Section
02730
GRAVITY
PIPELINE TESTING
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. The CONTRACTOR shall
furnish all tools, equipment, materials, and supplies and shall
perform all labor required to complete the Work as indicated on the
Drawings and specified herein.
B. This section covers
the performance of all pipeline flushing and testing, complete, for
sanitary sewer system piping as specified herein and in
accordance with the requirements of the Contract Documents.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following sections and divisions apply to the Work of this
section. Other sections and divisions of the Specifications, not
referenced below, shall also apply to the extent required for proper
performance of this Work.
1. Section 02200,
Earthwork
2. Section 02726,
Manhole and Pre-Cast Vault Construction
1.3
REFERENCE
SPECIFICATIONS, CODES, AND STANDARDS
A. All Work specified
herein shall conform to or exceed the applicable requirements of the
referenced portions of the following publications to the extent that
the provisions thereof are not in conflict with other provisions of
these Specifications.
B. Comply with the
applicable editions of the following codes, regulations and
standards.
1. Industry Standards:
ASTM C1244
Standard Test Method for Concrete Sewer Manholes
by the Negative Air Pressure (Vacuum) Test Prior to Backfill
SSPWC Section 306-1.4
“Green Book”, Standard Specifications for
Public Works
Construction, Testing Pipelines
PCAP
Pipeline Assessment and Certification Program by
NASSCO
2. Other Standards:
NASSCO
National Association of Sewer Service
Companies
C. Comply with the
applicable reference Specifications as directed in the General
Requirements and the
Supplemental General Requirements.
1.4
CONTRACT
SUBMITTALS
A. Submittals shall
be made in accordance with the General Requirements,
Supplemental General Requirements and as specified herein.
B. The CONTRACTOR
shall submit in writing all proposed plans for testing, and for
water conveyance, control, and disposal. The CONTRACTOR shall also
submit written notice 48 hours in advance of the proposed testing
schedule for review and concurrence of the ENGINEER.
1.5
QUALITY
ASSURANCE
A. Inspection:
After installation, the CONTRACTOR shall demonstrate that all
manholes have been properly installed, level, with tight joints, at
the correct elevations and orientations in accordance with the
Contract Documents.
PART 2 - PRODUCTS
2.1
GENERAL
A. Temporary valves,
plugs, bulkheads, and other air pressure testing and water control
equipment and materials shall be provided by the CONTRACTOR subject
to the ENGINEER’s review. No materials shall be used that
will be injurious to pipeline structure and future function.
Air test gauges shall be laboratory-calibrated annually and shall be
recalibrated by a certified laboratory at the CONTRACTOR's expense
prior to the leakage test, only if required by the ENGINEER.
B. ENGINEER or
ENGINEER’s representative shall be present during testing and
shall be notified of the time and place of testing at least 3 days
prior to commencement of the Work. All Work shall be performed to
the satisfaction of ENGINEER.
PART 3 - EXECUTION
3.1
GENERAL
A. Unless otherwise
specified, water for testing will be furnished by OCSD inside the
plant areas; however, the CONTRACTOR shall make all necessary
provisions for conveying the water from an OCSD-designated source to
the points of use. Outside the treatment plants, the CONTRACTOR
shall furnish and pay for water for testing.
B. All pipeline
trenches shall be backfilled and compacted per Section
02200, Earthwork, prior to testing of pipe.
C. Release of water
from pipelines, after testing has been completed, shall be
performed as reviewed by the ENGINEER.
D. All testing
operations shall be performed in the presence of the ENGINEER.
3.2
TESTING
OF PIPELINE
A. General:
All gravity sewer pipes and service laterals shall be tested for
exfiltration and/or infiltration and deflection, as specified. All
manholes shall be tested for leakage, as specified. Manholes shall
be tested prior to backfill placement; whereas, all pipe shall be
backfilled and compacted prior to testing. All leakage tests of
sanitary sewer systems shall be in conformance with SSPWC Section
306-1.4. For pressure sewers (force main) tests, the water pressure
shall be measured at the lowest point of the pipeline section being
tested.
B. Water Exfiltration
Test shall be in conformance with SSPWC Section 306-1.4.2.
C. Water Infiltration
Test shall be in conformance with SSPWC Section 306-1.4.3.
Unless otherwise specified, infiltration will be measured by the
CONTRACTOR using measuring devices accepted by the ENGINEER.
D. Air Pressure Test
shall be in conformance with SSPWC Section 306-1.4.4.
E. At the CONTRACTOR's
option, joints may be air-tested individually, joint by joint, with
the use of specialized equipment. The CONTRACTOR shall submit its
joint testing procedure for the ENGINEER’s review and acceptance
prior to testing. Prior to each test, the pipe at the joint shall
be wetted with water. The maximum test pressure shall be
3.0 pounds per inch.
The minimum allowable pressure drop shall be 1.0 pounds per inch
over a 30-second test period.
F. Water Pressure Test
shall be in conformance with SSPWC Section 306-1.4.5.
G. Deflection
Test:
All flexible and semi-rigid main line pipe shall be
tested in accordance with SSPWC Sections 306-1.2.12 and 306-1.2.13
for deflection, joint displacement, or any other obstruction by
passing a rigid mandrel through the pipe by hand, not less than 30
days after completion of the trench backfill, but prior to permanent
resurfacing. The mandrel shall be a full circle, solid cylinder, or
a rigid, nonadjustable, odd-numbered leg (9-leg minimum) steel
cylinder, accepted by the ENGINEER as to design and manufacture. The
circular cross section of the mandrel shall have a diameter of at
least 95 percent of the specified average inside diameter of the
pipe and the minimum length of the circular portion of the mandrel
shall be equal to the nominal diameter of the pipe. Obstructions
encountered by the mandrel shall be corrected by the CONTRACTOR.
3.3
TESTING
OF MANHOLES
A. All sewer manholes
shall be vacuum tested per ASTM C1244 for leakage after
installation, but prior to being backfilled. Prior to vacuum
testing, all manholes shall be visually inspected for leaks. All
leaks or cracks shall be repaired by the CONTRACTOR, prior to vacuum
testing. The repair shall be subject to acceptance by the ENGINEER.
All pipes entering the manhole shall be sealed at a point outside
the manhole walls so as to include testing of the pipe/manhole
joints. The CONTRACTOR shall then be required to make all necessary
repairs and retest the manhole. The exterior of the manhole shall
be inspected during this period for visible evidence of leakage.
B. Manholes and
appurtenances shall be as watertight and free from infiltration as
possible. Any evidence of leakage shall be repaired at the expense
of the CONTRACTOR. The repair shall be subject to acceptance by the
ENGINEER.
C. When, in the
ENGINEER’s opinion, the groundwater table is too low to permit
visual detection of leaks, project manholes shall be hydrostatically
tested.
D. All costs of testing
manholes for watertightness shall be included in the appropriate
contract unit price.
No comments:
Post a Comment