Section
01711
MOBILIZATION
AND DEMOBILIZATION
PART 1 - GENERAL
1.1
REQUIREMENTS
A. The CONTRACTOR shall
mobilize and demobilize in accordance with the Contract
Documents.
B. Mobilization shall
include the obtaining of all permits, preparing and
furnishing specified submittals, moving onto the site the dedicated
street sweeper, moving onto the Site all equipment necessary for the
Work; furnishing and erecting plants, temporary buildings, and other
construction facilities; and implementing security requirements; all
as required for the proper performance and completion of the Work.
Mobilization shall include the following principal items:
1. Moving onto the Site
all of the CONTRACTOR’s equipment required for the proper
performance and completion of the first sixty (60) days of work.
2. Installing temporary
construction power, wiring, communications facilities, and lighting
facilities.
3. Developing
construction water supply connections.
4. Providing on-site
sanitary facilities and potable water facilities.
5. Arranging,
preparing, and erecting CONTRACTOR's work and storage yard, and site
offices, parking, demarcation fencing in the staging area.
6. Complying with the
General Requirements, section entitled “Temporary Facilities” and
Section 01500, Temporary Facilities and Controls, and Section 01140,
Work Restrictions. Constructing and implementing access and
security features, as required, including, but not limited to, the
following:
a. Site Fencing
b. Construction Access
Gate c. Access Road Repair
d. Security Guards e.
Guard Station
f. Traffic Guard
7. Obtaining and
providing all required permits.
8. Posting all OSHA
required notices and establishment of safety programs.
9. Having the
CONTRACTOR's Management Team defined in Section 01010, Project
Management, at the job site.
10. Providing
furnishings, office equipment and utility services
for the CONTRACTOR's field offices as described in Section 01500,
Temporary Facilities and Controls.
11. Purchasing and
moving onto the Site the dedicated street sweeper as described in
Section 01140, Work Restrictions.
C. Prior to Final
Completion and Final Payment, the CONTRACTOR shall:
1. Dismantle and
remove all temporary construction power, wiring, communications
facilities, lighting facilities, work and storage yard, and Site
offices. The CONTRACTOR shall also remove all excess construction
materials, equipment, and associated site restoration.
2. Dismantle and
remove all construction water supply connections.
3. Dismantle and
remove on-site sanitary facilities and potable water facilities.
4. Dismantle and
remove security features, as required, including Site fencing
construction access gate, access road repair, security guards and
guard station.
1.2
SUBMITTAL
REQUIREMENTS
A. The following
submittals are due by the day indicated and must be approved by the
ENGINEER as a condition precedent to completion of Mobilization.
Submittals shall be submitted in accordance with the provisions
of the General Requirements sections entitled “Submittal
Procedures”.
Submittal
|
Due (Days from
Notice to Proceed)
|
Contract Documents
and Specification Section Reference
|
1.
Mobilization Plan
|
7
|
01711,
Mobilization and
Demobilization
|
2. Resumes for
CONTRACTOR’S Management Team
|
7
|
01010,
Project Management
|
3.
Resume for Project Scheduler
|
7
|
01300, Contractor’s
Construction
Schedule
and Reports
|
4.
Preliminary Schedule of Submittals
|
10
|
General
Requirements
|
5.
Preliminary Schedule of Values
|
10
|
General Conditions
& General
Requirements
|
6.
CONTRACTOR’s Safety Program
|
15
|
General
Requirements
|
7.
Project Signs
|
15
|
01580
|
8.
Staging Area Plan
|
15
|
Special Provisions,
sections entitled “Contractor’s Storage and Staging Area”
and Project Site Access” and as shown in the Plans under
“Contractor Work and Staging Area”
|
Submittal
|
Due (Days from
Notice to Proceed)
|
Contract Documents
and Specification Section Reference
|
9.
List of Permits and Licenses
|
30
|
General
Requirements,, Special
Provisions
and 01150, Permits
|
10.
Schedule of Values
|
30
|
General Conditions
and 01155, Measurement and Payment
|
11.
Baseline Construction Schedule
|
30
|
01300, Contractor’s
Construction
Schedule
and Reports
|
12. Unsuitable,
Contaminated, Non- Hazardous Materials Identification and
Disposal Plan
|
30
|
01140,
Work Restrictions, and
02200, Earthwork |
13. Storm Water
Management and
Control
Plans (Including SWPPP)
|
30
|
02270, Stormwater
Pollution
Prevention
Plan
|
14.
Noise Mitigation Plan
|
30
|
General
Requirements, section entitled “Environmental Control” and
01140, Work Restrictions
|
15.
Traffic Control Plan
|
30
|
General
Requirements, section entitled “Plant Access Roads”, Sections
01140, Work Restrictions, and 01575, Traffic Control, and as
shown in the Plans under “Contractor Work and Staging Area”,
|
16. Off-Site Parking
Plan (for information only; not for ENGINEER’s approval)
|
30
|
Special
Provisions, section entitled “Project Site Access” and
01140,
Work Restrictions
|
17.
Security Plan
|
30
|
Special
Provisions, section entitled “Project Site Access” and
01140,
Work Restrictions
|
18.
Odor Control Plan
|
30
|
General
Requirements, section entitled “Environmental Control” and
01140, Work Restrictions
|
19.
Inspection and Test Plan
|
30
|
01455, Special
Test and
Inspections
|
PART 2 - PRODUCTS
(NOT USED) PART 3 - EXECUTION
3.1
MOBILIZATION
PLAN
A. Within seven (7)
days after date of the effective date of the Notice to Proceed
(NTP), submit a mobilization plan to the ENGINEER for approval,
which shall include a breakdown showing the estimated value of each
component of Mobilization as described herein this Section, and
elsewhere in the Contract Documents.
B. The mobilization
plan shall include a bar chart schedule showing each item of
mobilization, mobilization submittals, scheduled start date,
finish dates, and total duration. The plan shall also list each
activity the CONTRACTOR expects to initiate in the first 120 days
following NTP, complete, with scheduled start date, finish date, and
total duration.
3.2
DEMOBILIZATION
PLAN
A. No later than 120
days-prior to the Final Completion date, submit a demobilization plan
to the ENGINEER for approval, which shall include a detailed
description of the work and a proposed schedule for accomplishing
demobilization from the Site.
B. The plan shall
contain descriptions of demobilization activities, sufficiently
detailed and divided into components, that it will enable
OCSD and the ENGINEER to satisfactorily monitor and measure the
CONTRACTOR's progress toward achieving full demobilization from the
Site. The plan shall also contain a recovery schedule and
mitigation efforts should it be necessary to implement
changes to the Contract Completion Date.
C. The demobilization
plan shall include a bar chart schedule listing each activity in the
demobilization plan, complete with scheduled start date, finish date,
and total duration.
3.3
PAYMENT
FOR MOBILIZATION AND DEMOBILIZATION
A. Payment for
Mobilization and Demobilization is described in the General
Conditions and Section 01155, Measurement and Payment.