Saturday, November 2, 2013

SECTION 03300 CAST-IN-PLACE CONCRETE


SECTION 03300

CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 THE REQUIREMENT

A. The CONTRACTOR shall furnish all materials for cast-in-place concrete in accordance with the provisions of this Section and shall form, mix, place, cure, repair, finish, and do all other work as required to produce finished concrete, in accordance with the requirements of the Contract Documents.

B. Unless specifically indicated otherwise in the Contract Documents, all concrete work, including steel reinforcing, shall be in accordance with the best standard practices as set forth in the ACI Building Code, Manuals and Recommended Practices.

1.2 RELATED WORK SPECIFIED ELSEWHERE

A. The requirements of the following Specification sections and divisions apply to the Work of this section. Other sections and divisions of the Specifications, not referenced below, shall also apply to the extent required for proper performance of this Work.

1. Section 03071, Epoxies

2. Section 03100, Concrete Formwork

3. Section 03123, Controlled Density Concrete

4. Section 03200 Reinforcement Steel

5. Section 03290, Joints in Concrete

6. Section 03350 Concrete Testing

7. Section 03366, Tooled Concrete Finishes

8. Section 03600, Grouts

9. Section 07130, Concrete Sealer and Hardener

10. Section 07900, Joint Sealants

1.3 REFERENCE SPECIFICATIONS, CODES, AND STANDARDS

A. All Work specified herein shall conform to or exceed the applicable requirements of the referenced portions of the following publications to the extent that the provisions thereof are not in conflict with other provisions of these Specifications.
B. Comply with the applicable editions of the following codes, regulations and standards.

1. Industry Standards:

American Concrete Institute (ACI):

318 Building Code Requirements for Structural Concrete

350 Building Code Requirements for Environmental Concrete
Structures Manual of Concrete Practice Recommended Practices
ASTM International (ASTM):

C 31 Practice for Making and Curing Concrete Test Specimens in the
Field

C 33 Specification for Concrete Aggregates

C 39 Test Method for Compressive Strength of Cylindrical Concrete
Specimens

C 40 Test Method for Organic Impurities in Fine Aggregates for
Concrete

C 42 Method of Obtaining and Testing Drilled Cores and Sawed
Beams of Concrete

C 88 Test Method of Soundness of Aggregates by Use of Sodium
Sulfate or Magnesium Sulfate

C 94 Specification for Ready-Mixed Concrete

C 114 Test Methods for Chemical Analysis of Hydraulic Cement

C 131 Test Method for Resistance to Degradation of Small-Size Coarse
Aggregate by Abrasion and Impact in the Los Angeles Machine C 136 Test Method for Sieve Analysis of Fine and Coarse Aggregates C 143 Test Method for Slump of Hydraulic Cement Concrete
C 150 Specification for Portland Cement

C 157 Test Method for Length Change of Hardened Hydraulic-Cement
Mortar and Concrete.

C 172 Practice for Sampling Freshly Mixed Concrete

C 173 Test Method for Air Content of Freshly Mixed Concrete by the
Volumetric Method
C 203 Test Methods for Breaking Load and Flexural Properties of
Block-Type Thermal Insulation

C 227 Test Method for Potential Alkali Reactivity of Cement-Aggregate
Combinations (Mortar-Bar Method)

C 260 Specification for Air-Entraining Admixtures for Concrete

C 289 Test Method for Potential Alkali-Silica Reactivity of Aggregates
(Chemical Method)

C 309 Specification for Liquid Membrane-Forming Compounds for
Curing Concrete

C 311 Test Methods for Sampling and Testing Fly Ash or Natural
Pozzolans for Use in Portland-Cement Concrete

C 469 Test Method for Static Modulus of Elasticity and Poisson's Ratio of Concrete in Compression

C 494 Specification for Chemical Admixtures for Concrete

C 595M Specification for Blended Hydraulic Cements

C 618 Specification for Coal Fly Ash and Raw or Calcined Natural
Pozzolan for Use in Concrete

D 75 Practice for Sampling Aggregates

1.4 DEFINITIONS

A. Alkali: Is defined to mean sum of sodium oxide and potassium oxide calculated as sodium oxide.

B. Hairline Crack: Crack with a crack width of less than 4 thousandths of an inch.

1.5 SYSTEM DESCRIPTION

A. Performance Requirements:

1. General:

a. Except as otherwise specified, provide concrete composed of portland cement, fine aggregate, coarse aggregate, and water so proportioned and mixed as to produce plastic, workable mixture in accordance with requirements as specified in this Section and suitable to specific conditions of placement.

b. Proportion materials in manner such as to secure lowest water-cement ratio which is consistent with good workability, plastic, cohesive mixture, and one which is within specified slump range.

c. Proportion fine and coarse aggregate in manner such as not to produce harshness in placing nor honeycombing in structures.
2. Watertightness of Concrete Work: It is intent of this Section to secure for every part of the Work concrete and grout of homogeneous structure, which when hardened will have required strength, watertightness, and durability.

a. It is recognized that some surface hairline cracks and crazing will develop in the concrete surfaces.

b. Construction, contraction, and expansion joints have been positioned in structures as indicated on the Drawings, and curing methods specified, for purpose of reducing number and size of these expected cracks, due to normal expansion and contraction expected from specified concrete mixes.

c. Class A, Class B, and Class D Concrete: Watertight: Repair cracks which develop in walls or slabs and repair cracks which show any signs of leakage until all leakage is stopped.

d. Pressure inject visible cracks, other than hairline cracks and crazing, in following areas with epoxy as specified in Section 03931, Epoxy Injection System.

1) Floors and walls of water bearing structures.

2) Walls and overhead slabs of passageways or occupied spaces, outsides of which are exposed to weather or may be washed down and are not specified to receive separate waterproof membrane.

3) Other Items Not Specified to Receive Separate Waterproof Membrane: Slabs over water channels, wet wells, reservoirs, and other similar surfaces.

e. Walls or slabs, as specified above, that leak or sweat because of porosity or cracks too small for successful pressure grouting: Seal on water or weather side by coatings of surface sealant system, as specified in this Section.

f. Grouting and Sealing: Continue as specified above until structure is watertight and remains watertight for not less than one year after final acceptance or date of final repair, whichever occurs later in time.

3. Workmanship and Methods: Provide concrete work, including detailing of reinforcing, conforming with best standard practices and as set forth in ACI 318, Manuals, and Recommended Practices.

1.6 SUBMITTALS

A. Submittals shall be made in accordance with the General Requirements, Additional
General Requirements and as specified herein.

B. Product Data: Submit data completely describing products.

C. Information on Heating Equipment to Be Used for Cold Weather Concreting: Submit information on type of equipment to be used for heating materials and/or new concrete in process of curing during excessively cold weather.
D. For conditions that promote rapid drying of freshly placed concrete such as low Humidity, high temperature, and wind: Submit corrective measures proposed for use prior to placing concrete.

E. Copies of Tests of Concrete Aggregates: Submit certified copies in triplicate of commercial laboratory tests of all samples of concrete aggregates.

1. Fine Aggregate: a. Clay lumps. b. Reactivity.
c. Shale and chert. d. Soundness.
e. Color.

f. Decantation.

2. Coarse Aggregate:

a. Clay lumps and friable particles. b. Reactivity.
c. Shale and chert. d. Soundness.
e. Abrasion loss.

f. Coal and ignite.

g. Materials finer than 200 sieve.

F. Sieve Analysis: Submit sieve analyses of fine and coarse aggregates being used in triplicate at least every 3 weeks and at any time there is significant change in grading of materials.

G. Concrete Mixes: Submit full details, including mix design calculations for concrete mixes proposed for use for each class of concrete.

1. Include information on correction of batching for varying moisture contents of fine aggregate.

2. Submit source quality test records with mix design submittal.

a. Include calculations for f'cr based on source quality test records.

H. If there is change in aggregate source, or aggregate quality from same source, submit new set of design mixes covering each class of concrete.
I. Test Batch Test Data:

1. Submit data for each test cylinder.

2. Submit data that identifies mix and slump for each test cylinder.

J. Sequence of Concrete Placing: Submit proposed sequence of placing concrete showing proposed beginning and ending of individual placements.

K. Curing Compound Other than Specified Compound: Submit complete data on proposed compound.

L. Repair of Defective Concrete: Submit mix design for grout.

M. Acceptance of Method of Concrete Repair: Make no repair until the ENGINEER has accepted method of preparing surfaces and proposed method of repair.

N. If either fine or coarse aggregate is batched from more than one bin, submit analyses for each bin, and composite analysis made up from these, using proportions of materials to be used in mix.

O. Cement Mill Tests: Include alkali content, representative of each shipment of cement for verification of compliance with specified requirements.

P. Pozzolan Certificate of Compliance: Identify source of pozzolan and certify compliance with requirements of ASTM C 618.

Q. Information on mixing equipment. R. Drying shrinkage test data.
1.7 DELIVERY, STORAGE, AND HANDLING A. Packing and Shipping:
1. Deliver, store, and handle concrete materials in manner as to prevent damage and inclusion of foreign substances.

2. Deliver and store packaged materials in original containers until ready for use.

3. Deliver aggregate to mixing site and handle in such manner that variations in moisture content will not interfere with steady production of concrete of specified degree of uniformity and slump.

B. Acceptance at Site: Reject material containers or materials showing evidence of water or other damage.
1.8 PROJECT CONDITIONS

A. Environmental Requirements:

1. Hot Weather Concreting:

a. When Ambient Air Temperature Is above 90 degrees F: Prior to placing concrete, cool forms and reinforcing steel to by water cooling to below
90 degrees F.

b. Temperature of Concrete Mix at Time of Placement: Keep temperature below 90 degrees F by methods which do not impair quality of concrete.

2. Cold Weather Concreting:

a. Concrete placed below ambient air temperature of 45 degrees F and falling or below 40 degrees F, make provision for heating water.

b. If materials have been exposed to freezing temperatures to degree that any material is below 35 degrees F, heat such materials.

c. Heating Water, Cement, or Aggregate Materials:

1) Do not heat in excess of 160 degrees F.

2) Protection of Concrete in Forms:

3) Protect by means of covering with tarpaulins, or other acceptable covering.

4) Provide means for circulating warm moist air around forms in manner to maintain temperature of 50 degrees F for at least 5 days.

3. For conditions that promote rapid drying of freshly placed concrete such as low humidity, high temperature, and wind, take corrective measures to minimize rapid water loss from concrete.

a. Furnish and use sufficient number of maximum and minimum self-recording thermometers to adequately measure temperature around concrete.

1.9 SEQUENCING AND SCHEDULING

A. Schedule placing of concrete in such manner as to complete any single placing operation to construction, contraction, or expansion joint.
PART 2 - PRODUCTS

2.1 MATERIALS

A. Aggregate:

1. General:

a. Provide concrete aggregates that are sound, uniformly graded, and free of deleterious material in excess of allowable amounts specified.

b. Grade aggregate in accordance with ASTM D 75 and C 136.

c. Provide unit weight of fine and coarse aggregate which produces in place concrete with weight of not less than 140 pounds per cubic foot.

B. Fine Aggregate:

1. Provide fine aggregate for concrete or mortar consisting of clean, natural sand or of sand prepared from crushed stone or crushed gravel.

2. Do not provide aggregate having deleterious substances in excess of following percentages by weight of contaminating substances. In no case shall total exceed percent listed.

Item
Test Method
Percent
Removed by decantation (dirt, silt, etc.)
ASTM C 117
3
Shale or Chert
ASTM C 295
1
Clay Lumps
ASTM C 142
1

3. Except as otherwise specified, grade fine aggregate from coarse to fine in accordance with requirements of ASTM C 33.

C. Coarse Aggregate:

1. General: Provide coarse aggregate consisting of gravel or crushed stone made up of clean, hard, durable particles free from calcareous coatings, organic matter, or other foreign substances.

2. Weight: Not exceeding 15 percent, for thin or elongated pieces having length greater than 5 times average thickness.

3. Deleterious Substances: Not in excess of following percentages by weight, and in no case having total of all deleterious substances exceeding 2 percent.

Item
Test Method
Percent
Shale or chert
ASTM C 295
1
Coal and lignite
ASTM C 123
1/4
Clay lumps and friable particles
ASTM C 142
1/4
Materials finer than Number 200 sieve
ASTM C 117
1/2*
*Except when material finer than Number 200 sieve consists of crusher
dust, maximum amount shall be 1 percent.
4. Grading:

a. Aggregate: As specified in ASTM C 33, Size Number 57, except as otherwise specified or authorized in writing by the ENGINEER.

b. Aggregate for Class CE Concrete for Encasement of Electrical Conduits: (1) Graded as specified in ASTM C 33, Size Number 8.
(2) Provide concrete utilizing this aggregate equal to Class C concrete in all other respects, and is designated as Class CE.

D. Portland Cement:

1. General: Conform to specifications and tests for ASTM C 150, Types II, III, sulfate resisting Type V, Low Alkali, except as specified otherwise.

2. Low Alkali Portland: Have total alkali containing not more than 0.60 percent.

3. Exposed Concrete in Any Individual Structure: Use only one brand of portland cement.

4. Cement for Finishes: Provide cement from same source and of same type as concrete to be finished.

E. Admixtures:

1. General:

a. Do not use admixtures of any type, except as specified, unless written authorization has been obtained from the ENGINEER.

b. Compatible with concrete and other admixtures.

c. Do not use admixtures containing chlorides calculated as chloride ion in excess of 0.5 percent by weight.

d. Use in accordance with manufacturer's recommendations and add each admixture to concrete mix separately.

2. Air Entraining Admixture:

a. Provide all concrete with 5 percent, plus or minus 1 percent, entrained air of evenly dispersed air bubbles at time of placement.

b. Conform to ASTM C 260.

3. Fly Ash Pozzolan Admixture:

a. Pozzolan:

(1) Conforming to requirements of ASTM C 618, Class F, may be used as admixture in concrete made with Type II Portland cement.
(2) Pozzolan may replace portland cement at ratio of 1.0 pound fly ash for each pound of portland cement replaced.

(3) Maximum of 15 percent by weight of minimum quantities of portland cement listed in Table A under paragraph 2.03E may be replaced with pozzolan.

(4) Do not use pozzolan as an admixture in concrete made with portland- pozzolan cement.

b. Loss on Ignition for Pozzolan: Not exceed four percent.

4. Water Reducing Admixture:

a. May be used at the CONTRACTOR's option. b. Conform to ASTM C 494, Type A or Type D. c. Not contain air entraining agents.
d. Liquid form before adding to the concrete mix.

e. No decrease in cement is permitted as result of use of water reducing admixture.

5. Superplasticizers: Are not to be used without acceptance by ENGINEER.

F. Water:

1. Water for Concrete, Washing Aggregate, and Curing Concrete: Clean and free from oil and deleterious amounts of alkali, acid, organic matter, or other substances.

2. Chlorides and Sulfate Ions:

a. Water for Conventional Reinforced Concrete: Use water not containing more than 1,000 milligrams per liter of chlorides calculated as chloride ion, nor more than 1,000 milligrams per liter of sulfates calculated as sulfate ion.

b. Water for Prestressed or Post-tensioned Concrete: Use water not containing more than 650 milligrams per liter of chlorides calculated as chloride ion, nor more than 800 milligrams per liter of sulfates calculated as sulfate ion.

G. Nonslip Abrasive:

1. Type: Aluminum oxide abrasive of size 8/16, having structure of hard aggregate, homogenous, nonglazing, rustproof, and unaffected by freezing, moisture, or cleaning compounds.

2. Manufacturers: One of the following, Or Equal:

a. Exolon Company, Tonawanda, New York.

b. Abrasive Materials, Incorporated, Hillsdale, Michigan.
H. Concrete Sealer:

1. Manufacturers: One of the following, Or Equal:

a. Hillyard Chemical Company, St. Joseph, Missouri, SEAL 341.

b. A. C. Horn, Inc., Horn Clear Seal EM-180. I. Conduit Encasement Coloring Agent:
1. Color: Red color concrete used for encasement of electrical ducts, conduits, similar type items.

2. Manufacturers: One of the following, Or Equal.

a. Frank D. Davis Company, Red Oxide Number 1117.

b. I. Reiss Company, Inc., equivalent product.

J. Keyway Material: Steel, plastic, or lumber.

K. Sprayed Membrane Curing Compound: Clear type with fugitive dye conforming to
ASTM C 309, Type 1D.

L. Surface Sealant System: Manufacturers: One of the following, Or Equal:

1. Radcon Laboratories, Inc., Las Vegas, Nevada, Formula Number 7.

2. IPA Systems, Philadelphia, Pennsylvania, Duripal.

2.2 EQUIPMENT

A. Mixing Concrete:

1. Mixers may be of stationary plant, paver, or truck mixer type.

2. Provide adequate equipment and facilities for accurate measurement and control of materials and for readily changing proportions of material.

3. Mixing Equipment:

a. Capable of combining aggregates, cement, and water within specified time into thoroughly mixed and uniform mass and of discharging mixture without segregation.

b. Maintain concrete mixing plant and equipment in good working order and operated at loads, speeds, and timing recommended by manufacturer or as specified.

c. Proportion cement and aggregate by weight. B. Machine Mixing:
1. Batch plant shall be capable of controlling delivery of all material to mixer within
1 percent by weight of individual material.
2. If bulk cement is used, weigh it on separate visible scale which will accurately register scale load at any stage of weighing operation from zero to full capacity.

3. Prevent cement from coming into contact with aggregate or with water until materials are in mixer ready for complete mixing with all mixing water.

4. Procedure of mixing cement with sand or with sand and coarse aggregate for delivery to project site, for final mixing and addition of mixing water will not be permitted.

5. Retempering of concrete will not be permitted.

6. Discharge entire batch before recharging.

7. Volume of Mixed Material Per Batch: Not exceed manufacturer's rated capacity of mixer.

8. Mixers:

a. Perform mixing in batch mixers of acceptable type.

b. Equip each mixer with device for accurately measuring and indicating quantity of water entering concrete, and operating mechanism such that leakage will not occur when valves are closed.

c. Equip each mixer with device for automatically measuring, indicating, and controlling time required for mixing.

(1) Interlock device to prevent discharge of concrete from mixer before expiration of mixing period.

C. Transit-mixed Concrete:

1. Mix and deliver in accordance with ASTM C 94.

2. Total Elapsed Time Between Addition of Water at Batch Plant and Discharging Completed Mix: Not to exceed 90 minutes or elapsed time at project site shall not exceed 30 minutes.

3. Under conditions contributing to quick setting, total elapsed time permitted may be reduced by the ENGINEER.

4. Equip each truck mixer with device interlocked so as to prevent discharge of concrete from drum before required number of turns and furnish such device that is capable of counting number of revolutions of drum.

5. Continuously revolve drum after it is once started until it has completely discharged its batch.

a. Do not admit water until drum has started revolving.

b. Right is reserved to increase required minimum number of revolutions or to decrease designated maximum number of revolutions allowed, if necessary, to obtain satisfactory mixing. The CONTRACTOR will not be entitled to additional compensation because of such increase or decrease.
D. Other Types of Mixers:

1. In Case of Other Types of Mixers, Mixing Shall Be as Follows:

a. Mix concrete until there is uniform distribution of materials, and discharge mixer completely before recharging.

b. Neither speed nor volume loading of mixer shall exceed manufacturer's recommendations.

c. Continue mixing for minimum of 1-1/2 minutes after all materials are in drum, and for batches larger than one cubic yard increase minimum mixing time
15 seconds for each additional cubic yard or fraction thereof.

2.3 MIXES

A. Measurements of Materials:

1. Measure materials by weighing, except as otherwise specified or where other methods are specifically authorized in writing by the ENGINEER.

2. Furnish apparatus for weighing aggregates and cement that is suitably designed and constructed for this purpose.

3. Accuracy of Weighing Devices: Furnish devices that have capability of providing successive quantities of individual material that can be measured to within one percent of desired amount of that material.

4. Measuring or Weighing Devices: Subject to review by the ENGINEER, and bear valid seal of the Sealer of Weights and Measures having jurisdiction.

5. Weighing Cement:

a. Weigh cement separately.
b. Cement in Unbroken Standard Packages (Sacks): Need not be weighed. c. Bulk Cement and Fractional Packages: Weigh such cement.

6. Mixing Water: Measured by volume or by weight.

B. Concrete Proportions and Consistency:

1. Concrete Consistency and Composition:

a. Provide concrete that can be worked readily into corners and angles of forms and around reinforcement without excessive vibration and without permitting materials to segregate or free water to collect on surface.

b. Prevent unnecessary or haphazard changes in consistency of concrete.

2. Ratio of Coarse Aggregate to Fine Aggregate: Not less than 1.0 nor more than
2.0 for all concrete Classes, with exception of Class CE.
3. Aggregate:

a. Obtain aggregate from source which is capable of providing uniform quality, moisture content, and grading during any single day's operation.

4. Concrete Mix Water to Cement Ratio, Minimum Cement Content, and Slump
Range: Conform to values specified in Table A in this section.

5. Concrete Batch Weights: Control and adjust so as to secure maximum yield, and at all times maintain proportions of concrete mix within specified limits.

6. Mixture Modification: If required, by the ENGINEER, modify mixture within limits set forth in this section.

C. Concrete Mixes:

1. Proportioning of Concrete Mix: Proportion mixes on required average on compressive strength f'cr as defined in Subparagraph 2.4A2.

2. Mixes:

a. Adjusting of Water: After acceptance, do not change mixes without acceptance by ENGINEER, except that at all times adjust batching of water to compensate for free moisture content of fine aggregate.

b. Total Water Content of Each Concrete Class: Not exceed those specified in
Table A in this section.

c. Checking Moisture Content of Fine Aggregate: Furnish satisfactory means at batching plant for checking moisture content of fine aggregate.

3. Change in Mixes: Undertake new trial batch and test program as specified in this section.

D. Hand Mixed Concrete:

1. Hand mix concrete only when acceptable to the ENGINEER.

2. Prepare hand mixed concrete on watertight, level platform in batches not to exceed 1/3 cubic yard each.

3. Aggregate:

a. First spread required amount of coarse aggregate on platform in an even and uniform layer, and then over such aggregate spread proper proportion of fine aggregate.

b. Combined Depth of Both Such Layers: Not be greater than one foot.

4. Cement:

a. First evenly spread required quantity of cement over fine aggregate.

b. Then turn entire batch with shovels at least twice before adding water.
5. Water:

a. Then uniformly sprinkle or spray proper amount of water over batched materials.

b. Then turn with shovels not less than three times before being removing from platform.

E. Classes of Concrete:

1. Provide concrete consisting of 5 classes, referred herein as Classes A, B, C, D, and CE specified in this section and use where specified or indicated on the Drawings.

2. Weight of Concrete Classes: Provide classes of concrete having minimum weight of 140 pounds per cubic foot. Where indicated as structural lightweeight, provide concrete with a weight of 120 pounds per cubic foot.

3. Class B Concrete: Class B concrete may be substituted for Class A concrete, when high-early strength concrete is needed in areas specifically accepted by the ENGINEER and that do not require sulfate resistant concrete.

4. Class C Concrete: Class C concrete may be used for fill for unauthorized excavation, for thrust blocks and ground anchors for piping, for bedding of pipe, and where indicated on the Drawings.

5. Class D Concrete: Use Class D for precast concrete items. Use Class D for liquid containment structures and basement walls per general structural notes.

6. Class CE Concrete: Use Class CE for electrical conduit encasements.

7. All other concrete, unless specified or otherwise indicated on the Drawings: Use
Class A concrete.

Table A Concrete
With Air Entrainment




Class
Specified Compressive Strength f'c at 28 Days (Pounds per Square Inch)


Maximum Net Water to Cement Ratio
M inimum Cement per Cubic Yard of Concrete by Weight (Pounds)

Slump Range (Inches)
A
4,000
0.45
564
2 to 4*
B (Type III cement)
4,000
4,000 lightweight

0.45

564

2 to 4*
C
2,500
0.62
423
3 to 6
D
4,500 or 5,000
0.45
658
2 to 4
CE
2,500
0.62
564
3 to 6
* NOTE: Slump for slabs, decks, walks, and beams shall be not more than 3-1/2 inches.

8. Pumped Concrete: Provide pumped concrete that complies with all requirements of this section.

9. Do not place concrete with slump outside limits indicated in Table A.
10. Classes:
a. Classes A, C, D, and CE Concrete: Make with Type II low alkali cement. b. Class B Concrete: Make with Type III low alkali cement.

c. Admixtures: Provide admixtures as specified in this section.

F. Air Entraining Admixture:

1. Add agent to batch in portion of mixing water.

2. Batch solution by means of mechanical batcher capable of accurate measurement.

2.4 SOURCE QUALITY CONTROL A. Tests:
1. Concrete Mixes:

a. After concrete mixes have been accepted by ENGINEER, have trial batches of the accepted Class A, Class B, and Class D concrete mix designs prepared by testing laboratory acceptable to the ENGINEER.

b. Prepare trial batches by using specified cement and aggregates proposed to be used for the Work.

c. Trial Batches: Provide batches of sufficient quantity to determine slump, workability, consistency, and finishing characteristics, and to provide sufficient test cylinders.

d. Test Cylinders: Provide cylinders having six inch diameter by 12 inch length and that are prepared in accordance with ASTM C 31 for tests specified in this section.

e. Determine slump in accordance with ASTM C 143. f. Test Cylinders from Trial Batch:
1) Test 8 cylinders for compressive strength in accordance with
ASTM C 39.

a) Test 4 cylinders at 7 days and 4 at 28 days.

b) Establish ratio between 7-day and 28-day strength for mix. Seven day strength may be taken as satisfactory indication of 28-day strength provided effects on concrete of temperature and humidity between 7-day and 28-day are taken into account.

2) Average Compressive Strength of 4 Test Cylinders Tested At 28 Days: Equal to or greater than required average compressive strength f'cr on which concrete mix design is based.
g. Drying Shrinkage:

1) Prepare 5 drying shrinkage specimens in accordance with ASTM C 157, except as modified herein.

2) Remove drying shrinkage specimens from molds at age of 23 hours plus or minus 1 hour after trial batching, then immediately place them in water at
73 degrees F plus or minus 3 degrees for at least 30 minutes and then measure specimens within 30 minutes thereafter to determine original length. Then submerge specimens in saturated lime water at 73 degrees F plus or minus three degrees for moist curing.

3) Make measurement to determine expansion expressed as percentage of original length at age 7 days. Use length at age 7 days as base length for drying shrinkage calculations.

4) Immediately store specimens in humidity controlled room maintained at
73 degrees F plus or minus 3 degrees and 50 percent plus or minus
4 relative humidity for remainder of test.

5) Make and report measurements to determine shrinkage expressed as percentage of base length separately for 7, 14, 21, and 28 days of drying after 7 days of moist curing.

6) Drying Shrinkage Deformation:

a) Measure drying shrinkage deformation of each specimen as difference between base length and length after drying at each test age.

b) Measure average drying shrinkage deformation of specimens to nearest 0.0001 inch at each test age.

c) If drying shrinkage of any specimen departs from average of test age by more than 0.0004 inch, disregard results obtained from that specimen and test another specimen.

d) Shrinkage of trial batch concrete at 28 days drying age shall not exceed 0.045 percent maximum.

h. If trial batch tests do not meet specified requirements for slump, strength, workability, consistency, drying shrinkage, and finishing, change concrete mix design proportions and, if necessary, source of aggregate. Make additional trial batches and tests until an acceptable trial batch is produced that meets requirements of this section.

i. Perform test batches and tests required to establish trial batches and acceptability of materials without change in Contract Price.

j. Do not place concrete until the concrete mix design and trail batch have been accepted by ENGINEER.
2. Required Average Compressive Strength:

a. Determine required average compressive strength (f'cr) for selection of concrete proportions for mix design, for each class of concrete, using calculated standard deviation and its corresponding specified compressive strength f'c, in accordance with ACI 318, Part 3, Chapter 5.

b. When test records of at least 30 consecutive tests that span period of not less than 45 calendar days are available, establish standard deviation as described in ACI 318, Part 3, Chapter 5 and as modified as follows herein.

c. Provide test records from which to calculate standard deviation that represent materials, quality control procedures, and conditions similar to materials, quality control procedures, and conditions expected to apply in preparation of concrete for the Work.

d. Provide changes in materials and proportions within test records that are more restricted than those for the Work.

e. Specified Compressive Strength (f'c) of Concrete Used in Test Records: Within 1,000 pounds per square inch of that specified for the Work.

When lacking adequate test records for calculation of standard deviation meeting requirements, determine required average compressive strength f'cr from following Table B.

Table B
Specified Compressive
Strength f'c
(pounds per square inch)
Required Average Compressive Strength f'cr (pounds per square inch)
Less than 3,000
f'c + 1,000
3,000 to 5,000
f'c + 1,200
Over 5,000
f'c + 1,400

3. Pozzolan:

a. Sampling and Testing:

(1) Sample and test pozzolan in accordance with ASTM C 311.

(2) In Computing Water to Cement Ratio And Cement Content Per Cubic Yard Of Concrete: Consider cement weight to be weight of portland cement plus 100 percent of weight of fly ash.

4. Aggregate:

a. Testing of concrete aggregate is at CONTRACTOR's expense. b. Sieves:
1) Use sieves with square openings for testing grading of aggregates.

2) Sieve Analyses: If sieve analyses indicate significant change in materials, the ENGINEER may require that new mix design be submitted and accepted before further placing of concrete.
c. Sample aggregate in accordance with ASTM D 75 and C 136. d. Fine Aggregate:
1) Provide fine aggregate not containing strong alkali nor organic matter which gives color darker than standard color when tested in accordance with ASTM C 40.

2) Provide aggregate having soundness complying with requirements of
ASTM C 33 when tested in accordance with ASTM C 88.

3) Provide aggregate complying with reactivity requirements of ASTM C 33 when tested in accordance with ASTM C 289.

e. Coarse Aggregate:

1) Soundness when tested in accordance with ASTM C 88: Have loss not greater than 10 percent when tested with sodium sulfate.

2) Abrasion Loss: Not exceed 45 percent after 500 revolutions when tested in accordance with ASTM C 131.

3) Reactivity: Not exceed limits specified in Appendix of ASTM C 33 when tested in accordance with ASTM C 289.

f. Portland Cement:

1) Determination Alkali Content: Determine by method set forth in
ASTM C 114.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Conduit Encasement Concrete: Mix into each cubic yard of concrete 10 pounds of coloring agent.

B. Surface Sealant System: Apply as recommended by manufacturer published instructions. Where concrete continues to sweat or leak, apply additional coats of surface sealant until the sweating or leaks stop.

C. Joints and Bonding:

1. As far as practicable, construct concrete work as monolith.

2. Locations of contraction, construction, expansion, and other joints are indicated on the Drawings or as specified in this section.

3. For the Following Structures:

a. Larger Structures.

1) Provide not less than 7 days between placement of concrete in adjacent concrete wall placements.
2) Place concrete for slabs in checker board pattern with not less than 14 days between placement of concrete in adjacent concrete slab placements for slabs more than 3 feet thick.

3) Place concrete for slabs in checker board pattern with not less than 7 days between placement of concrete in adjacent concrete slab placements for slabs less than 3 feet thick.

b. Tunnels.

1) Provide not less than 7 days between placement of concrete in adjacent concrete wall placements.

2) Place concrete for slabs in checker board pattern with not less than
3 days between placement of concrete in adjacent concrete slab placements.

4. Construction Joints:

a. Where construction joints are not indicated on the Drawings, provide slabs and walls with construction joints at intervals not greater than 30 feet.

b. In order to preserve strength and watertightness of structures, make no other joints, except as authorized by the ENGINEER.

c. At construction joints, thoroughly clean concrete of laitance, grease, oil, mud, dirt, curing compounds, mortar droppings, or other objectionable matter by means of heavy sandblasting, and wash surfaces just prior to succeeding concrete placement.

d. At Horizontal Joints: Immediately prior to resuming concrete placing operations, thoroughly spread bed of grout not less than 1/2 inch in thickness nor more than 1 inch in thickness over horizontal joint surfaces.

5. Keyways in Joints:

a. Provide keyways in joints as indicated on the Drawings.

b. Treat lumber keyway material with form release coating, applied in accordance with manufacturer's instructions.

c. Take special care to ensure that concrete is well consolidated around and against waterstops and that waterstops are secured in proper position.

6. Cleaning of Construction Joints:

a. Wash construction joints free of sawdust, chips, and other debris after forms are built and immediately before concrete or grout placement.

b. Should formwork confine sawdust, chips, or other loose matter in such manner that it is impossible to remove them by flushing with water, use vacuum cleaner for their removal, after which flush cleaned surfaces with water.

c. Provide cleanout hole at base of each wall and column for inspection and cleaning.
7. Expansion, Contraction, and Construction Joints

a. Constructed where and as indicated on the Drawings.

b. Waterstops, Expansion Joint Material, Synthetic Rubber Sealing Compound, and Other Similar Materials: As specified in Sections 03290, Joints in Concrete and 07900, Joint Sealants.

8. Repair of Concrete: Where it is necessary to repair concrete by bonding mortar or new concrete to concrete which has reached its initial set, first coat surface of set concrete with epoxy bonding agent as specified in Section 03071, Epoxies.

D. Conveying and Placing Concrete:

1. Convey concrete from mixer to place of final deposit by methods which prevent separation or loss of materials.

2. Use equipment for chuting, pumping, and conveying concrete of such size and design as to ensure practically continuous flow of concrete at delivery end without separation of materials.

3. Design and use chutes and devices for conveying and depositing concrete that direct concrete vertically downward when discharged from chute or conveying device.

4. Keep equipment for conveying concrete thoroughly clean by washing and scraping upon completion of any day's placement.

E. Placing Concrete:

1. Place no concrete without prior authorization of the ENGINEER.

2. Do Not Place Concrete Until:

a. Reinforcement is securely and properly fastened in its correct position and loose form ties at construction joints have been retightened.

b. Dowels, bucks, sleeves, hangers, pipes, conduits, bolts, and any other fixtures required to be embedded in concrete have been placed and adequately anchored.

c. Forms have been cleaned and oiled as specified.

3. Placement of concrete in which initial set has occurred, or of retempered concrete, will not be permitted.

4. Place no concrete during rainstorms or high velocity winds.

5. Protect concrete placed immediately before rain to prevent water from coming in contact with such concrete or winds causing excessive drying.

6. Keep sufficient protective covering on hand at all times for protection of concrete.

7. After acceptance, adhere to proposed sequence of placing concrete, except when specific changes are requested and accepted by the ENGINEER.
8. Notify the ENGINEER in writing of readiness, not just intention, to place concrete in any portion of the Work.

a. Provide this notification in such time in advance of operations as the ENGINEER deems necessary to make final inspection of preparations at location of proposed concrete placing.

b. Place forms, steel, screeds, anchors, ties, and inserts in place before notification of readiness is given to the ENGINEER.

c. Depositing Concrete:

1) Deposit concrete at or near its final position to avoid segregation caused by rehandling or flowing.

2) Do not deposit concrete in large quantities in one place and work along forms with vibrator or by other methods.

3) Do not drop concrete freely into place from height greater than 5 feet.

4) Use tremies for placing concrete where drop is over 5 feet.

5) Commence placement of concrete on slopes, at bottom of slope.

9. Place concrete in approximately horizontal layers not to exceed 24 inches in depth and bring up evenly in all parts of forms.

10. Continue concrete placement without avoidable interruption, in continuous operation, until end of placement is reached.

11. If more than 20 minutes lapse prior to placement of new concrete over concrete previously placed, reduce depth of layers being placed at one time, and/or increase placing equipment, until it is possible to return with placing operation to previously placed concrete within 20 minutes.

12. If concrete is to be placed over previously placed concrete and more than
20 minutes have elapsed, then spread layer of grout not less than 1/2 inch in thickness nor more than 1 inch in thickness over surface before placing additional concrete.

13. Placement of Concrete for Slabs, Beams, or Walkways:

a. If cast monolithically with walls or columns, do not commence until concrete in walls or columns has been allowed to set and shrink.

b. Allow set time of not less than one hour for shrinkage. F. Consolidating Concrete:
1. Place concrete with aid of acceptable mechanical vibrators.

2. Thoroughly consolidate concrete around reinforcement, pipes, or other shapes built into the Work.
3. Provide sufficiently intense vibration to cause concrete to flow and settle readily into place and to visibly affect concrete over radius of at least 18 inches.

4. Vibrators:

a. Keep sufficient vibrators on hand at all times to vibrate concrete as placed.

b. In addition to vibrators in actual use while concrete is being placed, have on hand minimum 1 spare vibrator in serviceable condition.

c. Place no concrete until it has been ascertained that all vibrating equipment, including spares, are in serviceable condition.

5. Take special care to place concrete solidly against forms so as to leave no voids.

6. Take every precaution to make concrete solid, compact, and smooth, and if for any reason surfaces or interiors have voids or are in any way defective, repair such concrete in manner acceptable to the ENGINEER.

G. Footings and Slabs on Grade:

1. Do not place concrete on ground or compacted fill until subgrade is in moist condition acceptable to the ENGINEER.

2. If necessary, sprinkle subgrade with water not less than 6 nor more than
20 hours in advance of placing concrete.

3. If it becomes dry prior to actual placing of concrete, sprinkle again, without forming pools of water.

4. Place no concrete if subgrade is muddy or soft. H. Loading Concrete:
1. Green Concrete:

a. No heavy loading of green concrete will be permitted.

b. Green concrete is defined as concrete with less than 100 percent of the specified strength.

2. No backfill shall be placed against concrete walls until the concrete has reached the specified strength and the connecting slabs and bemas have been cast and have reached the specified strength.

3. Use construction methods, sequencing, and allow time for concrete to reach adequate strength to prevent overstress of the concrete structure during construction.

I. Curing Concrete:

1. General:

a. Cure concrete by methods specified in this section. b. Cure concrete minimum of 7 days.
c. Cure concrete to be painted with water or plastic membrane.

d. Do not use curing compound on concrete surfaces that are to receive paint or upon which any material is to be bonded.

e. Water cure or plastic membrane cure concrete slabs which are specified to be sealed by concrete sealer.

f. Cure other concrete by water curing or sprayed curing membrane at the
CONTRACTOR's option.

g. Floor slabs may be cured using plastic membrane curing.


h. All liquid containment structures shall be water-cured.

2. Water Curing:

a. Keep surfaces of concrete being water cured constantly and visibly moist day and night for period of not less than 7 days.

b. Each day forms remain in place may count as 1 day of water curing.

c. No further curing credit will be allowed for forms in place after contact has once been broken between concrete surface and forms.

d. Do not loosen form ties during period when concrete is being cured by leaving forms in place.

e. Flood top of walls with water at least 3 times per day, and keep concrete surfaces moist at all times during 7-day curing period.

3. Sprayed Membrane Curing:

a. Apply curing compound to concrete surface after repairing and patching, and within 1 hour after forms are removed.

b. If more than 1 hour elapses after removal of forms, do not use membrane curing compound, but apply water curing for full curing period.

c. If surface requires repairing or painting, water cure such concrete surfaces. d. Curing Compound:
1) Do not remove curing compound from concrete in less than 7 days.

2) Curing compound may be removed only upon written request by the CONTRACTOR and acceptance by the ENGINEER, stating what measures are to be performed to adequately cure structures.

3) Take care to apply curing compound in area of construction joints to see that curing compound is placed within construction joint silhouette.

4) Remove curing compound placed within construction joint silhouette by heavy sandblasting prior to placing any new concrete.
5) CONTRACTOR's Option: Instead of using curing compound for curing of construction joints such joints may be water cured.

6) Apply curing compound by mechanical, power operated sprayer and mechanical agitator that will uniformly mix all pigment and compound.

7) Apply compound in at least 2 coats.

8) Apply each coat in direction 90 degrees to preceding coat.

9) Apply compound in sufficient quantity so that concrete has uniform appearance and that natural color is effectively and completely concealed at time of spraying.

10) Continue to coat and recoat surfaces until specified coverage is achieved and until coating film remains on concrete surfaces.

11) Thickness and Coverage of Compound: Provide compound having film thickness that can be scraped from surfaces at any and all points after drying for at least 24 hours.

12) The CONTRACTOR is cautioned that method of applying curing compound specified herein may require more compound than normally suggested by manufacturer of compound and also more than is customary in the trade.

a) Apply amounts specified herein, regardless of manufacturer's recommendations or customary practice, if curing compound is used in place of water curing.

13) If the CONTRACTOR desires to use curing compound other than specified compound, coat sample areas of concrete wall with proposed compound and also similar adjacent area with specified compound in specified manner for comparison.

a) If proposed sample is not equal or better, in opinion of the
ENGINEER, in all features, proposed substitution will not be allowed.

14) Prior to final acceptance of the Work, remove, by sandblasting or other acceptable method, any curing compound on surfaces exposed to view, so that only natural color of finished concrete is visible uniformly over entire surface.

4. Plastic Membrane Curing:

a. Polyethylene film may be used to cure slabs. Seal joints and edges with small sand berm.

b. Install plastic membrane as soon as concrete is finished and can be walked on without damage.

c. Keep concrete moist under plastic membrane.
3.2 CONCRETE FINISHING

A. Provide concrete finishes in accordance with Section 03366, Tooled Concrete
Finishes, and the Concrete Finish Schedule indicated on the Drawings.

B. Edges of Joints:

1. Provide joints having edges as indicated on the Drawings.

2. Protect wall and slab surfaces at edges against concrete spatter and thoroughly clean upon completion of each placement.

C. Concrete Sealer:

1. Floors and Slabs to Receive Sealer: As specified in Division 9, Finishes.

2. Seal Floors and Slabs at CONTRACTOR's Option:

a. All Floor Slabs Except for the Following:

1) Those indicated on the Drawings to receive seamless Floor surfacing.

2) Any slabs which receive concrete or grout surfacing, in lieu of water or curing compound.

3. Apply Sealant:

a. Apply sealant at coverage rate not to exceed 500 square feet per gallon. b. Apply as soon as slab or floor will bear weight.
c. Sealer:

1) Before applying sealer, sweep entire surface clean with very soft bristled brush which will not mark finish.

2) Apply sealer with large, clean, mop type applicator.

3) Paint rollers are not acceptable.

4) Workmen shall wear flat soled shoes which will not mark or scar surface.

5) Do not allow traffic on floors and slabs until sealer has dried and hardened.

3.3 FIELD QUALITY CONTROL A. Testing of Concrete:
1. During progress of construction, the CONTRACTOR will have tests made to determine whether the concrete, as being produced, complies with requirements specified.
2. Tests will be performed in accordance with ASTM C 31, ASTM C 39, and
ASTM C 172.

3. The CONTRACTOR will make and deliver test cylinders to the laboratory and testing expense will be borne by the CONTRACTOR.

4. Required Number Cylinders:

a. Not less than 3 cylinder specimens, 6 inch diameter by 12 inch long, will be tested for each 150 cubic yards of each class of concrete with minimum of
3 three specimens for each class of concrete placed and not less than
3 specimens for each half day's placement.

b. One cylinder will be broken at 7 days and 2 at 28 days.

5. The CONTRACTOR shall:

a. Test slump of concrete using slump cone in accordance with requirements of
ASTM C 143.

b. Furnish test equipment.

c. Do not use concrete that does not meet specification requirements in regards to slump, but remove such concrete from project site.

d. Test slump at the beginning of each placement, as often as necessary to keep slump within the specified range, and when requested to do so by the ENGINEER.

e. Make provisions for and furnish concrete for test specimens, and prepare test specimens under supervision of the ENGINEER.

B. Assume responsibility for care of and providing of curing conditions for test specimens in accordance with ASTM C 31.

C. Air Entraining Admixture:

1. Test percent of entrained air in concrete at beginning of each placement, as often as necessary to keep entrained air within specified range, and when requested to do so by the ENGINEER.

2. Provide test equipment.

3. Do not use concrete that does not meet Specification requirements as to air entrainment and shall remove such concrete from project site.

4. Test air entrainment in concrete in accordance with ASTM C 173.

5. The ENGINEER may at any time test percent of entrained air in concrete received on project site.
D. Enforcement of Strength Requirement:

1. Concrete is expected to reach higher compressive strength than that which is indicated in Table A as specified compressive strength f'c.

2. Strength Level of Concrete: Will be considered acceptable if following conditions are satisfied.

a. Averages of all sets of 3 consecutive strength test results is greater or equal to specified compressive strength f'c.

b. No individual strength test (average of 2 cylinders) falls below specified compressive strength f'c by more than 500 pounds per square inch.

c. Whenever one, or both, of 2 conditions stated above is not satisfied, provide additional curing of affected portion followed by cores taken in accordance with ASTM C 42 and ACI 318 and comply with following requirements:

1) If additional curing does not bring average of 3 cores taken in affected area to at least specified compressive strength f'c, designate such concrete in affected area as defective.

2) The ENGINEER may require the CONTRACTOR to strengthen defective concrete by means of additional concrete, additional reinforcing steel, or replacement of defective concrete, all of the CONTRACTOR's expense.

3.4 ADJUSTING

A. Repair of Defective Concrete:

1. Remove and replace or repair defective work.

2. Correct defective work as specified in this Article.

3. Do not patch, repair, or cover defective work without inspection by the
ENGINEER.

4. Provide repairs having strength equal to or greater than specified concrete for areas involved.

a. Chip out and key imperfections in the Work and make them ready for repair.

5. Dry Pack Method:

a. Dry Pack Method: Use for holes having depth nearly equal to or greater than least surface dimension of hole, for cone-bolt, and narrow slots cut for repair.

b. Smooth Holes: Clean and roughen by heavy sandblasting before repair.l

6. Mortar Method of Replacement: Use for following:

a. Holes too wide to dry pack and too shallow for concrete replacement.
b. Comparatively shallow depressions, large or small, which extend no deeper than reinforcement nearest surface.

7. Concrete Replacement:

a. Use: When holes extend entirely through concrete section or when holes are more than 1 square foot in area and extend halfway or more through the section.

b. Method of Repair for Surfaces of Set Concrete to Be Repaired: First coat with epoxy bonding agent.

8. Acceptable Method of Concrete Repair:

a. Make no repair until the ENGINEER has accepted method of preparing surfaces and proposed method of repair.

No comments:

Post a Comment