Section
02050
DEMOLITION
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. The CONTRACTOR
shall furnish materials, equipment and labor necessary to
perform and complete demolition work called for in the Contract
Documents.
B. The WORK includes
demolition of certain areas of Plant 1, foundations, walls, slabs,
supports, piping, mechanical, electrical, instrumentation, to
facilitate new construction as shown and specified. In addition,
various yard piping, electrical, etc. shall be cut, abandoned
and capped or removed.
C. Building structures,
foundations, slabs, roofs and supporting walls shall be
demolished as shown, in an orderly and careful manner.
D. The WORK shall
include, but not be limited to, removal of existing furniture,
built-in cabinetry, piping, electrical (fixtures, conduits and
wiring), mechanical (ducts and equipment), floors, walls, ceilings,
doors, windows, wood or metal framing, masonry, concrete slabs,
concrete walls and asphaltic paving.
E. Manufactured
articles, materials, equipment, and accessories shall be demolished
as shown on the Contract Drawings and in accordance
with the manufacturer's specifications and recommendations, and
industry standards, unless otherwise shown or specified.
F. Building utilities
shall be disconnected, removed, capped and identified as necessary
and as shown.
G. The CONTRACTOR shall
notify “DIGALERT” 48 hours prior to beginning excavation,
tunneling or boring operations.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following sections and division apply to the Work of this
section. Other sections and divisions of the Specifications, not
referenced below, shall also apply to the extent required for proper
performance of this Work.
1. Section 01110,
Summary of Work
2. Section 01140, Work
Restrictions
3. Section 01500,
Temporary Facilities and Controls
4. Section 01575,
Traffic Control
5. Section 02110,
Clearing, Grubbing, and Stripping
6. Section 02200,
Earthwork
1.3
REFERENCE
SPECIFICATIONS, CODES, AND STANDARDS
A. All Work specified
herein shall conform to or exceed the applicable requirements of the
referenced portions of the following publications to the extent that
the provisions thereof are not in conflict with other provisions of
these Specifications.
B. Comply with the
applicable editions of the following codes, regulations and
standards:
1. Codes and
Regulations:
29 CFR 1910
Code of Federal Regulations, Title 29, Part
1910, U.S.
Occupational Safety and Health
Standards (OSHA)
29 CFR 1926
Code of Federal Regulations, Title 29, Part
1926, U.S. Safety and
Health Regulations for
Construction
(OSHA)
CCR
California Code of Regulations, Title 8,
Industrial
Relations (Cal/OSHA)
CCR
California Code of Regulations, Title 22,
Social
Security
CCR
California Code of Regulations, Title 24, Part
2, California Building Code (CBC)
2. Industry Standards:
SSPWC
“Green Book,” Standard Specifications for
Public
Works Construction
C. Comply with the
applicable reference Specifications as directed in the General
Requirements and the
Additional General Requirements.
1.4
CONTRACTOR
SUBMITTALS
A. General:
Submittals shall be made in accordance with the General
Requirements, Additional General Requirements, and as specified
herein.
B. Demolition
Schedule:
The CONTRACTOR shall submit a complete coordination schedule for
demolition work, including shut-off and continuation of utility
services, with the ENGINEER’S acceptance prior to start of the
Work. The schedule shall indicate proposed methods and operations
of facility demolition, and provide a detailed sequence of
demolition and removal work to ensure uninterrupted operation of
occupied areas.
1.5
QUALITY
ASSURANCE
A. Comply with the
applicable reference Specifications as specified in the General
Requirements, Additional
General Requirements, and as specified herein.
B. Pre-Demolition
Conference: Conduct conference at Project Site. Review methods and
procedures related to demolition including, but not limited to:
1. Inspect and discuss
conditions of construction to be demolished.
2. Review structural
load limitation of structures.
3. Review and finalize
demolition schedule and verify availability of materials, demolition
personnel, equipment, and facilities needed to make progress and
avoid delays.
4. Review requirements
of work performed by other trades that rely on substrates exposed by
demolition operations.
5. Review areas where
existing construction is to remain and requires protection.
1.6
SITE
CONDITIONS
A. The location and
general condition of the facilities to be demolished are shown on
the Drawings and listed in the Specifications. The CONTRACTOR shall
make allowance in its Bid for actual condition of facilities to be
demolished.
PART 2 - PRODUCTS
(NOT USED) PART 3 - EXECUTION
3.1
GENERAL
A. The demolition of
designated portions of structures and appurtenances shall be in
accordance with applicable OCSD, city, county, state, and federal
regulations; and after obtaining required permits, and filing
required reports.
B. Comply with the
California Code of Regulations, Title 24, California Building Code.
C. Comply with the
California Code of Regulations, Title 8, Title 22, Title 26 and
obtain the required permits.
3.2
OCCUPANCY
AND POLLUTION CONTROL
A. Water sprinkling,
temporary enclosures, chutes, and other suitable methods shall be
used to limit dust and dirt rising and scattering in the air.
Comply with government regulations pertaining to environmental
protection.
B. Water shall not be
used when it creates hazardous or objectionable conditions such as
ice, flooding, or pollution.
C. Water contaminated
with sediment or hazardous or toxic materials shall not be
allowed to run off into the public storm drain system (including
street gutters). Such runoff shall be intercepted, collected and
disposed of according to existing environmental regulations.
3.3
PROTECTION
A. Safe passage of
persons around area of demolition shall be ensured. Operations
shall be conducted to prevent damage to adjacent buildings,
structures, other facilities, and people.
B. Interior and
exterior shoring, bracing, or supports shall be provided to prevent
movement, settlement or collapse of structures to be
demolished, and to adjacent facilities to remain.
C. Existing landscaping
materials, structures, and appurtenances, which are not to be
demolished shall be protected and maintained as necessary and in
accordance with General Requirements, Additional General
Requirements, General Conditions, and as specified herein.
D. The CONTRACTOR shall
protect and maintain conduits, drains, sewers, pipes, and wires that
are to remain on the property.
3.4
STRUCTURE
DEMOLITION
A. All structures,
equipment, piping, valves, panels, and I&C components to be
demolished shall be red spray painted with an “X” mark prior to
the pre-demolition walkthrough.
B. For all structures
to be demolished the electrical wiring shall be removed before
demolition process starts. Demolition of wiring means removal of all
wires from source to load.
C. Building structures
and appurtenances shall be demolished as shown on the
drawings and required to complete work in conformance with governing
regulations.
D. Small structures may
be removed intact when acceptable to the ENGINEER and approved by
authorities having jurisdiction.
E. Demolition shall
proceed in a systematic manner, in accordance with permits and
approved submittals.
F. Concrete and
masonry shall be demolished in sections. Use bracing and shoring to
prevent collapse.
G. Demolition equipment
shall be dispersed throughout the structure and demolished materials
removed in a timely manner to prevent excessive loads on supporting
walls, floors or framing.
H. Demolition Work
shall be phased to correspond with other Work and maintain
existing facilities operating as described in Section 01140, Work
Restrictions.
I. In the existing
areas and buildings, remove all items designated to be demolished on
the Plans including all attached ancillary features such as piping,
seal water piping, valves, fittings, motors, equipment bases,
concrete equipment pads, belt guards, supports, anchor bolts, wires,
conduit, switches, control stations, instrumentation and other
related items including the following:
1. Building M requires
removal and disposal of equipment and appurtenances as shown on the
Plans including four belt filter presses, one belt conveyor, two
belt press control panels, three FRP polymer mixing tanks, ten
polymer mixing solution pumps and all designated interconnecting
piping, valves and fittings within the building. Remove and dispose
of all foul air ductwork inside and outside Building M.
Remove and dispose all
other items as shown on the Plans. The CONTRACTOR shall protect in
place the Building M structure, lighting, HVAC, crane rails, drain
piping, sump pumps and the MCC room. The CONTRACTOR shall replace
existing utility trench gratings in kind per the grating
specifications.
2. Building M sludge
feed pumps and plant water booster pumps shall be removed and
disposed of as shown on the Plans including four sludge feed pumps,
two grinders, three plant water booster pumps, and all designated
interconnecting piping, valves, and fittings. The CONTRACTOR shall
protect in place the designated drain piping, plant water piping,
and sump pumps.
3. Building M cake
transfer shall be removed and disposed of as shown on the Plans
including three sludge cake transfer pumps, three hydraulic power
unit pumps, one conveyor, three hoppers, three screw augers,
miscellaneous handrails, stairs, structural beams and supports,
Tunnel 12 piping and all designated interconnecting piping, valves,
and fittings. The CONTRACTOR shall protect in place the designated
drain piping, and sump pumps.
4. Building C requires
removal and disposal of equipment and appurtenances as shown on the
Plans including four belt presses, one belt conveyor, four belt
press control panels, lighting, HVAC, belt filter press equipment
pads, above grade drain piping, and all designated interconnection
piping, valves and fittings with the building. Remove and dispose
doors, door frames, windows, and window frames, metal siding,
existing roofing membrane, insulation, and steel columns and beams.
Remove and dispose of all foul air ductwork inside and outside of
Building C. Remove and dispose all other items as shown on the
Plan. The CONTRACTOR shall protect in place the designated plant
water piping, the reclaimed water piping, sump pumps, the pipe
trench, the control room and the electrical room. The CONTRACTOR
shall replace existing utility trench gratings in kind per the
grating specifications.
5. Building C sludge
feed pumps shall be removed and disposed of as shown on the Plans
including four sludge feed pumps, two grinders, and all designated
interconnecting piping, valves, and fittings. The CONTRACTOR shall
protect in place the designated drain piping, plant water piping,
reclaimed water piping, high pressure air piping, and sump pumps.
6. Building C cake
transfer shall be removed and disposed of as shown on the Plans
including two sludge cake transfer pumps, two hydraulic power unit
pumps, one conveyor, two hoppers, two screw augers, miscellaneous
handrails, stairs, structural beams and supports, and all designated
interconnecting piping, valves, and fittings. The CONTRACTOR shall
protect in place the designated drain piping, and sump pumps.
J. Grind down existing
reinforced concrete equipment pads, for pumps, grinders, pipe
supports, and other items, to match adjacent existing pavement.
Embedded reinforcing steel, and anchor bolts shall be cut off one
inch below the existing surrounding slab. The slab shall be patched
with non-shrink grout to restore a smooth walking surface to match
the existing adjacent undisturbed slab surface.
K. In areas where
demolition is shown on the Plans, cut back flush and seal any pipe
stub-outs remaining, and remove exposed piping, conduits, fixtures,
J-boxes, light fixtures, water fixtures, and supports. Switches,
receptacles, and boxes shall also be removed. Concealed piping and
conduits shall be removed or capped and abandoned as necessary to
facilitate the remodeling work. All other items shall be removed as
shown.
3.5
BELOW-GRADE
DEMOLITION
A. Footings,
foundation walls, roots, below-grade construction and concrete slabs
on grade shall be demolished and removed, or as indicated on the
Contract Drawings.
B. Below-grade areas
and voids resulting from demolition of structures shall be
completely backfilled using structure backfill in accordance with
Specification section
02200, Earthwork.
C. After fill and
compaction, surfaces shall be graded to meet adjacent contours and
to provide flow to surface drainage structures, or as shown.
3.6
DISPOSAL
OF DEMOLISHED MATERIALS
A. Demolition and
removal of debris shall be conducted to ensure minimum interference
with roads, streets, walks, and other adjacent occupied or used
facilities which shall not be closed or obstructed without
permission from the DISTRICT. Alternate routes shall be provided
around closed or obstructed traffic ways.
B. Site debris,
rubbish, and other materials resulting from demolition operations
shall be removed at the CONTRACTOR'S expense. Burning of removed
materials from demolished structures shall not be permitted on site.
C. The CONTRACTOR shall
provide a schedule for approval by the ENGINEER, for removal of
demolished materials. Removal and disposal shall be performed in a
timely manner.
3.7
DISPOSAL
OF NON-FRIABLE ASBESTOS
A. If non-friable
asbestos cement pipe (ACP) is identified, the CONTRACTOR shall
employ adequate care to maintain the pipe in a non-friable
condition. Removal of ACP shall be in whole sections where
possible. Cutting or breaking of ACP to facilitate removal shall
be in compliance with California Regulations, Title 8, Section 5208.
At a minimum, the CONTRACTOR shall follow the following
requirements for ACP that is to be cut or broken:
1. The CONTRACTOR
shall evacuate the area of unauthorized and untrained
personnel, post warning signs, and provide a demarcation zone and
adequate barriers to keep unauthorized personnel out of the area.
2. The CONTRACTOR
shall provide personal protective equipment consisting at least of a
respirator and disposable clothing to asbestos accredited workers
performing the cutting or breaking of ACP. Respiratory
protection shall be in accordance with the requirements of
California Regulations, Title 8, Section 5144.
3. The area to be cut
or broken shall be adequately wetted with amended water to reduce
fiber emission. The method employed by the CONTRACTOR shall
minimize fiber release. Power saw cutting will not be allowed.
All related debris from the cutting or breaking of ACP shall be
considered friable. The CONTRACTOR shall dispose of friable
material in accordance with California Regulations, Title 22.
4. All waste generated
and ACP shall be wrapped in 6 mil polyethylene sheeting or bags and
shall be properly transported and disposed of.
B. The CONTRACTOR
is responsible for all ACP removal and associated
contamination. CONTRACTOR shall coordinate with local landfill
regarding disposal of non-friable ACP acceptance requirements.
CONTRACTOR shall submit removal and disposal plan prior to beginning
demolition.
C. Payment for disposal
of non-friable asbestos-containing materials shall be included in
the lump sum Bid price for demolition and no separate payment will
be allowed.
3.8
DISPOSAL
OF FRIABLE ASBESTOS
A. Friable
asbestos-containing materials is defined as material that can be
crumbled, pulverized, or reduced to powder by hand pressure. All
friable asbestos-containing materials shall be considered as
hazardous waste and shall be transported by a licensed hazardous
waste hauler. Procedures for handling friable asbestos-containing
material shall conform to all applicable laws and codes and as
detailed in AQMD rule number
1403. Friable asbestos
containing materials shall be disposed of at an approved hazardous
waste landfill. CONTRACTOR shall submit removal and disposal plan
prior to beginning demolition and confirmation that material shall
be handled by technicians certified by Cal-OSHA.
B. Upon discovery of
friable asbestos, the CONTRACTOR shall immediately notify the
ENGINEER
C. Payment for the
disposal of friable asbestos-containing materials shall be included
in the lump sum Bid price for demolition and no separate payment
will be allowed.
3.9
PATCHING
AND REPAIRING
A. The CONTRACTOR
shall provide patching, replacing, repairing, and refinishing of
damaged areas involved in demolition as necessary to match the
existing adjacent surfaces whether shown or not shown or not shown
on the Drawings, with materials and procedures approved by the
ENGINEER.
B. The CONTRACTOR
shall repair all damages caused to adjacent facilities by
demolition as directed by the ENGINEER at no cost to OCSD.
C. The CONTRACTOR shall
make a detailed inspection after patching and repairing has been
completed, and shall carefully remove splattering of mortar from
adjoining work (particularly, but not limited to, plumbing fixtures,
trim, tile, and finish metal surfaces), and repair any damage caused
by such cleaning operations.
3.10
CLEANING
A. During and upon
completion of work, the CONTRACTOR shall promptly remove unused
tools and equipment, surplus materials, rubbish, debris, and dust
and shall leave areas affected by work in a clean condition,
acceptable to the ENGINEER, in accordance with Paragraph entitled
“Environmental Control” of the General Requirements.
B. Clean adjacent
structures and facilities of dust, dirt, and debris caused by
demolition, as directed by the ENGINEER, and return adjacent areas
to the condition that existed prior to start of work.
C. The CONTRACTOR shall
remove and legally dispose of demolished materials and debris from
the site.
D. The CONTRACTOR shall
clean and sweep the street and road daily.
3.11
SALVAGE
A. OCSD and CONTRACTOR
shall tag all salvageable items. The tag shall indicate what the
item is, the location and equipment it was removed from, and the date
of removal.
B. The following items
shall be salvaged by the CONTRACTOR:
1. Building M –
Existing RIO I/O chassis with all cards and PLC processors with
chassis and power supplies.
2. Truck Loading
Facility – HMI Workstation
C. The CONTRACTOR shall
deliver all salvaged items to the location designated by the
DISTRICT upon approval of
the ENGINEER.
D. All non-salvageable
items shall be removed at the CONTRACTOR's expense.
No comments:
Post a Comment