Section
02527
CONCRETE
PAVEMENTS, CURBS AND SIDEWALKS
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. The CONTRACTOR shall
furnish all tools, equipment, materials, and supplies and shall
perform all labor required to complete the Work as indicated
in the Contract Documents and specified herein.
B. This section
covers the Work necessary to construct the following concrete
pavements, curbs and sidewalks, complete, in place in accordance with
the requirements of the Contract Documents.
1. Curbs and sidewalks
are shown on the Contract Documents and include curbing along East
Perimeter Road, around the Thickening and Dewatering building, and
other new facilities built as part of this project. See Drawings
C1-1002 and C1-1003 for curb and sidewalk locations.
2. Concrete pavement is
shown on the Contract Documents drawing C1-1001.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following sections and divisions apply to the Work of this
section. Other sections and divisions of the Specifications, not
referenced below, shall also apply to the extent required for proper
performance of this Work.
1. Section 02200,
Earthwork
2. Section 02232,
Preparation of Pavement Subgrade
3. Section 03100,
Concrete Formwork
4. Section 03200,
Reinforcement Steel
5. Section 03290,
Joints in Concrete
6. Section 03300,
Cast-In-Place Concrete
7. Section 03350,
Testing of Cementitious Material
8. Section 03360,
Concrete Curing, Finishing and Dampproofing
1.3
REFERENCE
SPECIFICATIONS, CODES AND STANDARDS
A. Comply with the
applicable reference Specifications as specified in the General
Requirements.
B. Work of this
section shall be performed in accordance with the Standard
Specifications for Public Works Construction (SSPWC) unless otherwise
specified in this Section.
1.4
CONTRACTOR
SUBMITTALS
A. Submittals shall be
made in accordance with the General Requirements and Additional
General Requirements.
1.5
QUALITY
ASSURANCE
A. Comply with the
applicable reference Specifications of the General Requirements.
PART 2 - PRODUCTS
2.1
FORMS
A. Form material shall
be in conformance with SSPWC Section 303-5.2.
2.2
DRAINAGE
OUTLET THROUGH CURB
A. Curb drainage
outlets shall be constructed in conformance with SSPWC Section 303-
5.1.2.
2.3
CRUSHED
AGGREGATE BASE
A. Crushed Aggregate
Base shall conform to SSPWC Section 200-2.2.
2.4
EXPANSION
JOINT FILLER
A. Expansion joint
filler shall be 1/2 inch thick, preformed
asphalt-impregnated, expansion joint material conforming to ASTM D
994.
2.5
CONCRETE
A. Refer to Section
03300, Cast-in-Place Concrete.
2.6
REINFORCING
A. Refer to Section
03200, Reinforcement Steel.
2.7
CURING
COMPOUND
A. Refer to Section
03360, Concrete Curing, Finishing and Dampproofing.
2.8
ACCEPTANCE
OF MATERIALS
A. All materials
shall be subject to testing, inspection and acceptance by
the
ENGINEER
at any time prior to or during the Work, as applicable.
2.9
EXCAVATION
AND BACKFILL
A. Refer to Section
02200, Earthwork.
PART 3 - EXECUTION
3.1
GENERAL
A. Unless otherwise
specified, all curb and gutter is aligned by the top front edge of
the curb, which is set as to alignment and grade. All other
dimensions for the curb and gutter section are taken from this edge.
B. Construction joints
or weakened-plane joints shall be used to mark locations on curbing
where aprons will be constructed for driveway and handicap access
ramps.
C. Unless otherwise
specified on the Contract Documents, forms for sidewalk
construction shall be set to place the finished surface in a plane
sloping up from the top of curb at a rate of 1/4 inch per foot when
measured at right angles to the face of curb. Where this grade does
not meet existing improvements, such as private driveway slabs or
building entrances, the CONTRACTOR shall notify the ENGINEER, who
shall adjust sidewalk grades accordingly.
D. Where existing
concrete curb, gutter or sidewalk is being replaced, improvements
shall be removed back to the nearest joint before beginning
replacement.
E. The edge of
existing asphalt shall not be used as a form for new curb and
gutter. Existing Asphalt shall be cut back a minimum of 1
foot, new curb and/or gutter constructed and asphalt replaced.
3.2
EXCAVATION
AND BACKFILL
A. Excavation and
backfill shall be in conformance with Section 02200, Earthwork.
3.3
PREPARATION
OF SUBGRADE
A. Preparation of
subgrade shall be in conformance with Section 02232, Preparation of
Pavement Subgrade.
3.4
PLACING
CRUSHED AGGREGATE BASE
A. Crushed Aggregate
Base shall be in conformance with the SSPWC Section 301-2.2. B.
Crushed Aggregate Base shall be compacted in conformance with SSPWC
Section
301-2.3 with the
exception that all subgrade shall be compacted to 95 percent
relative
density.
3.5
SETTING
FORMS
A. Setting forms shall
be in conformance with SSPWC Section 303-5.2.1.
3.6
SLIP
FORMING
A. Slip-form equipment
shall be in conformance with SSPWC Section 303-5.2.2.
3.7
EXPANSION
JOINTS
A. Expansion joints
shall be constructed in conformance with SSPWC Section 303-
5.4.2.
3.8
WEAKENED
PLANE JOINTS AND CONTROL JOINTS
A. Weakened plane
joints shall be placed in conformance with SSPWC Section 303-
5.4.3.
3.9
PLACING
CONCRETE
A. Concrete shall be
placed in conformance with SSPWC Section 303-5.3.
3.10
FINISHING
A. General:
Finishing shall be completed as specified herein for the type of
work being performed.
B. Pavement:
Float by longitudinally reciprocating float, passing gradually from
edge to edge. Assure successive advances do not exceed half the
length of the float. Test level of slab with minimum 10-foot
straightedge. Fill depressions with fresh material, consolidate and
refinish. Cut down high areas and retest. Belt surface with
two-ply canvas belt, using transverse strokes while advancing along
center line. Provide final finish by full width burlap or carpet
drag, drawn longitudinally. Keep drag clean to avoid build up and
consequent scarring. Tool pavement edges with suitable edger. Retest
with straightedge and if pavement shows deviation of more than 1/8
inch in 10 feet, remove and replace.
C. Curb:
The stripping of front forms and finishing of curb shall be in
conformance with SSPWC Section 303-5.5.2. Where the back of new
curb is exposed, it shall likewise be finished in conformance with
SSPWC Section 303-5.5.2.
D. Walk:
The finished surface of the walk shall be in conformance with SSPWC
Section
303-5.5.3.
E. Gutter:
The gutter shall be finished in conformance with SSPWC Section
303-5.5.4.
F.
Access
Ramps and Driveways:
The Access Ramps and Driveways shall be finished
in conformance with
SSPWC Section 303-5.5.5.
G. Painting:
Curbs which were previously painted shall be repainted as shown on
the
Drawings per
city/county/state requirements.
3.11
CURING
A. Refer to Section
03360, Concrete Curing Finishing and Dampproofing.
3.12
OPENING
TO TRAFFIC
A. After 14 days,
pavement may be opened to traffic if job cured test cylinders have
attained a compressive strength of 3,000 pounds per square inch
when tested in accordance with ASTM standard methods.
B. Prior to opening to
traffic, clean and refill joints as required with the specified
filler material.
3.13
FIELD
QUALITY CONTROL
A. Provide test
cylinders per section 03350, Testing of Cementitious Material. B.
Pavement Thickness Testing.
1. General:
a. Core pavement to
determine the actual thickness, as directed by Engineer. b.
Determine thickness by ASTM C174.
c. Fill holes from
removal of cores with concrete of the same mixture as
specified.
d. Cost incidental to
coring of cores showing a deficiency greater than 1/4 inch shall be
paid by the Contractor.
e. Cost of cores
showing a deficiency of 1/4 inch or less shall be paid by the
Owner.
f. If average
pavement thickness, as directed by core measurement, is outside
specified tolerances, payment will be reduced per PART 1 of this
Specification Section.
g. If deficiency in
pavement thickness is 1 inch or more, remove and replace pavement at
Contractor's expense.
2. Core categories:
a. In determining the
average thickness of acceptable pavement for which payment will
be made, utilize the following core categories:
Category
Number
Core Thickness in
Relation
to Design
Core Length Used in
Calculating
1 1
inch or more deficiency NOT USED
2 Less than
1 inch deficiency through 1/2 inch excess
Actual
Core Thickness
3 More
than 1/2 inch excess Design Thickness plus 1/2 inch
b. Core sampling:
1) Take cores in each
lane in each block.
c. Take cores at
locations where the cement content was found to be low when checking
the quantities of cement used during the progress of the work.
d. Each separately
poured lane of the pavement to be considered as a unit.
e. A lane shall be
considered to be the pavement surface between longitudinal
construction joints, between a longitudinal construction joint and
the edge, or between two (2) pavement edges in cases where
the entire width of the pavement is poured in one (1) operation.
f. Should any core
show a deficiency in thickness in excess of 1 inch, check cores shall
be taken 5 feet on either side of this location parallel to the
centerline of the pavement.
g. If both of these
cores are within the 1 inch tolerance, no further special borings for
this individual zone of deficiency will be made.
h. If either one (1) or
both of these cores are not within the 1 inch tolerance, the
procedure will be to cut cores in the following order on either side
of the original short core parallel to the centerline of the
pavement:
1) 25 feet, 50 feet,
the same to be measured from the location of original core found to
be deficient in thickness, then at 50 feet intervals until a
thickness within the 1 inch tolerance is found in both directions.
2) On either side of
the original deficient core, the procedure will then be to make a
coring approximately half the distance within the first core which
comes within the 1 inch tolerance.
3) Repeat the above
procedure until the station (+5 feet), at which the pavement comes
within the 1 inch tolerance is located.
4) If for some reason
two (2) or more cores are taken at the same station and at least one
(1) of them is beyond the 1 inch tolerance, the section of pavement
at the station shall be considered as unacceptable.
No comments:
Post a Comment