Section
01722
PROTECTION
OF ADJACENT CONSTRUCTION
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. This section covers
the CONTRACTOR's responsibilities for coordinating Work on this
Project and protecting in place key structures pipelines and
conduits.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following sections and divisions apply to the Work of this
section. Other sections and divisions of the Specifications, not
referenced below, shall also apply to the extent required for proper
performance of this Work.
1. Section 01140, Work
Restrictions
2. Section 02050,
Demolition
3. Section 02200,
Earthwork
4. Section 02634,
Existing Utilities
1.3
SUBMITTALS
A. The CONTRACTOR shall
submit reports and drawings documenting the results of pot-holing and
survey work for the pipelines listed below. CONTRACTOR also shall
submit pile installation drawings demonstrating that the proposed
pile locations will not damage any of these pipelines. These
submittals must be accepted by the ENGINEER before any excavation,
pile installation or pipeline demolition work can proceed in the
vicinity of these pipelines.
1. 72-inch Trickling
Filter Effluent pipe
2. 84-inch Interplant
pipe (in the vicinity of the pipe rack / screen wall)
3. 66-inch Primary
Effluent pipe (in the vicinity of the pipe rack / screen wall)
4. Twin 60-inch
Secondary Effluent pipe (Abandoned) (in the vicinity of the pipe rack
/ screen wall)
B. The CONTRACTOR
shall submit reports and drawings demonstrating how the
pipelines and conduit crossing the Tunnel 32 corridor will be
protected in place and maintained in operation during the
construction of Tunnel 32.
C. CONTRACTOR shall
submit shoring design submittals in accordance with the requirements
of Specification section 02200, Earthwork for the shoring located
along the following facilities:
1. 72-inch Trickling
Filter Effluent pipe
2. Tunnel 17
3. Digesters 9 and 10
D. CONTRACTOR shall
submit a plan for protecting the TFE pipe during access to the
Thickening and Dewatering Facility for shoring, excavation and
placement of materials and equipment.
1.4
WORK
BY OTHERS
A. OCSD, ENGINEER,
utilities, and others may be working within the project area while
the Work is in progress. If so, the CONTRACTOR shall schedule its
work in conjunction with these other organizations to minimize
interference with any of them.
B. Refer to the
GENERAL REQUIREMENTS, sections entitled “Construction Access and
Coordination” and “Concurrent Work Under Separate Contract”,
for additional information related to this Section.
1.5
RESPONSIBILITY
OF CONTRACTOR
A. If any part of the
Work depends, for proper execution or results upon the work of
others, the CONTRACTOR shall inspect and promptly report to the
ENGINEER any apparent discrepancies or defects in such work of
others that render it unsuitable for such proper execution and
results. Failure of the CONTRACTOR to do so shall constitute an
acceptance of the work by others as fit and proper except as to
defects which may develop in the work of others after execution of
the Work by the CONTRACTOR.
1.6
PROJECT
COORDINATION
A. The CONTRACTOR
shall be responsible for the coordination of all Work performed
under these Contract Documents; including scheduling of all Work,
delivery of equipment and materials, establishing the Work sequence,
and completion of the Work in accordance with the construction
schedule and the specified Time for Completion.
B. The CONTRACTOR
shall be responsible for the division and coordination of all work
performed by Subcontractors. Contracts between the CONTRACTOR
and Subcontractors shall completely describe the work to be
performed by each Subcontractor, and the division of work between
trades or crafts will be solely a matter for agreement between the
CONTRACTOR and its employees or Subcontractors. Based on the
Critical Path Method (CPM) construction schedule prepared in
accordance with the Contract Documents, the CONTRACTOR shall obtain
from each of its subcontractors a similar schedule and shall be
responsible for all parties maintaining these schedules, or for
coordinating required modifications.
PART 2 - PRODUCTS
(NOT USED)
PART 3 - EXECUTION
3.1
PROGRESS
MEETINGS
A. The ENGINEER shall
schedule and hold regular progress meetings at least once each week
and at other times as required by progress of the Work.
B. The purpose of the
meetings will be to review the progress of the Work, maintain
coordination of efforts, discuss changes in scheduling, and resolve
other problems that may develop. The meetings shall be attended by
the CONTRACTOR's superintendent and the ENGINEER. Attendance by
representatives of the CONTRACTOR's suppliers, manufacturers, and
other subcontractors, may be requested by the ENGINEER or the
CONTRACTOR.
C. The ENGINEER shall
preside at the meetings and provide for keeping and
distribution of the minutes.
D. Other meetings may be
held to discuss matters relative to the Work and its performance at
the request of the CONTRACTOR or the ENGINEER.
E. The CONTRACTOR and
appropriate subcontractors and/or suppliers shall participate in
quarterly, full day planning sessions with the ENGINEER to
coordinate the work.
3.2
COORDINATION
WITH OTHER CONTRACTORS
A. The CONTRACTOR
shall inform the ENGINEER, and all other parties with an
interest in this Project concerning its construction schedule and
shall coordinate its Work with that performed by others. The
CONTRACTOR shall make all necessary arrangements concerning the
timing, methods, and division of work required by any connections
between this Work and other work to be performed by others.
B. It shall be the
duty of the CONTRACTOR of this project to coordinate with the
contractors of other adjacent projects under construction to avoid
any delays or inconvenience to any project. The CONTRACTOR’s
attention is directed to the fact that other contractors will be
working in the areas where work under this Contract is being
performed. The following list includes known projects that will
occur concurrent to the CONTRACTOR’s work. The list is provided
for the CONTRACTOR’s convenience, however does not relieve the
CONTRACTOR’s responsibilities to coordinate with other projects
not listed herein.
Project
Description
|
Start
Construction
Date
|
Anticipated
End
Construction
Date
|
Project
Areas
|
Job No. P1-102:
Secondary
Activated
Sludge Facility 2
|
March
2009
|
April
2011
|
See
Attachment
A
|
Job No. P1-100:
Sludge Digester
Rehabilitation
at Plant No. 1
|
April
2010
|
September
2013
|
See
Attachment
A
|
Job No. J-109:
Cengen Cooling Water
S
ystem Replacement Project
|
October
2011
|
December
2013
|
See
Attachment
A
|
Job No. J-106:
Interplant Gas Line
Rehabilitation
|
March
2012
|
April
2013
|
|
Project
Description
|
Start
Construction
Date
|
Anticipated
End
Construction
Date
|
Project
Areas
|
Job No. J-71-8:
Rehabilitation of Odor
Control
Facilities
|
October
2012
|
February
2015
|
See
Attachment
A
|
Job No. P1-112:
Plant Water System
Rehabilitation
at Plant 1
|
January
2013
|
July
2014
|
|
Job No. J-33-3:
Power Monitoring and
Control
Systems
|
August
2011
|
November
2014
|
See
Attachment
A
|
Job No. J-36-1:
Joint GWRS Microfiltration Backwash Redirection
|
July
2013
|
October
2016
|
|
Job No. P1-113:
Trickling Filter
Covers
and Odor Control
|
August
2014
|
January
2016
|
|
Job No. P1-115:
Title 24 Access Compliance and Building Rehabilitation
|
May
2013
|
January
2018
|
|
3.3
RELATIONS
WITH OTHER CONTRACTORS
A. The CONTRACTOR
shall cooperate with all other contractors who may be
performing work on behalf of OCSD and workers who may be employed by
OCSD on any work in the vicinity of the Work to be done under this
Contract, and it shall so conduct its operations so as to
interfere to the least possible extent with the work of such
contractors or workers. The CONTRACTOR shall promptly make
good, at its own expense, any injury or damage that may be
sustained by other contractors or employees of OCSD, as a result of
actions or lack of action by the CONTRACTOR.
B. Any difference or
conflict which may arise between the CONTRACTOR and other
contractors or between the CONTRACTOR and workers of OCSD in regard
to their work shall be adjusted as determined by the ENGINEER. If
the Work of the CONTRACTOR is delayed because of any acts or
omissions by any other contractor, the CONTRACTOR shall have no
claim against OCSD on that account other than an extension of time.
3.4
EXISTING
STRUCTURES, PIPELINES AND CONDUITS A. General:
1. The dimensions and
elevations of existing structures and locations of existing
foundations, pipelines, conduits, cables, and equipment indicated on
the Drawings were taken for the most part from OCSD's records of the
existing wastewater treatment facilities and are not guaranteed for
accuracy.
2. It shall be the
responsibility of the CONTRACTOR to check all dimensions and
elevations of existing structures, foundations, pipelines, conduits,
cables, equipment, or other existing items, both above and below
ground, affected by or affecting the Work under this Contract, prior
to the start of construction or the ordering of materials and
equipment affected thereby.
3. The CONTRACTOR
shall be solely responsible for determining and bearing the cost of
all removal and salvage operations.
B. Tunnel 17:
1. Tunnel 17 runs
parallel to the north wall of the Thickening and Dewatering
Facility. This tunnel was built in 1964 and is not supported on
piles. CONTACTOR shall use caution during all construction
activities to avoid damage to Tunnel 17.
2. To minimize
potential damage to Tunnel 17, CONTRACTOR shall locate shoring for
the Thickening and Dewatering Facility as far as possible from the
south wall of Tunnel 17 and shall use a shoring system that will not
damage this tunnel during installation.
3. The shoring system
installed parallel to Tunnel 17 shall be left in place, except for
the top four (4) feet below final grade, which shall be removed.
The north wall of the Thickening and Dewatering Facility shall be
poured against the shoring.
C. Trickling Filter
Effluent Pipeline:
1. The 72-inch
diameter Trickling Filter Effluent (TFE) RCP pipeline is located on
the west and south side of the Thickening and Dewatering Facility.
This pipeline was installed in 2004. Plan and profile drawings for
the pipeline are provided as attachments to the Contract Documents.
2. Prior to beginning
any excavation, pipeline demolition or pile installation in the
vicinity of the TFE pipeline, CONTRACTOR shall perform extensive pot
holing along the length of the TFE from Tunnel 17 to the Trickling
Filter Secondary Effluent Junction Box No. 2. The pot holing shall
be sufficient to clearly establish the outside edges of the pipe on
both sides and the pipe profile for the entire pipe length. The
CONTRACTOR shall survey the pothole locations and prepare a map and
report documenting the location of the pipe.
3. CONTRACTOR shall
prepare a pile installation drawing for the Thickening and
Dewatering Facility and Solids Scrubbers, showing the horizontal and
vertical coordinates of each pile and their relation to the TFE
pipe. If any piles are found to be closer than 2 feet-0 inches to
the edge of the TFE pipe (edge to edge horizontal distance),
CONTRACTOR will consult with ENGINEER to adjust the pile location.
ENGINEER must accept final pile configuration plan before pile
installation can begin.
4. To minimize
potential damage to the TFE pipe, CONTRACTOR shall locate shoring
for the west wall of the Thickening and Dewatering Facility as far
as possible from the TFE pipe and shall use a shoring system that
will not damage the pipe.
5. The shoring
system installed along the west wall of the Thickening and
Dewatering Facility shall be left in place, except for the top four
(4) feet below final grade, which shall be removed. The west wall
of the Thickening and Dewatering Facility shall be poured against
the shoring.
6. CONTRACTOR shall
develop a plan for protecting the TFE pipe from damage due to
cranes, earth-moving equipment and other construction activities
needed to perform for shoring, pile installation, excavation and
placement of materials and equipment at the Thickening and
Dewatering Facility
D. Digester Nos. 9 and
10:
1. Tunnel 29 shall be
constructed between Digester Nos. 9 and 10. These tanks were built
in 1979 and are supported on piles. The District is concerned
about potential damage to the digesters due to undermining.
2. To minimize
potential damage to Digester Nos. 9 and 10, CONTRACTOR shall locate
shoring for Tunnel 29 as far as possible from the digester walls for
approximately 20 feet to either side of the centerline between
Digester Nos. 9 and
10, CONTRACTOR shall use
a shoring system that will not damage the digesters during
installation.
3. The shoring system
installed along Tunnel 29 shall be left in place for approximately
20 feet to either side of the centerline between Digester Nos. 9 and
10, except for the top
four (4) feet below final grade, which shall be removed. In this
40 foot section, the
north and south walls of Tunnel 29 shall be poured against the
shoring.
E. Pipelines Along
Pipe Rack / Screen Wall Alignment:
1. The pipe rack /
screen wall will cross or be in close proximity to 1) an 84”
Interplant pipe, 2) a 66” Primary Effluent pipe and 3) two 60”
Secondary Effluent pipes. The 84” and 66” pipes are in service.
The 60” pipes are abandoned.
2. Prior to beginning
any excavation, pipeline demolition or pile installation in the
vicinity of the four pipelines, CONTRACTOR shall perform extensive
pot holing of these pipelines between Stations 3+50 and 6+00 of the
pipe rack. The pot holing shall be sufficient to clearly establish
the outside edges of the pipes on both sides and the pipe
profiles in the area of the proposed pile installation.
The CONTRACTOR shall survey the pothole locations and prepare a map
and report documenting the location of the pipes.
3. CONTRACTOR shall
prepare a pile installation drawing for all facilities in the
vicinity of four pipes, showing the horizontal and vertical
coordinates of each pile and their relation to the pipes. If any
piles are found to be closer than 1-foot-0 inches to the edge of the
pipes (edge to edge horizontal distance), CONTRACTOR will consult
with ENGINEER to adjust the pile location. ENGINEER must accept the
final pile configuration plan before pile installation can begin.
F. Pipelines Crossing
Tunnel 32:
1. The following
pipelines and electrical conduits must be protected in place and
remain in service during construction of Tunnel 32:
a. 16-inch Steel High
Pressure Digester Gas
b. 12-inch Steel High Pressure Digester Gas
c. 3-inch Steel Natural Gas
d. 1-1/2-inch
Electrical Conduit
2. Prior to beginning
excavation, shoring or pipeline demolition in the vicinity of Tunnel
32, CONTRACTOR shall prepare a plan and drawings demonstrating how
these pipes and conduits will be supported and protected throughout
construction of Tunnel 32. ENGINEER must accept the pipe and conduit
protection plan before any work in this area can begin.
No comments:
Post a Comment