update the CONTRACTOR shall identify any changes to the schedule, such as Field Change Orders, accepted time adjustment requests, new activities, constraint changes, deleted activities, activity duration changes, activity description changes, and changes in logic relationships between activities in a Schedule Change Table as detailed in Appendix G of this Specification section. Logic changes shall be described with an explanation of the rationale for the change provided in the report. Such revisions may be incorporated into an electronic file entitled “Draft Update” for target comparison with the “Pure Progress” update. The CONTRACTOR shall provide printed diagrams of the target comparisons as part of its presentation to the review meeting.

4. All progress period schedule updates shall be compared to the Baseline Construction Schedule. In addition, each current progress period update shall be compared to the previous period update. Each update shall be labeled with the OCSD project number, data date and title abbreviation identified on the hard copy and electronic file as described in Appendix G of this Specification section.

5. The schedule shall be updated with actual start and finish dates for every in- progress or completed activity, as documented by the CONTRACTOR’s Daily Reports and Three Week Look Ahead schedules. No other basis, including automated software calculations or default mechanisms shall be allowed. Failure of the CONTRACTOR to ensure that documented dates as specified herein are incorporated into the schedule update shall constitute cause for disapproval of the update and the inability of the ENGINEER to accurately evaluate the CONTRACTOR’s progress for payment purposes.

6. Activities that have reported progress without predecessor activities being completed such as Finish to Start (FS) Relationships with out of sequence progress will not be allowed except on a case-by-case basis with the written acceptance by the ENGINEER. A written explanation of each such activity shall be included with each update in the Schedule Change Table as detailed in Appendix G of this Specification section. The ENGINEER may direct that changes in schedule logic be made to correct any or all out-of-sequence Work.

7. Change order work shall be identified in the schedule as a new activity inserted into the affected schedule logic. The schedule activity shall only be added after the Change Order is approved for payment by OCSD.

1.13 CONSTRUCTION SCHEDULE REVISION

A. If the CONTRACTOR decides to make major changes to the sequencing and logic of the accepted work plan it shall prepare a schedule reflecting its proposed changes for submittal to, and review by, the ENGINEER separate and apart from the periodic schedule updates.

B. The CONTRACTOR’s submittal shall be made in accordance with the requirements of the Contract Documents and the ENGINEER will have a maximum 25 day period for review before scheduling a meeting with the CONTRACTOR.
C. A Revised Schedule that results in a predicted completion date later than the Contract Completion date shall be rejected unless the delay is deemed to be excusable or caused by OCSD and a time extension is authorized in writing by the ENGINEER.

D. The ENGINEER will then arrange a meeting with the CONTRACTOR to review the submittal, discuss its content, and authorize modifications required to allow its integration into the Construction Schedule.

1.14 AS-BUILT CONSTRUCTION SCHEDULE

A. As a condition precedent to release of any retention, the CONTRACTOR shall submit its As-Built Construction Schedule. The As-Built Construction Schedule shall reflect the manner in which the contract was actually constructed including start and completion dates, and all activities, sequences, and logic ties.

B. This schedule submission shall be accompanied by a certification, signed by an officer of the CONTRACTOR’s company, the CONTRACTOR’s Project Manager and Construction Scheduler, stating “To the best of our knowledge, the accompanying As- Built Construction Schedule accurately reflects the actual start and completion dates and logical relationships of all activities contained herein and represents an accurate depiction of the way in which the contract was constructed.”

1.15 WEEKLY THREE WEEK LOOK AHEAD

A. The CONTRACTOR shall submit an electronic copy of the Three Week Look Ahead schedule to the ENGINEER no later than 48 hours prior to the weekly construction progress meeting. The Three Week Look Ahead schedule shall be developed maintained and provided using MS Excel® software, shall be in the form shown in Appendix G and
include at a minimum actual performance for the previous week compared to the planned work for the previous week, planned work for the current week and planned work for the two weeks following the current week.

B. Each weekly Three Week Look Ahead schedule shall be based on the current Construction Schedule update Four Week Look Ahead Report and fully correlated to the activities planned in its Primavera® counterpart, including submittal reviews, procurement, fabrication and delivery of contract deliverables.

C. The CONTRACTOR shall use the Three Week Look Ahead schedule actual performance record in preparing its Construction Schedule update.

1.16 FLOAT OWNERSHIP AND EARLY COMPLETION

A. Total float, free float, independent float, near-critical float, critical path float, slack time, or contingency within the overall Construction Schedule is not for the exclusive use of either OCSD or the CONTRACTOR but is jointly owned by both and is an expiring resource available to and shared by both as needed to meet Contract Milestones and the Contract Completion date.

B. Pursuant to the float sharing requirements of the Contract, use of float suppression techniques such as preferential sequencing, special lead/lag logic restraints, extended activity times, or imposed dates shall be cause for rejection of the Construction Schedule and any revisions or updates thereto.
C. Within fifteen days of Contract award, the CONTRACTOR shall formally notify OCSD in writing of its intent to finish the Work earlier than the Contract Completion date. Agreement between the ENGINEER and the CONTRACTOR to adopt an early completion Baseline Construction Schedule shall include agreement by both parties to amend the Contract Milestones, completion dates, and associated liquidated damages, by Change Order, to those completion dates contained in the agreed to schedule.

1.17 TIME ADJUSTMENT REQUESTS

A. Requests for time adjustments shall be submitted in the time and manner specified in the Contract Documents, as described herein and further elaborated in Appendix F of this Specification section.

B. OCSD initiated changes that extend or shorten the Contract Duration shall be the sole basis to adjust the Contract Completion date. Delays in the critical path not associated with proper requests for time extensions in accordance with the Contract Documents shall be deemed to be the responsibility of the CONTRACTOR.

1.18 REMEDIAL MEASURES AND RECOVERY SCHEDULE

A. The CONTRACTOR shall mitigate any potential delay to the Work as efficiently and economically as possible regardless of cause. Where practical the CONTRACTOR shall do so without added cost or adverse time impact. Prior to initiating any action for which it expects OCSD to be liable, the CONTRACTOR shall notify the ENGINEER in writing and receive written authorization to proceed.

B. If the CONTRACTOR believes the delay may result in a predicted completion date later than the Contract Completion date, it shall review all uncompleted activities on the critical and near critical paths to assess mitigation options and, within seven days of discovering the potential delay it shall submit a written statement to the ENGINEER describing its plan to recover, including a statement that it has verified the accuracy of all critical and near critical paths. Following acceptance by the ENGINEER the CONTRACTOR shall incorporate its recovery plan into the next schedule update.

C. Whenever it becomes apparent to the ENGINEER that the current schedule update shows a delay to the critical path, that these delays are through no fault of OCSD and hence, the Contract completion date will not be met, or when so directed by the ENGINEER, the CONTRACTOR shall submit to the ENGINEER for review a written statement of the steps it intends to take to remove or arrest the delay to the schedule and the CONTRACTOR shall promptly provide the requisite level of effort to bring the Work back on schedule. The CONTRACTOR shall then incorporate its recovery plan into the next Construction Schedule update.

D. A Recovery Schedule that results in a predicted completion date later than the Contract Completion date shall be rejected unless the ENGINEER determines that the delay is the responsibility of OCSD, is excusable or that it cannot be mitigated, and authorizes a time extension in writing.

E. The ENGINEER may require the CONTRACTOR to provide reasonable additional resources to recover from any schedule delay, however under no circumstances will the addition of equipment or construction forces, increasing the working hours or any other method, manner, or procedure to recover from delays to the Schedule be considered justification for contract modification for extra Work.
PART 2 - PRODUCTS (NOT USED) PART 3 - EXECUTION
3.1 SUPPLEMENTS

A. The supplements listed below are attached to and form a part of this Specification section:

Appendix A - Definitions

Appendix B - Work Breakdown and Activity Coding Structure

Appendix C - Activity ID System Appendix D - Electronic File Naming Appendix E - Update Preparation Sequence Appendix F - Time Adjustment Request Appendix G - Contractor Deliverables



No comments:

Post a Comment