Section
02232
PREPARATION
OF PAVEMENT SUBGRADE
PART 1 - GENERAL
1.1
THE
REQUIREMENT
A. The CONTRACTOR shall
furnish all tools, equipment, materials, and supplies and shall
perform all labor required to complete the work of preparation of
subgrade requirements as indicated on the Drawings and specified
herein.
B. The subgrade will be
considered as those areas and surfaces, new or existing, upon which
subbase or base material, pavement, curbs and gutters, driveways, or
sidewalks are to be placed.
C. All underground work
in the area of the subgrade shall be completed, properly backfilled
and compacted in compliance with the Geotechnical Study Report
prepared by Converse Consultants, and Section 02200,
Earthwork,
before subgrade work is started.
1.2
RELATED
WORK SPECIFIED ELSEWHERE
A. The requirements of
the following Specification sections and divisions apply to the Work
of this section. Other sections and divisions of the Specifications,
not referenced below, shall also apply to the extent required for
proper performance of this Work.
1. Section 02050,
Demolition
2. Section 02110,
Clearing, Grubbing, and Stripping
3. Section 02200,
Earthwork
4. Section 02527,
Concrete Curbs and Sidewalks
5. Section 02550,
Asphalt Concrete Pavement
1.3
REFERENCE
SPECIFICATIONS, CODES, AND STANDARDS
A. All Work specified
herein shall conform to or exceed the applicable requirements of the
referenced portions of the following publications to the extent that
the provisions thereof are not in conflict with other provisions of
these Specifications.
B. Comply with the
applicable editions of the following codes, regulations and
standards.
1. Industry Standards:
ASTM D 1557
Standard Test Methods for Laboratory
Compaction Characteristics of Soil Using Modified Effort (56,000
ft-lbf/ft3 (2,700 kN- m/m3))
SSPWC Subsection 301-1
“Green Book”, Standard Specifications for Public
Works Construction, Subgrade Preparation
C. Comply with the
applicable reference Specifications as directed in the General
Requirements and the
Additional General Requirements.
1.4
CONTRACTOR
SUBMITTALS
A. Submittals shall be
made in accordance with the General Requirements, Additional
General Requirements and
as specified herein.
1.5
QUALITY
ASSURANCE A. General
1. Quality assurance
shall be as specified in Section 02200, Earthwork.
1.6
WARRANTY
A. Guarantees and
Warranty shall be furnished in accordance with “Warranty”
(CONTRACTOR’s Guarantee) of the General Conditions.
PART 2 - PRODUCTS
2.1
EXCAVATION
AND EMBANKMENT
A. The excavation
shall include removal of materials that are encountered in
excavating to the required grades as shown on the Drawings,
including existing pavement, sidewalks and curbs designated to be
removed, or other deleterious materials as required to accomplish
the construction.
B. Unsuitable material
below the processing depth for subgrade shall be excavated and
disposed of specified in Section 02200, Earthwork, or as directed by
the ENGINEER.
PART 3 - EXECUTION
3.1
SUBGRADE
A. Excavate and
shape subgrade to line, grade, and cross-section shown on
the Drawings. Scarify and compact the top 3 (three) feet of
subgrade to at least 95 percent of the maximum dry density
attainable as determined by ASTM D 1557 except clay soils with a
Liquid Limit greater than or equal to 50 percent and a plasticity
index greater than or equal to 20 shall be prepared according to the
recommendation of the ENGINEER. The upper 1 (one) foot of subgrade
soils should be compacted to at least 95 percent of the laboratory
maximum dry density. Remove all soft or otherwise unsuitable
material and replace with suitable material as specified in Section
02200, Earthwork. In sandy soils the moisture content shall be kept
at or slightly above the optimum moisture content. However, in
clayey and silty soils, the moisture content shall be kept at about
2 percent above the optimum moisture content. The finished
subgrade shall be firm, hard, and unyielding. The subgrade shall be
considered to extend over the full width of the base course.
Compaction shall extend a minimum of 2 (two) feet beyond the edge of
paving, curb, or form.
B. Subgrade
tolerances for roadway structures, sidewalk, curb and gutter,
and driveways shall be in conformance with SSPWC Section 301-1.4.
3.2
EXCAVATION
BELOW SUBGRADE
A. Where the ENGINEER
determines the subgrade material to be unsuitable, excavation
below subgrade will be required to such depths as necessary to remove
the unsuitable material. Special equipment may be required because of
the presence of shallow utilities or other unforeseen conditions.
B. The over excavated
unsuitable subgrade shall be replaced with suitable material per
Section 02200, Earthwork.
3.3
PROTECTION
OF SUBGRADE
A. After preparing the
subgrade as specified, all traffic on the subgrade shall be avoided
prior to paving. Should it be necessary to haul over the
prepared subgrade, the CONTRACTOR shall drag and roll the traveled
way as frequently as may be necessary to remove ruts, cuts, and
breaks in the surface. All cuts, ruts, and breaks in the surface of
the subgrade that are not removed by the above operations shall be
raked and hand tamped. All equipment used for transporting materials
over the prepared subgrade shall be equipped with pneumatic tires.
B. Continued use of
sections of prepared subgrade for hauling that cause it to be cut up
or deform it from the true cross-section will not be permitted. The
CONTRACTOR shall protect the prepared subgrade from all traffic.
C. The CONTRACTOR will
be required to plank the subgrade before hauling materials or
equipment over it.
D. The subgrade shall
be maintained in the finished condition as required by
Article entitled “SUBGRADE” of this Specification until the first
succeeding course is placed.
No comments:
Post a Comment