Section
02110
CLEARING,
GRUBBING, AND STRIPPING
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. CONTRACTOR shall
furnish all tools, equipment materials and supplies and shall perform
all labor to complete the work associated with removal of all natural
and artificial material from the designated areas of Work as
indicated in the Contract Documents.
B. This Work shall also
include the protection from injury and preservation of existing
improvements, adjacent property, utility vegetation and existing
objects designated to remain.
C. Prior to commencing
the Work, obtain acceptance from the ENGINEER regarding methods to be
used and disposal of removed materials.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following sections and divisions apply to the Work of this
section. Other sections and divisions of the Specifications, not
referenced below, shall also apply to the extent required for proper
performance of this Work.
1. Section 02200,
Earthwork
2. Section 02050,
Demolition
1.3
REFERENCE
SPECIFICATIONS, CODES AND STANDARDS
A. All Work specified
herein shall conform to or exceed the applicable requirements of the
referenced portions of the following publications to the extent that
the provisions thereof are not in conflict with other provisions of
these Specifications.
B. Comply with the
applicable editions of the following codes, regulations and
standards.
1. Industry Standards:
SSPWC Subsection 7-8
Standard Specifications for Public Works
Construction, Project
Site Maintenance
C. Comply with the
applicable reference Specifications as directed in the General
Requirements and the
Additional General Requirements.
1.4
CONTRACTOR
SUBMITTALS
A. Submit schedule of
clearing, grubbing, and erosion control measures to be put in place
for all work scheduled during the rainy season (October - April).
B. Submittals shall be
made in accordance with the General Requirements, Additional
General Requirements and
as specified herein.
1.5
QUALITY
ASSURANCE
A. Comply with the
requirements specified herein and the applicable reference
Specifications of the
General Requirements and Additional General Requirements.
PART 2 - PRODUCTS
2.1
CLEARING
A. Clearing shall
consist of removing all vegetable growth such as trees, roots,
stumps, shrubs, brush, limbs, and other vegetative growth. Remove
all evidence of their presence from the growth surface. Clearing
shall also include the removal and disposal of trash piles, rubbish,
abandoned piping and equipment, and fencing.
2.2
PRESERVATION
OF TREES, SHRUBS, AND OTHER VEGETATION
A. Protect trees,
shrubbery, and other vegetation not designated for removal from
damage resulting from the Work. Cut and remove tree branches only
where, in the opinion of the ENGINEER, such cutting is
necessary to affect construction. Scars resulting from the
removal of branches shall be treated with an approved tree sealant.
The ENGINEER will identify all trees for removal, relocation, or
preservation.
2.3
GRUBBING
A. Grubbing shall
consist of the removal and disposal of wood, stumps or root matter a
minimum of 36 inches below existing ground surface or bottom of
subgrade, whichever is deeper, unless otherwise shown on the
Drawings. Clearing shall include stumps, logs, roots, or root
systems greater than 1.5 inches in diameter or thickness.
2.4
CLEARING
AND GRUBBING FOR TRENCHING
A. The CONTRACTOR
shall obtain ENGINEER’s approval before beginning excavation. The
CONTRACTOR shall complete clearing and grubbing prior to the start
of trenching. The CONTRACTOR shall not permit excavated materials to
cover vegetation prior to disposal.
2.5
REMOVAL
AND DISPOSAL OF CLEARING AND GRUBBING DEBRIS
A. General: All
materials removed shall be disposed of and removed from the site.
No accumulation of flammable material shall remain on or adjacent to
the right-of-way. The roadway and adjacent areas shall be left with
a neat and finished appearance.
B. Bituminous
Pavement: Bituminous pavement removal shall be in conformance with
SSPWC Section 300-1.3.2 (a). Estimated thickness of paving sections
to be removed are shown on Sheets C1-7002 and C1-7003] of the
Drawings
C. Concrete Pavement:
Concrete pavement removal shall be in conformance with SSPWC Section
300-1.3.2 (b). Estimated thickness of paving sections to be removed
is shown on sheet C1-7003 of the Drawings.
D. Concrete Curb, Walk,
Gutters, Cross Gutters, Driveways, and Alley Intersections: Concrete
removal shall be in conformance with SSPWC Section 300-1.3.2 (c) and
shall be limited to the areas shown on the Drawings unless otherwise
specified.
2.6
STRIPPING
A. Stripping shall
include the removal and disposal of all organic sod, topsoil, grass
and grass roots, and other objectionable material remaining after
clearing and grubbing from the areas designated to be stripped. The
depth of stripping shall be as shown on the Drawings and specified
herein.
B. Topsoil from the
stripping shall be stockpiled and used for the finished site grading.
Excess topsoil will be placed in the waste disposal areas designated
by the ENGINEER.
PART 3 - EXECUTION
3.1
CLEARING
AND GRUBBING
A. Clearing and
grubbing shall be in conformance with the SSPWC Section 300-1.
3.2
STRIPPING
A. Prior to beginning
any excavation or fill, strip the topsoil to a depth sufficient to
remove all organic material and stockpile for future use. In
general, topsoil shall be removed where structures are to be built,
trenches dug, and roads, parking lots, walks, and similar
improvements constructed within the areas presently covered with
topsoil. Topsoil shall be stored clear of the construction area.
Take reasonable care to prevent the topsoil from becoming mixed with
subsoil.