Thursday, July 24, 2014

Section 11250 SLUDGE CAKE PUMPING SYSTEM

Section 11250

SLUDGE CAKE PUMPING SYSTEM

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Material, design, fabrication and installation requirements for progressing cavity pumps and related equipment for pumping sludge cake (dewatered sludge) from dewatering building to cake silos and from cake silos to loadout facilities.

B. Related Sections include but are not necessarily limited to:

1. The requirements of the following sections and divisions apply to the Work of this section. Other sections and divisions of the Specifications, not referenced below, shall also apply to the extent required for proper performance of this Work.

a. Division 01, Additional General Requirements b. Section 05500, Miscellaneous Metalwork
c. Section 09800, Protective Coating

d. Section 11005, Equipment: Basic Requirements e. Section 11309, Progressing Cavity Pumps
f. Section 11210, Pumps and Equipment, General g. Section 15101, Valve Operators
h. Section 15008, Steel Pipe

i. Section 15009, Fabricated Specials j. Section 15106, Ball Valves
k. Section 16220, Electric Motors

l. Section 16418, Variable Frequency Drives Below 100 HP

m. Section 16419, Variable Frequency Drives 100 HP and Above n. Section 16442, Control Panels
o. Section 17300, Control Strategies

p. Section 17405, Process Instrumentation and Controls

1.2 QUALITY ASSURANCE

A. Referenced Standards:

1. American Bearing Manufacturers Association (ABMA)

2. American Iron and Steel Institute (AISI):

a. Steel Products Manual

3. American National Standards Institute (ANSI).

4. ASTM International (ASTM):

a. A48 Standard Specification for Gray Iron Castings

5. Hydraulic Institute (HI)
1.3 WARRANTY

A. The pumping units shall be warranted by the manufacturer for a minimum of three (3) year period after beneficial occupancy of the Work pursuant to “Use Prior to Final Completion” of the general conditions, against defects in workmanship and materials. Wear items such as seals, bearings, rotor, stator and motor. Rotors and stators may be prorated during the three year period. The first year warranty shall cover pump performance to comply with the design criteria stated in Articles “2.3 Equipment and 2.4
Dewatered Cake and Cake Silo Transfer Pump Accessories” and the pump manufacturer shall be responsible for replacing the pumps with adequately sized pumps to meet the criteria.

1.4 SYSTEM DESCRIPTION

A. All pumps specified in this section shall be provided by the same manufacturer. B. Pump manufacturer will also supply:
1. Inlet chutes (hoppers) with flexible top connection.

2. Slide gates for cake transfer pumps only (not required for the silo pumps because it is furnished with the sliding frame equipment).

3. Load cell weighing system.

4. Flexible connection on pump discharge.

5. Slip injection rings.

6. Slip injection pumps.

7. Slip injection control panels.

8. Cake piping and fittings.

9. Full port ball valves with pneumatic actuators for the cake silo pumps.

10. Full port ball valves with electric motor actuators for the cake pumps.

11. Pipe supports for the cake piping and valves.

1.5 SUBMITTALS

A. The CONTRACTOR shall submit complete shop drawings for acceptance in accordance with Shop Drawing Submittals of the General Requirements and as specified herein.

B. In addition to the submittal requirements of Section 11210, Pumps, General, the following shall be submitted:

1. Shop drawings showing complete fabrication and construction details, materials, weights, dimensions, clearances, anchorage locations and bolt detail, piping and utility requirements, and step-by-step sequence of controls.

2. Pump manufacturer, type and model, rpm at rated condition, size of suction and discharge flanges, and maximum bhp requirement at maximum differential pressure condition.

3. Certified Pump Curves showing maximum and minimum speeds.

4. Shop drawings including fabrication layout and construction details, materials, weights, dimensions, clearances, connection locations and bolt detail, piping and utility connections for the inlet chutes and or hoppers.
5. Shop drawings showing layout of slip injection rings with piping, connection and support details and catalog cuts for materials, weights, dimensions, configuration, and installation instructions.

6. For pump control panels, complete master wiring diagrams, elementary or control schematics, interconnection drawings, loop drawings including required coordination with other electrical control devices operating in conjunction with the pumping system and acceptable outline Drawings shall be furnished for acceptance before proceeding with manufacture. Due to the complexity of the control functions, it is imperative the above Drawings be clear and carefully prepared to facilitate interconnections with other equipment. Standard preprinted sheets or Drawings simply marked to indicate applicability to this Contract will not be acceptable. Refer to section 16442, Control Panels, for additional requirements.

7. Coordination letter stating that the pump manufacturer has coordinated with the manufacturer of the Variable Frequency Drives specified in Specification section
16418, Variable Frequency Drives below 100 hp and 16419, Variable Frequency
Drives 100 hp and Above, for complete compatibility.

8. Bearing Life Calculations.

1.6 DELIVERY, STORAGE, AND HANDLING

A. All materials and equipment shall be shipped, stored, handled and installed in such a manner as not to degrade quality, serviceability or appearance. The equipment shall be stored in a clean, dry location free from construction dust, precipitation and excess moisture. If stored for more than two weeks, the equipment shall receive all maintenance considerations required by the manufacturer for proper storage of the equipment.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Subject to compliance with the Contract Documents, the following Manufacturers are acceptable:

1. Progressing cavity pumps for Dewatered Cake Transfer Pumps:

a. Seepex, Model THE 300-27

2. Progressing cavity pumps for Silo Cake Transfer Pumps:

a.

b. Seepex, Model -THE 240-24D

B. Submit request for substitution in accordance with the General Requirements.

1. CONTRACTOR shall provide the following additional information for substitution:

a. Five references for similar operating installation with contact names and numbers.

b. Detailed Drawings in 3-D.

c. Ensure substitution fits within the allocated space.

d. Substitution cannot encroach in the open space around the cake pumps as indicated on the construction Drawings.

2.2 MATERIALS

A. Cake Silo Transfer Pumps (15JPMP810; 15JPMP830; 15JPMP850; 15JPMP870), and Dewatered Cake Transfer Pumps (15MPMP580 and 15MPMP590):
1. Pump Body: Cast iron, ASTM A48 Class 35.

2. Rotor: D6 tool steel hardened to Rockwell C57-60:

a. For abrasive service; a fissure free non-porous coating diffusing deep into the base metal will be provided. The coating shall be a minimum of .010 inch thickness and 1250 Vickers hardness minimum. Galvanic chrome plating in 633 Vickers hardness or 57hRc shall be acceptable if the pump manufacturer furnished an extended warranty for the rotor for two years after the contractors warranty for 12 month from beneficial use of the facility expires.

3. Stator:

a. Buna-N The stator shall be molded with a seal integral to the stator elastomer preventing the metal stator tube and the bonding agent from the elastomer from contacting the pumped liquid. Gaskets or "O" rings may not be used to form this seal. All stators must be individually made and not cut to size. Each stator must have elastomer cover the end of each stator tube. The stator tube shall not be exposed to the product.

b. Joints: Each pump shall use two flexible joints. The joints must be guaranteed for a minimum of 20,000 hours


4. Base plate: Fabricated steel.

5. Stuffing Box Gland: Ductile iron.

6. Lantern Ring: Teflon. B. Slip Injection Rings
1. Body: Type 316 stainless steel.

C. Inlet Chutes/Hoppers: Type 304 stainless steel

2.3 EQUIPMENT

A. Performance and Configuration Requirements:

1. Material Description:

a. Dewatered anaerobically digested municipal sludge.

b. Maximum Sludge Density: 65 pounds/cubic foot. (1040 kg/m3). c. Minimum Sludge Density: 60 pounds/cubic foot (960 kg/m3).
d. Maximum Sludge Moisture: 75 percent. e. Minimum Sludge Moisture: 65 percent. f. Abrasive.
g. Corrosive.

h. Contains oil, grease, grit, ferric chloride, and polymer. i. Maximum Lump Size: 1 inch
2. Dewatered Cake Transfer Pumps:

a. Tag Id’s: 15MPMP580 and 15MPMP590

b. Liquid Pumped: 25 – 35 percent Centrifuge Dewatered Cake. c. Design conditions:
a) 130 gpm with 25 percent cake solids. b) 120 gpm with 30 percent cake solids. c) 93 gpm with 35 percent cake solids.
d. Maximum condition:

a) 150 gpm at 400 pounds per inch with 25 percent solids. e. Nameplate Driver hp: 200
f. Feed Mechanism: Provide positive means of shearing cake to reduce apparent viscosity and ensuring that cake feeds properly to pumping elements. Use one of two methods:

1) Ribbon auger:

a) Ribbon auger attached to plate fixed to pump drive shaft extending through oversized extension tube.

b) Feed rate minimum of four times rated pump capacity. c) Support with heavy duty urethane liner in hopper.
g. Number of Stages: 8 minimum.

h. Pump Speed: 50 RPM at design condition.

i. Pump Speed: <60 RPM at Maximum condition.

j. Pressure per Stage: 60 pounds per inch at maximum pressure. k. Drive Type: Variable frequency.
l. Drive Configuration: Inline helical gear.

m. Discharge ANSI B16.5, 300 pounds; 14-inch diameter, minimum.

3. Silo Cake Transfer Pumps:

a. Tag Id’s: 15JPMP810; 15JPMP830; 15JPMP850; 15JPMP870

b. Liquid Pumped: 25-35 percent Centrifuge Dewatered Cake Stored in the
Silo.

c. Design condition:

1) 145 gpm with 25 percent cake solids.

2) 110 gpm with 30 percent cake solids.

3) 85 gpm with 35 percent cake solids. d. Maximum condition:
1) 145 gpm at 220 psig with 25 percent cake solids. e. Nameplate Driver hp: 150.
f. Feed Mechanism: Provide positive means of shearing cake to reduce apparent viscosity and ensuring that cake feeds properly to pumping elements. Use one of two methods:

1) Ribbon auger:

a) Ribbon auger attached to plate fixed to pump drive shaft extending through oversized extension tube.

b) Feed rate minimum of four times rated pump capacity. c) Support with heavy duty urethane liner in hopper.
g. Number of Stages: 4 minimum.
h. Pump Speed: 50 RPM (At design condition). i. Drive Type: Variable frequency.
j. Drive Configuration: Right angle drive; vertical orientation.

k. Discharge ANSI B16.5, 300 pounds; 8-inch diameter, minimum.
2.4 DEWATERED CAKE AND CAKE SILO TRANSFER PUMP ACCESSORIES A. Load cells:
1. Provide load cells and transmitter where shown on the Drawings.

2. Provide four load cells per pump on one controller to provide one weight signal to the control system.
3. Load cells suitable for installation in corrosive and humid environment.

4. Designed and installed so sensors can be replaced without removing load cell.
5. Sealed, 316 stainless steel.

6. Fully potted in NEMA 6P enclosure with watertight cable system.
7. Temperature range 50 – 100 degrees F.

8. Nonlinearity/Hysteresis Combined: 0.2 percent rated output.
9. Return to Zero: 0.05 percent rated output.

10. Kistler Morse Model LD II with SVS 2000 controller, Hardy Model ADVANTAGE Series Load Point HI LPRA with HI 4050 controller and associated junction box, Or Equal.

B. Provide run-dry protection for each pump consisting of a temperature probe installed in the pump stator for switching off the pump upon high temperature.

C. Boundary Layer Injection Rings:

1. Continuous annular ring to evenly introduce fluid around inner wall of pipe.

2. Wafer style for installation between ANSI B16.5 Class 400 flanges.

3. Provide multiple point fluid connection, 1/2 inch NPT, minimum 2 points.

4. From connection, provide injection rings at every 50 feet. D. Inlet Chutes (Hoppers):
1. Fabricate as indicated on the Drawings.

2. Provide flex connection as indicated on the Drawings.

3. Coordinate dimensions with conveyor supplier.

4. Provide flanged nozzles as shown for connection of rupture disk return line, as indicated on the Drawings.

E. Electrically Actuated Slide Gate:

1. Provide AISI 316 stainless steel frame.

2. Maximum vertical dimension of 4 inches excluding the electric motor operator.

3. Opening at least the full width of the pump trough.

4. Stainless steel minimum thickness is 1/4 inch and UHMW Polyethylene (PE) 3/16 inch minimum thickness.
5. The UHMW PE shall have a machined groove to accept the gate blade and give a positive seal.

6. Actuators:

a. Electric actuators meeting the requirements of Section 15101, Valve
Operators.

7. Control panels meeting the requirements of Section 16442, Control Panels. F. Cake Forcemain:
1. Provide 14-inch diameter welded steel pipe for conveying cake as shown on the
Drawings. Pipe shall be in accordance with Section 15008, Steel Pipe.

2. For fabricated fittings, refer to Drawings for size and location. Fittings shall be in accordance with AWWA standards with flanged joints and a 4 feet minimum turning radius.

G. Slip Injection Pumps:

1. Slip Injection Pumps:

a. For Dewatered Cake Transfer Pumps:

1) Tag Id’s: 15MPMP600; 15MPMP605; 15MPMP610; 15MPMP615;
15MPMP620; 15MPMP625; 15MPMP630; 15MPMP635

2) Liquid Pumped: Water

3) Design conditions:

a) Maximum Condition: 0.5 gpm at 400 psig. b) Minimum Condition: 0.25 gpm at 400 psig.
4) Nameplate Driver hp: 1.5

b. For Silo Cake Transfer Pumps:

1) Tag Id’s: 15JPMP911; 15JPMP913; 15JPMP915; 15JPMP917;
15JPMP919; 15JPMP921; 15JPMP923; 15JPMP925; 15JPMP927;
15JPMP929; 15JPMP931; 15JPMP933; 15JPMP935; 15JPMP937;
15JPMP939; 15JPMP941

2) Liquid Pumped: Water

3) Design Conditions:

a) Maximum Condition: 0.5 gpm at 250 psig. b) Minimum Condition: 0.25 gpm at 250 psig.
4) Nameplate Driver hp: 1.5

2. Rotor and Stator: Each pump shall be a minimum eight stage design for the dewatered cake slip injection and four stage design for the silo cake transfer slip injection employing a convoluted rotor operating in a similarly convoluted stator. The convolutions shall be configured to form a cavity between the rotor and stator, which shall progress from the pump's inlet to discharge port with the operation of the rotor. The fit between the rotor and stator at the point of contact shall compress the stator material sufficiently to form a seal and to prevent leakage from the discharge back to the inlet end of the pumping chamber. The stator shall be molded with a seal integral to the stator elastomer preventing the metal stator tube and the bonding agent from the elastomer from contacting the pumped liquid. Gaskets with clamp ring design can
be used to form this seal. Stators for the pumps shall have EPDM elastomer. The pump rotors shall be constructed of 316 stainless steel.

3. Rotor and Drive Train: Each pump rotor shall be driven through a positively sealed and lubricated pin joint. The joint shall be grease lubricated with a high temperature (450 degrees F), PTFE filled synthetic grease, covered with EPDM sleeve and positively sealed with hose clamps constructed of 304 type stainless steel. The shaft under the mechanical seal shall be constructed of 316 stainless steel.

4. Casing: NPT connections shall be provided at both the inlet and discharge ports. Casings shall be constructed of 316 type stainless steel. SHAFT SEALS AND BEARINGS: Shaft shall be sealed using a single-acting mechanical seal constructed of EPDM elastomer, carbon vs. silicon carbide faces, and 316 stainless steel metal parts. The shaft shall be solid through the mechanical seal area, but of a two part design which allows the mechanical seal and all other wetted rotating parts to be removed from the pump without disassembly of the pump or gear motor (if required) bearings. Bearings shall be located in the motor or gear motor as required and shall be designed to adequately withstand all radial and thrust loads imposed by the pump at the service conditions.

5. Motor and Drive Unit: Motor shall be 1.5 hp, 600 to 20 rpm gear motor, meeting the requirements of Section 16220, Electric Motors. TEFC High Efficiency, 480V 60
Hz with power cord. The controller housing shall be NEMA 4X Type 316 stainless steel and meeting the requirements of Section 16442, Control Panels. The control panel shall have a main circuit breaker with external operating handle interlocked with the door so that the door cannot be opened unless the breakers are in the OFF positions. The main breakers shall be pad-lockable in the OFF position. The control panel shall contain a variable frequency drive, control power transformer and indicating and control devices as shown on the Drawings.

H. Sludge Cake Pumping System Valves:

1. Ball Valves:

a) Valve Schedule:

(1) The following Valve Schedule establishes the tagging convention for ball valves on the Drawings related to the sludge cake pumping system. For valves indicated on the Drawings that are not included in the Valve Schedule, CONTRACTOR shall request confirmation of the tag number during the submittal review. CONTRACTOR shall provide all valves shown on the Drawings whether or not listed in the Valve Schedule.







15MFV702


15J-NP-160


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV814


15J-NP-160


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV817


15J-NP-160


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE







15JFV819


15J-NP-160


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV903


15J-NP-160


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV722


15J-NP-170


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE



15JFV834


15J-NP-170


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV837


15J-NP-170


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV839


15J-NP-170


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV904


15J-NP-170


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV638


15J-NP-180


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV742


15J-NP-180


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV854


15J-NP-180


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV857


15J-NP-180


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV859


15J-NP-180


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV905


15J-NP-180


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV762


15J-NP-190


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV874


15J-NP-190


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV877


15J-NP-190


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE







15JFV879


15J-NP-190


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15JFV906


15J-NP-190


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV641


15J-NP-200


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV642


15J-NP-200


BALL


14


AOV

OPEN/CLOSE,NC, FAIL CLOSE


CAKE


15MFV585


15M-NP-210
FULL
PORT BALL


14


MOV


OPEN/CLOSE, NO


CAKE


15MFV595


15M-NP-220
FULL PORT
BALL


14


MOV


OPEN/CLOSE, NC


CAKE


15MFV653


15M-NP-230
FULL
PORT BALL


14


MOV


OPEN/CLOSE, NC


CAKE


15MFV651


15M-NP-230
FULL
PORT BALL


14


MOV


OPEN/CLOSE, NO


CAKE


15MFV652


15M-NP-230
FULL
PORT BALL


14


MOV


OPEN/CLOSE, NC


CAKE


15MFV650


15M-NP-230
FULL
PORT BALL


14


MOV


OPEN/CLOSE, NC


CAKE



15MFV639



15M-NP-230

FULL PORT BALL



14



AOV



OPEN/CLOSE, NC



CAKE



15MFV640



15M-NP-230

FULL PORT BALL



14



AOV



OPEN/CLOSE, NC



CAKE


b) Ball Valves (6 inches and larger):

(1) CONTRACTOR shall meet the requirements as specified in Section
15106, Ball Valves.
2.5 FABRICATION FOR DEWATERED CAKE TRANSFER AND SILO CAKE TRANSFER PUMPS

A. Pump Body:

1. Provide body containing two (2) inspection ports 180 degrees apart.

2. Provide connections for seal water, drainage, and gauge connections. B. Rotor:
1. Rotor shall have a minimum of .010 inch thickness chromium nitride surface; Galvanic chrome plating in 633 Vickers hardness or 57hRc shall be acceptable if the pump manufacturer furnished an extended warranty for the rotor for two years after the contractors warranty for 12 months from beneficial use of the facility expires.

C. Stator:

1. Construct by bonding rubber-type material to inside of a steel tube.

2. Minimum 65 durometer hardness (Shore A). D. Drive Train:
1. Include crown gear-type or Cardan-type universal joints, seals, connecting rod, driveshaft, and shaft bearings.

2. Connect rotor drive shaft by a connecting rod equipped with two (2) crowned gear-type or Cardan-type factory grease/oil lubricated and positively sealed universal joints.

a. Joint unconditionally guaranteed by manufacturer to meet 10,000-hour operation at the required performance conditions.

3. Use universal joints to transmit thrust and torque while allowing the rotor to move through an eccentric path.

4. Joint shall be positively sealed and encased in a series 300 stainless steel cover to protect it from tramp metal and glass.

5. Joints shall be designed to withstand 60 pounds per inch in the suction casing.

6. Joints design shall allow for filling of the oil so that no air pockets exist inside the
Buna-N Sleeve.

7. The pumps shall be with a dedicated bearing frame and drive shaft that is solid and one-piece through the (2) tapered roller bearings and sealing area up to the concentrically rotating universal joint. Friction welded shafts are not allowed due to the likelihood of increased shaft run-out with high thrust loads. The gear reducer shall be sized for a minimum service factor of 1.5, net of any factors for thermal loading reductions.

8. Bearing ABMA L-10 Life: 50,000 hours at design operating conditions specified

9. Provide fittings for grease or oil lubrication of bearings.

10. Stuffing box:

a. Design for either grease lubrication or water seal.

b. Permit gland adjustment and repacking without dismantling pump.

c. The drive shaft under the packing shall have 0.010 inch thickness Chromium
Nitride coating for wear resistance.

E. Provide open throat suction flange, 24 inches x 36 inches minimum.
F. Base Plate:

1. Provide common base plate for pump, drive and motor.

2. Support discharge end of pump body on pivoting support assembly that permits free movement of the drive end to ensure that the load cells reflect the weight of material

3. Pump system will provide full restraint of axial loads imposed by the sweep elbows on the discharge.

4. Baseplate shall be hot dipped galvanized steel

5. All anchor bolts shall be 316 stainless steel.

PART 3 - EXECUTION

3.1 INSTALLATION

A. All materials and equipment shall be installed in a neat, workmanlike manner.

B. All wiring of the equipment shall be as specified under Division 16, Electrical, of these
Specifications.

C. All equipment specified herein shall be installed in accordance with the manufacturer's recommendations and the Drawings.

D. Where anchor bolts and other parts to be embedded in concrete are required, such parts shall be furnished to the site in advance of the equipment along with templates and instructions for their installation.

E. Such installation shall be done under Division 3, Concrete.

3.2 PAINTING

A. Shop painting and the surface preparation is a part of the Work specified in this section and shall be as specified in Section 09800, Protective Coatings. Stainless steel shall not be painted.

3.3 CLEAN-UP

A. Prior to start-up and field testing, all foreign matter shall be removed from the pumps, interconnecting piping, and spillage of lubricants used in servicing the equipment shall be cleaned from pumps, piping and concrete surfaces.

3.4 LUBRICATION REQUIREMENTS

A. All lubricants required for the first year of operation shall be provided for the system.

3.5 SPARE PARTS

A. The following spare parts shall be provided:

1. One (1) shaft sleeve.

2. One (1) rotor.

3. One (1) stator.

4. One (1) connecting rod with bushings.

5. One (1) set of connecting rod joint assemblies.
3.6 MAINTENANCE OF INSTALLED EQUIPMENT

1. Maintain the operability and functionality of all installed equipment between the time of installation and the commissioning period. See Specification section 01660 for requirements.

3.7 MANUFACTURER’S FIELD SERVICES

1. Furnish the services of authorized technical representatives of the Manufacturer to assist/inspect the installed equipment and to certify that the equipment has been properly installed and is ready to operate, train OCSD personnel, conduct pre-operational mechanical checkout of the equipment, place equipment into operation, optimize the performances of the equipment and perform the field performance testing.

2. Conduct multiple, separate site visits as follows:

a. Inspection of equipment installation – three visits

1) Cake Silos 1 and 3 (8 hours minimum)

2) Cake Silos 2 and 4 (8 hours minimum)

3) Thickening and Dewatering Facility Dewatered Cake Pumps (8 hours minimum)
b. Training of OCSD personnel. See Specification section 01820 for requirements. c. Commissioning. See Specification section 01810 for requirements. Number of
trips and hours shall be as required to meet all testing and commissioning
requirements, but shall not be less than 48 hours.

3.8 PUMP TESTS


A. Pump tests shall be performed for all equipment supplied under this section as outlined in Section 11210, Pumps and Equipment and Section 01810, Commissioning.

No comments:

Post a Comment