Section 02374
DRILLED PIERS - LOAD TESTING
PART 1 –
GENERAL
1.1 THE REQUIREMENT
A. The Work covered
under this section consists of furnishing all plant, labor equipment,
appliances, design and materials and performing all operations in
connection with dynamic and static load testing of piles.
Installation of piles is covered under Section
02373 – Drilled Piers.
Pile load testing shall be designed to verify the required load
carrying capacity for the installation of production piles.
B. The CONTRACTOR shall
retain a Professional Engineer registered in the State of California
with experience on at least five similar projects to supervise or
perform all functions associated with performing the static pile load
tests which shall be observed by the ENGINEER. The CONTRACTOR’s
professional Engineer shall evaluate the test results in accordance
with these Specifications. The results shall be sealed by the
CONTRACTOR’s Professional Engineer and submitted to the ENGINEER
for review and acceptance.
C. Piles required to be
tested:
1. Perform Static Load
Testing in accordance with Article 3.1 on the following piles. The
piles selected for testing shall be production piles acceptable to
the ENGINEER, or extra piles placed specifically for testing at
locations beneath the indicated structures acceptable to the
ENGINEER. Reaction piles shall be extra piles placed specifically for
testing and shall not be used for production piles.
a. Two (2) piles under
Zone H (Typical 130 kip vertical capacity)
b. Two (2) piles under
Zone A (Typical 160 kip vertical capacity)
c. Two (2) piles under
Zone E and Zone G (Typical 200 kip capacity)
d. Two (2) piles under
Zone C (Typical 240 kip capacity)
2. Tension Load Testing.
Not required unless specifically requested by the ENGINEER; except
that deformation dial gages shall be installed on each of the
reaction piles and be monitored during load tests.
3. Lateral Load
Testing. Not required unless specifically requested by the
ENGINEER.
1.2 RELATED WORK
SPECIFIED ELSEWHERE A. Section 02373, Drilled Piles.
1.3 SUBMITTALS
A. The CONTRACTOR shall
submit at least the following to the ENGINEER in accordance with the
General Requirements.
1. A dimensional sketch
of the loading arrangement.
2. Testing and
measuring equipment used in the load test, including jack,
deformation dial gages, pressure gauge, and load cell calibrations.
3. Proposed test pile
locations.
4. Proposed reaction
pile locations.
5. Certifications of
applied loads.
6. Load test records
and report.
B. Locations of test
and reaction piles shall be acceptable to the ENGINEER.
1.4 REFERENCE
SPECIFICATIONS, CODES, AND STANDARDS
A. Comply with the
reference specifications of the General Requirements.
B. Comply with the
current provisions of the following Codes and Standards.
1. Commercial
Standards.
ASTM D1143
ASTM D3689
PART 2 – PRODUCTS
2.1 STATIC LOAD
TESTING
A. All equipment and
materials required for load testing of the test piles shall be
furnished by the CONTRACTOR. Load test piles may be incorporated
into the Work as permanent piles provided the piles meet the
required capacity and are undamaged. Permanent piles shall not be
used as reaction piles.
B. Load testing
shall consist of a minimum of 2 axial compressive load tests.
C. The load test
apparatus shall be capable of sustaining loads at least 40 percent
greater than the maximum anticipated load. The capacity of the
loading apparatus shall be sufficient to operate under the
anticipated loading without incurring damage or interrupting the
load test. A sketch of the proposed method of testing shall be
submitted to the ENGINEER for acceptance before the test piles are
installed.
D. The pistons shall
have sufficient strokes to accommodate the anticipated test beam
deflections of hydraulic jacks and test pile movements, and the
pressure gauge shall be certified for accuracy by an independent
testing laboratory at the expense of the CONTRACTOR. The hydraulic
jack shall have a capacity sufficient to preclude the use of
multiple jacking systems. The applied loads shall be verified and
recorded by a calibrated load cell certified for accuracy of at
least 2 percent of the applied load by an independent laboratory.
Copies of the certifications shall be submitted to the ENGINEER.
E. The test piles
shall be installed at the same cutoff elevation as the production
piles.
2.2 REACTION PILES
A. The CONTRACTOR
shall install reaction piles as required around the test piles.
B. Reaction piles
shall be drilled piers similar in construction to permanent piles;
but after testing, reaction piles shall be abandoned in place and
not considered part of the permanent structure.
C. The spacing,
reinforcing, and number of reaction piles shall be selected by the
CONTRACTOR to coordinate
with the pile testing apparatus and procedures.
D. All
information on the reaction piles shall be submitted to the
ENGINEER.
PART 3 – EXECUTION
3.1 STATIC LOAD
TESTING
A. Axial Compressive
Load:
1. The axial
compressive load test and report of the results shall be conducted
and written in accordance with ASTM D1143, except as modified or
supplemented by these specifications.
2. Axial compressive
load testing shall be conducted in accordance with ASTM D1143, 5.6 –
Quick Load Test Method for Individual Piles. Load increments shall
be based on the working load carrying capacity (design load) for the
pile, and the full test load shall be at least twice the working
load carrying capacity.
B. Net Settlement:
1. Net settlement of
the test pile shall be recorded as a function of load applied and
time. Net settlement shall be defined as the elevation difference of
the butt prior to loading and after unloading of the test pile.
Measurement of movement shall be in accordance with ASTM D1143, 6.4 –
Readings for Quick Load Test Method.
C. Load Test Acceptance:
1. Pile failure shall
be defined as a net settlement exceeding 0.01 inch per ton of the
test load, but not exceeding 0.5 inches. If any test pile
experiences a net settlement in excess of that defined by pile
failure at or before the full test load has been attained shall be
rejected, the pile load test shall be halted, and the test results
submitted in accordance with the load test records paragraph of this
specification.
D. Load Test Records:
1. Load test data shall
be reduced in both numerical and graphical form. The reduced data
shall be submitted to the ENGINEER for review and acceptance. Six
copies of the load test report shall be submitted on forms acceptable
to ENGINEER. In addition to pile installation records required
by Section 02373 test pile data recorded shall include, but not
be limited to, the following:
a. Test pile number and
location. b. Date and time of testing.
c. Load and settlement
readings. Both applied loads and loads recorded by the load cell
shall be submitted for all settlement readings.
d. Time-load-settlement
curve.
2. All data recorded
shall be certified as correct.
3.2 OTHER PILE LOAD
TESTING
A. Tension
Capacity:
In the event design tension pile capacities are required to be
tested, the tension capacity for individual piles will be determined
in accordance with the requirements of ASTM D3689 or an approved
method of analysis based on a minimum safety factor of 3. Load test
records shall be similar to Article 3-1.D.
B. Lateral Capacity: In
the event design lateral pile capacities are required to be tested,
the ENGINEER will determine an appropriate test method.
No comments:
Post a Comment