Section 15008
STEEL PIPE – MORTAR-LINED AND
MORTAR-COATED
1.1 THE REQUIREMENT
A. The CONTRACTOR shall furnish and
install mortar-lined and mortar-coated steel pipeline, where
indicated, complete and in place, in accordance with the requirements
of the Contract Documents.
1.2 RELATED WORK SPECIFIED
ELSEWHERE
A. The requirements of the following
sections and divisions apply to the Work of this section. Other
sections and divisions of the Specifications, not referenced below,
shall also apply to the extent required for proper performance of
this Work.
1. Section 03600, Grout
2. Section 09800, Protective Coating
3. Section 15000, Piping, General
4. Section 15009, Steel Pipe -
Fabricated Specials
1.3 REFERENCE SPECIFICATIONS,
CODES, AND STANDARDS
A. All Work specified herein shall
conform to or exceed the applicable requirements of the referenced
portions of the following publications to the extent that the
provisions thereof are not in conflict with other provisions of these
Specifications.
B. Comply with the applicable
editions of the following codes, regulations and standards.
1. Codes and Regulations:
ASME BPVC
International Boiler and Pressure Vessel Code
CCR
California Code of Regulations, Title 24, Building
Standards Code
NFPA 70
National Electrical Code (NEC)
NFPA 70E
Standard for Electrical Safety in the Workplace
2. Industry Standards:
ASTM A 36
Standard Specification for Carbon Structural
Steel
ASTM A 139
Standard Specification for Electric-Fusion (Arc)- Welded Steel Pipe
(NPS 4 and Over)
ASTM A 283
Standard Specification for Low and Intermediate
Tensile Strength Carbon Steel Plates
ASTM A 572
Standard Specification for High-Strength Low- Alloy
Columbium-Vanadium Structural Steel
ASTM A 1011
Standard Specification for Steel, Sheet and Strip, Hot-Rolled,
Carbon, Structural, High- Strength Low-Alloy, High-Strength
Low-Alloy with Improved Formability, and Ultra-High Strength
ASTM C 150
Standard Specification for Portland Cement ASTM E 94
Standard Guide for Radiographic Examination ASTM E
165 Standard Practice for
Liquid Penetrant
Examination for General Industry
AWS D1.1
Structural Welding Code- Steel
AWWA C200
Steel Water Pipe - 6 in. (150 mm) and Larger
AWWA C205
Cement-Mortar Protective Lining and Coating for Steel Water Pipe - 4
In. (100 mm) and Larger - Shop Applied
AWWA C206
Field Welding of Steel Water Pipe
AWWA C208
Dimensions for Fabricated Steel Water Pipe
Fittings
AWWA C602
Cement-Mortar Lining of Water Pipelines in
Place - 4 in. (100 mm) and Larger
AWWA M11
Steel Water Pipe - A Guide for Design and
Installation
C. Comply with the applicable
reference Specifications as directed in the General
Requirements and Additional General
Requirements.
1.4 CONTRACTOR SUBMITTALS
A. Submittals shall be made in
accordance with the General Requirements, Additional
General Requirements and as specified
herein.
B. Shop Drawings: The CONTRACTOR
shall submit shop drawings of pipe and fittings and the following
supplemental requirements as applicable:
1. Joint and pipe/fitting wall
construction details that indicate the type and thickness of
cylinder; the position, type, size, and area of reinforcement;
manufacturing tolerances; and all other pertinent information
required for the manufacture of the product.
2. Fittings and specials details
such as elbows, wyes, tees, outlets, connections, test bulkheads,
and nozzles or other specials where shown that indicate amount and
position of all reinforcement. All fittings and specials shall be
properly reinforced to withstand the internal pressure, both
circumferential and longitudinal, and the external loading
conditions as indicated in the Contract Documents.
3. Design calculations of each
critical section of pipe wall, girth joints, and specials - all
sufficient to ascertain conformance of pipe and fittings with the
Specifications.
4. Material lists and steel
reinforcement schedules that include and describe all materials to
be utilized.
5. Line layout and marking diagrams
that indicate the specific number of each pipe and fitting, the
location of each pipe, and the direction of each fitting in the
completed line. In addition, the line layouts shall include the
pipe station and invert elevation at all changes in grade or
horizontal alignment; the station and invert elevation to which the
bell end of each pipe will be laid; all elements of curves and
bends, both in horizontal and vertical alignment; and the limits of
each reach of restrained and/or welded joints, or of concrete
encasement.
6. Full and complete information
regarding location, type, size, and extent of all welds shall be
shown on the shop drawings. The shop drawings shall distinguish
between shop and field welds. Shop drawings shall indicate by
welding symbols or sketches the details of the welded joints, and
the preparation of parent metal required to make them. Joints or
groups of joints in which welding sequence or technique is
especially important shall be carefully controlled to minimize
shrinkage stresses and distortion.
C. Certifications: The CONTRACTOR
shall furnish a certified affidavit of compliance for all pipe and
other products or materials furnished under this section of the
Specifications, as specified in AWWA C200 and C205, respectively.
D. Physical and chemical properties
of all steel:
1. Hydrostatic test reports.
2. Results of production weld tests.
E. All expenses incurred in making
samples for certification of tests shall be borne by the CONTRACTOR.
F. Grooved joint couplings and
fittings shall be shown on product submittals, and shall be
specifically identified with the applicable style or series
designation.
1.5 QUALITY ASSURANCE A.
General:
1. Inspection: All pipes shall be
subject to inspection at the place of manufacture in accordance with
the provisions of AWWA C200 and C205, respectively, as supplemented
by the requirements herein. The CONTRACTOR shall notify the
ENGINEER in writing of the manufacturing starting date not less than
14 calendar days prior to the start of any phase of the pipe
manufacture.
2. Tests: Except as modified
herein, all materials used in the manufacture of the pipe shall be
tested in accordance with the requirements of AWWA C200 and C205, as
applicable.
a. Material Testing: The ENGINEER
shall have the right at any time to call for and witness the making
of test specimens by any welder in accordance with these
Specifications. Any and all tests shall be at the CONTRACTOR's
expense. The CONTRACTOR shall furnish the ENGINEER three certified
copies of mill test reports. Mill test reports shall show results of
the chemical and physical tests made on each melt of steel
representing the steel plate furnished for the manufacture of the
pipe.
b. After the joint configuration is
completed and prior to lining with cement- mortar, each length of
pipe of each diameter and pressure class shall be shop- tested and
certified to a pressure of at least 80 percent of the yield strength
of the pipe steel.
c. In addition to the tests
required in AWWA C200, weld tests shall be conducted on each
5,000 feet of production welds and at any other times there is a
change in the grade of steel, welding procedure, or welding
equipment.
3. The CONTRACTOR shall perform said
material tests at no additional cost to OCSD. The ENGINEER shall
have the right to witness all testing conducted by the CONTRACTOR,
provided that the CONTRACTOR's schedule is not delayed for the
convenience of the ENGINEER.
4. In addition to those tests
specifically required, the ENGINEER may request additional samples
of any material including mixed concrete and lining and coating
samples for testing by the ENGINEER. The additional samples shall
be furnished at no additional cost to OCSD.
5. Specimen Plates: The ENGINEER
may require the CONTRACTOR to furnish specimen plates of the steel
to be used in the fabrication of the pipe. Specimen plates shall
be large enough to provide the number of test specimens required.
Should any test specimen fail to meet the requirements of the plate
specification, a second specimen plate of the same heat number shall
be furnished. Should any one test specimen from the second plate
fail, then all plates furnished from the same heat number will be
rejected. Tests of these specimens will be made by an independent
laboratory accepted by the ENGINEER. The CONTRACTOR will be
responsible for all expenses incurred in making the tests.
6. Required Tests: Specimen plates
shall be tested as follows:
7. Reduced Section Tensile Test:
The yield point and ultimate tensile strength shall not be less than
the minimum of the specified tensile range of the plate used.
8. Guided Bend Test: Bend tests
shall be performed on both root and face weld specimens. The
specimen shall be bent cold without fracture 180 degrees around a
pin or mandrel, having a diameter 3 times the thickness of the
plate, and shall show an elongation of not less than 20 percent
across the weld.
9. Radiographic Test: A 4-1/2-inch
x 17-inch spot x-ray shall be taken at a location as directed by the
ENGINEER. Procedures and interpretation shall be in accordance with
the International Boiler and Pressure Vessel Code, Section VIII,
Division 1, Part UW51, with the exception that ASTM E 94, Type I,
industrial radiographic film shall be used.
10. Porosity: The maximum acceptable
porosity shall be as set forth in Appendix IV
of the International Boiler and
Pressure Vessel Code.
11. Retest of Welds: Should any of the
tests taken from a shift's production fail to meet any of the
requirements of these Specifications, one additional set of weld
tests shall be made from each of the adjoining pipe sections. Retest
of welds shall be performed at the CONTRACTOR's expense, and shall be
made and accepted before beginning the next shift's production.
Should any retest result in failure to meet any of the requirements
of these Specifications, all pipe sections of that shift's production
will be rejected.
12. Welding Procedures: Welding
procedure specifications shall be furnished to the ENGINEER for
acceptance prior to the welding of pipe. The welding procedure
specifications shall specify, on a form equivalent to the ASME
Welding Procedure form, the type of plate edge preparation, welding
method, arc-voltage, arc-amperes, travel speed, wire size and type,
flux type, and all other procedures necessary to make the weld.
13. Welding Requirements: All welding
procedures used to fabricate pipe shall be prequalified under the
provisions of AWS D1.1. Welding procedures shall be required
for, but not necessarily limited to, longitudinal and girth or spiral
welds for pipe cylinders, spigot and bell ring attachments,
reinforcing plates and ring flange welds, and plates for lug
connections.
14. All Grooved products shall be of a
single manufacturer. Gaskets for grooved systems shall be of the
same manufacturer.
15. All castings used for coupling
housings, fittings, valve bodies, etc., shall be date stamped for
quality assurance and traceability.
B. CONTRACTOR Qualifications:
1. Welder Qualifications:
a. All welders and welding operators
shall be qualified under the applicable provisions of the standard
qualification procedure of the International Boiler and Pressure
Vessel Code, Section IX.
b. All welding shall be done by
skilled welders, welding operators, and tackers who have had adequate
experience in the methods and materials to be used. Welders shall be
qualified under the provisions of AWS D1.1 by an independent local,
approved testing agency not more than 6 months prior to commencing
work on the pipeline. Machines and electrodes similar to those used
in the Work shall be used in qualification tests. The CONTRACTOR
shall furnish all material and bear the expense of qualifying
welders.
2. Comply with the requirements for
the certifications, licenses, training, skills, experience, and
other qualifications specified in Paragraph entitled “Cement-Mortar
Lining for Shop Application” of Article entitled “Cement-Mortar
Lining” of this Specification.
PART 2 - PRODUCTS
2.1 GENERAL
A. Mortar-lined and mortar-coated
steel pipe shall conform to AWWA C200 and C205, subject to the
following supplemental requirements. The pipe shall be of the
diameter and class shown, shall be furnished complete with rubber
gaskets or welded joints, as indicated in the Contract Documents,
and all specials and bends shall be provided as required under the
Contract Documents. For pipe 14 inches in diameter and larger, the
inside diameter after lining shall not be less than the nominal
diameter specified or shown. Pipe smaller than 14 inches in
diameter may be furnished in standard outside diameters.
B. Markings: The CONTRACTOR
shall legibly mark all pipes and specials in accordance with
the laying schedule and marking diagram. Each pipe shall be numbered
in sequence and said number shall appear on the laying schedule and
marking diagram in its proper location for installation. All
special pipe sections and fittings shall be marked at each end with
top field centerline.
C. Handling and Storage: The pipe
shall be handled by use of wide slings, padded cradles, or other
devices, acceptable to the ENGINEER, designed and constructed to
prevent damage to the pipe coating/exterior. The use of chains,
hooks, or other equipment which might injure the pipe
coating/exterior will not be permitted. Stockpiled pipe shall be
suitably supported and shall be secured to prevent accidental
rolling. All other pipe handling equipment and methods shall be
acceptable to the ENGINEER.
D. The CONTRACTOR shall be fully
liable for the cost of replacement or repair of pipe which is
damaged.
E. Stockpiled pipe shall be
supported on sand or earth berms free of rock exceeding 3 inches in
diameter. The pipe shall not be rolled and shall be
secured to prevent accidental rolling.
F. Strutting: Adequate strutting
shall be provided on all specials, fittings, and straight pipe so as
to avoid damage to the pipe and fittings during handling, storage,
hauling, and installation. For mortar-lined or mortar-coated steel
pipe, the following requirements shall apply:
1. The strutting shall be placed as
soon as practicable after the mortar lining has been applied and
shall remain in place while the pipe is loaded, transported,
unloaded, installed and backfilled at the jobsite.
2. The strutting materials, size and
spacing shall be adequate to support the backfill plus any greater
loads which may be imposed by the backfilling and compaction
equipment.
3. Any pipe damaged during
handling, hauling, storage, or installation due to improper
strutting shall be repaired or replaced.
4. The details of the strutting
assembly shall be submitted for review by the
ENGINEER prior to the start of pipe
manufacture.
G. Laying Lengths: Maximum pipe
laying lengths shall be 40 feet with shorter lengths provided as
required by the Drawings.
H. Offset Tolerances: For pipe wall
thicknesses of 3/8 inch or less, the maximum radial offset
(misalignment) for submerged arc and gas metal arc welded pipe shall
be 0.1875 times the pipe wall thickness or 1/16 inch, whichever is
larger. For pipe wall thickness of greater than 3/8 inch, the
maximum radial offset shall be 0.1875 times the wall thickness or
5/32 inch, whichever is smaller.
I. Lining: The pipe lining shall
have smooth dense interior surfaces and shall be free from
fractures, excessive interior surface crazing and roughness.
J. Bonding and Electrical
Conductivity: All unwelded pipe joints shall be bonded for
electrical conductivity in accordance with the details shown.
K. Closures and Correction Pieces:
Closures and correction pieces shall be provided as required so that
closures may be made due to different headings in the pipe-laying
operation and so that correction may be made to adjust the pipe
laying to conform to pipe stationing shown on the Drawings. The
locations of correction pieces and closure assemblies are shown
on the Drawings. Any change in location or number of said items
shall be acceptable to the ENGINEER.
2.2 MATERIALS
A. Cement: Cement for mortar shall
conform to the requirements of AWWA C205; provided, that cement for
mortar coating shall be Type II and mortar lining shall be Type II
or V. A fly ash or pozzolan shall not be used as a cement
replacement.
B. Steel for Cylinders and Fittings:
Pipe manufactured under AWWA C200 shall be fabricated from sheet
conforming to the requirements of ASTM A 1011, Grade 36, or from
plate conforming to the requirements of ASTM A 36, A 283, Grades C
or D, or A 572, Grade 42, or coil conforming to the requirements of
ASTM A 139, Grades B or C. All longitudinal and girth seams,
straight or spiral, shall be butt-welded using an approved
electric-fusion-weld process.
C. All steel used for the fabrication
of pipe shall have a maximum carbon content of 0.25 percent and
shall have a minimum elongation of 22 percent in a 2-inch gauge
length.
2.3 SPECIALS AND FITTINGS
A. Unless otherwise necessary under
the requirements of the Contract Documents, all specials and
fittings shall be in accordance with Section 15009, Steel Pipe -
Fabricated Specials, and shall conform to the dimensions of AWWA
C208.
2.4 DESIGN OF PIPE
A. General: The pipe furnished shall
be steel pipe, mortar-lined and mortar-coated, with rubber-gasketed
or field-welded joints as shown. The pipe shall consist of a
steel cylinder, either shop-lined or lined-in-place with Portland
cement-mortar with an exterior coating of cement-mortar.
B. The pipe shall be designed,
manufactured, tested, inspected, and marked according to applicable
requirements previously stated and, except as hereinafter modified,
shall conform to AWWA C200.
C. Pipe Dimensions: The pipe shall be
of the diameter and class shown. The minimum steel cylinder
thickness for each pipe size shall be as specified or shown.
D. Fitting Dimensions: The fittings
shall be of the diameter and class shown.
E. Joint Design: The standard field
joint for steel pipe shall be either a single-welded lap joint or a
rubber-gasketed joint for all pipe sizes up to and including
diameter of 54 inches and shall be a single-welded lap joint for
pipe sizes above diameters of 54 inches. Mechanically coupled or
flanged joints shall be required where shown. Butt-strap joints
shall be used only where required for closures or where shown. The
joints furnished shall have the same or higher pressure rating as
the abutting pipe. Gaskets shall be captured between the ends of
the pipe to protect the ends of the exposed metal from corrosion.
F. Lap joints prepared for field
welding shall be in accordance with AWWA C200. The method used to
form, shape, and size bell ends shall be such that the physical
properties of the steel are not substantially altered. Unless
otherwise accepted by the ENGINEER, bell ends shall be formed by an
expanding press or by being moved axially over a die in such a
manner as to stretch the steel plate beyond its elastic limit to
form a truly round bell of suitable diameter and shape. Facing
surfaces of the bell and spigot shall be essentially parallel, but
in no case shall the bell slope vary more than 2 degrees from the
longitudinal axis of the pipe.
G. For bell-and-spigot ends with
rubber gaskets, the clearance between the bells and spigots shall be
such that, when combined with the gasket groove configuration and
the gasket itself, will provide watertight joints under all
operating conditions when properly installed. The CONTRACTOR shall
require the pipe manufacturer to submit details complete with
significant dimensions and tolerances and also to submit performance
data indicating that the proposed joint has performed satisfactorily
under similar conditions. In the absence of a history of field
performance, the results of a test program shall be submitted.
Unless otherwise accepted by the ENGINEER, bell ends shall be formed
by an expanding press or by being moved axially over a die in such a
manner as to stretch the steel plate beyond its elastic limit to
form a truly round bell of suitable diameter and shape. No process
will be permitted in which the bell is formed by rolling.
Shop-applied interior linings and exterior coatings shall be held
back from the ends of the pipe as shown or as otherwise acceptable
to the ENGINEER.
H. Restrained Joints: Where
shown restrained joints shall be field-welded joints, designs
shall include considerations of stresses induced in the steel
cylinder, the joint rings, and any field welds caused by thrust at
bulkheads, bends, reducers, and line valves resulting from the
design working pressure. For field welded joints, design
stresses shall not exceed 50 percent of the specified minimum yield
strength of the grade of steel utilized, or 16,500 pounds per
inch, whichever is less, for the part being examined when
longitudinal thrust is assumed to be uniformly distributed around
the circumference of the joint. At the CONTRACTOR's option, the
steel cylinder area may be progressively reduced from the point of
maximum thrust to the end of the restrained length. All joints to
be field welded for thrust restraint shall have the joint rings
attached to the cylinder with double fillet welds.
2.5 CEMENT-MORTAR LINING
A. Cement-Mortar Lining for Shop
Application: Except as otherwise provided herein, interior
surfaces of all steel pipe, fittings, and specials shall be cleaned
and lined in the shop with cement-mortar lining applied
centrifugally in conformity with AWWA C205. During the lining
operation and thereafter, the pipe shall be maintained in a round
condition by suitable bracing or strutting. The lining machines
shall be of a type that has been used successfully for similar work
and shall be subject to ENGINEER's acceptance. Every precaution
shall be taken to prevent damage to the lining. If lining is
damaged or found faulty at delivery site, the damaged or
unsatisfactory portions shall be replaced with lining conforming to
these Specifications at no additional cost to OCSD.
B. The minimum lining thickness
shall be as follows, with a tolerance of plus or minus 25 percent:
-
Nominal Pipe Diameter(inches)
Lining Thickness(inches)
4 – 12
5/16
13 – 16
3/8
17 – 24
1/2
Over 24
3/4
C. The pipe shall be left bare where
field joints occur as shown. Ends of the linings shall be left
square and uniform. Feathered or uneven edges will not be permitted.
D. Defective linings, as determined
by the ENGINEER, shall be removed from the pipe wall and shall be
replaced to the full thickness required. Defective linings shall be
cut back to a square shoulder in order to avoid feather edged
joints.
E. The progress of the application
of mortar lining shall be regulated in order that all handwork,
including the repair of defective areas is cured in accordance with
the provisions of AWWA C205. Cement-mortar for patching shall be
the same materials as the mortar for machine lining, except that a
finer grading of sand and mortar richer in cement shall be used when
field inspection indicates that such mix will improve the finished
lining of the pipe.
G. Protection of Pipe
Lining/Interior: For all pipe and fittings with plant-applied or
cement-mortar linings, the CONTRACTOR shall provide a polyethylene
or other suitable bulkhead on the ends of the pipe and on all
special openings to prevent drying out of the lining. All
bulkheads shall be substantial enough to remain intact during
shipping and storage until the pipe is installed.
2.6 EXTERIOR COATING OF PIPE
A. Exterior Coating of Exposed
Piping: The exterior surfaces of pipe which will be exposed to
the atmosphere inside structures or above ground shall be
thoroughly cleaned and then given a shop coat of rust-inhibitive
primer conforming to the requirements of Section 09800, Protective
Coating.
B. Exterior Coating of Buried
Piping: All pipe for buried service, including bumped heads, shall
be coated with a 1.5-inch minimum thickness of reinforced
cement-mortar coating. Unless otherwise shown on the Drawings,
exterior surfaces of pipe or fittings passing through structure
walls shall be cement-mortar coated from the center of the wall or
from the wall flange to the end of the underground portion of pipe
or fitting. The coating shall be reinforced with a spiral wire
reinforcement or welded wire fabric in accordance with AWWA C205.
The welded wire fabric shall be securely fastened to the pipe with
welded clips or strips of steel. The wire spaced 2 inches on
centers shall extend circumferentially around the pipe. The ends
of reinforcement strips shall be lapped 4 inches and the free
ends tied or looped to assure continuity of the
reinforcement.
C. Coal-Tar Epoxy Protective Coating:
The exterior surface of all mortar-coated pipe and fittings shall
be protected with a minimum of 25-mil-thick 100 percent solids
coal-tar epoxy coating, Carboline Bitumastic 300M, Tnemec Hi-Build
Tnemec-Tar Series 46H-413
Or Equal. The coating may be applied
to freshly placed, partially cured, or cured cement- mortar coating.
Application shall be in accordance with the manufacturer's
printed instructions.
2.7 PIPE APPURTENANCES
A. Pipe appurtenances shall be in
accordance with Section 15000, Piping, General.
PART 3 - EXECUTION
3.1 INSTALLATION OF PIPE
A. Handling and Storage: All pipe,
fittings, etc., shall be carefully handled and protected against
damage to lining and coating/interior and exterior surfaces, impact
shocks, and free fall. All pipe handling equipment shall be
acceptable to the ENGINEER. Pipe shall not be placed directly on
rough ground but shall be supported in a manner which will protect
the pipe against injury whenever stored at the trench site or
elsewhere. Pipe shall be handled and stored at the trench site in
accordance with the requirements stated in Part 2 of this
Specification. No pipe shall be installed when the lining or
coating/interior or exterior surfaces show cracks that may be
harmful as determined by the ENGINEER. Such damaged lining and
coating/interior and exterior surfaces, shall be repaired, or a new
undamaged pipe shall be furnished and installed.
B. All pipe damaged prior to
Substantial Completion shall be repaired or replaced by the
CONTRACTOR.
C. The CONTRACTOR shall inspect each
pipe and fitting to insure that there are no damaged portions of the
pipe. The CONTRACTOR shall remove or smooth out any burrs, gouges,
weld splatter or other small defects prior to laying the pipe.
D. Before placement of pipe in the
trench, each pipe or fitting shall be thoroughly cleaned of any
foreign substance, which may have collected thereon and shall be
kept clean at all times thereafter. For this purpose, the openings
of all pipes and fittings in the trench shall be closed during any
interruption to the Work.
E. Pipe Laying: When the pipe is
being laid, it shall be turned and placed where possible, so that
any slightly damaged portion will be on top. The damaged area shall
be repaired for the protection of any exposed steel. All damaged
areas shall be repaired using materials and methods acceptable to
the ENGINEER.
F. Pipe shall be laid directly on
the bedding material. No blocking will be permitted, and the
bedding shall be such that it forms a continuous, solid bearing for
the full length of the pipe. Excavations shall be made as needed to
facilitate removal of handling devices after the pipe is laid. Bell
holes shall be formed at the ends of the pipe to prevent point
loading at the bells or couplings. Excavation shall be made as
needed outside the normal trench section at field joints to permit
adequate access to the joints for field connection operations and
for application of coating on field joints.
G. Each section of pipe shall be laid
in the order and position shown on the laying schedule. In laying
pipe, it shall be laid to the setline and grade, within
approximately one (1) inch plus or minus. On grades of zero slope,
the intent is to lay to grade.
H. Where necessary to raise or lower
the pipe due to unforeseen obstructions or other causes, the
ENGINEER may change the alignment and/or the grades. Such change
shall be made by the deflection of joints, by the use of bevel
adapters, or by the use of additional fittings. However, in no
case shall the deflection in the joint exceed the maximum deflection
recommended by the pipe manufacturer. No joint shall be misfit any
amount that will be detrimental to the strength and water tightness
of the finished joint. In all cases the joint opening, before
finishing with the protective mortar inside the pipe, shall be the
controlling factor.
I. Except for short runs that may
be permitted by the ENGINEER, pipes shall be laid uphill on grades
exceeding 10 percent. Pipe that is laid on a downhill grade shall
be blocked and held in place until sufficient support is furnished
by the following pipe to prevent movement. All bends shall be
properly installed as shown.
J. Pipe struts shall be left in
place until backfilling operations have been completed for pipe 42
inches in diameter and larger. Struts in pipe smaller than 42
inches may be removed immediately after laying, provided, that the
deflection of the pipe during and after backfilling does not exceed
that specified. After the backfill has been placed, the struts
shall be removed and shall remain the property of the CONTRACTOR.
K. Pipe and Specials Protection:
The openings of all pipe and specials where the pipe and specials
have been cement-mortar lined in the shop shall be protected with
suitable bulkheads to maintain a moist atmosphere and to
prevent unauthorized access by persons, animals, water or any
undesirable substance. The bulkheads shall be so designed to
prevent drying out of the interior of the pipe. The CONTRACTOR
shall introduce water into the pipe to keep the mortar moist where
moisture has been lost due to damaged bulkheads. At all times,
means shall be provided to prevent the pipe from floating.
L. Pipe Cleanup: As pipe laying
progresses, the CONTRACTOR shall keep the pipe interior free of all
debris. The CONTRACTOR shall completely clean the interior of the
pipe of all sand, dirt, mortar splatter and any other debris
following completion of pipe laying, pointing of joints and any
necessary interior repairs prior to testing and disinfecting the
completed pipeline.
3.2 RUBBER GASKETED JOINTS
A. Rubber-Gasketed Joints:
Immediately before jointing pipe, the spigot end of the pipe shall
be thoroughly cleaned, and a clean rubber gasket lubricated with an
approved vegetable-based lubricant shall be placed in the spigot
groove. The volume of the gasket shall be "equalized" by
moving a metal rod between the gasket and the spigot ring around the
full circumference of the spigot ring. The bell of the pipe already
in place shall be carefully cleaned and lubricated with a
vegetable-based lubricant. The spigot of the pipe section shall
then be inserted into the bell of the previously laid joint and
telescoped into its proper position. Tilting of the pipe to insert
the spigot into the bell will not be permitted. After the pipe
units have been joined, a feeler gauge shall be inserted into the
recess and moved around the periphery of the joint to detect any
irregularity in the position of the rubber gasket. If the gasket
cannot be "felt" all around, the joint shall be
disassembled. If the gasket is undamaged, as determined by the
ENGINEER, it may be reused, but only after the bell ring and gasket
have been re-lubricated.
3.3 WELDED JOINTS
A. General: Field-welded joints
shall be in accordance with AWWA C206.
B. Where exterior welds are
performed, adequate space shall be provided for welding and
inspection of the joints.
C. During installation of welded
steel pipe in either straight alignment or on curves, the pipe shall
be laid so that at any point around the circumference of the joint
there is a minimum lap of 1/2 inch and a minimum space of 3/4 inch
plus the thickness of the steel pipe wall between the spigot end of
the pipe and the nearest tangent to a bell radius.
D. Butt straps, where used or
required, shall be a minimum of 6 inches wide, the same thickness as
the pipe wall and shall provide for a minimum of 3/4 inch lap at
each pipe joint.
E. After the pipe and pipe joint are
properly positioned in the trench, the length of pipe between joints
shall be backfilled to at least one (1) foot above the top of the
pipe. Care shall be exercised during the initial backfilling to
prevent movement of the pipe and to prevent any backfill material
from being deposited on the joint.
F. Prior to the beginning of the
welding procedure, any tack welds used to position the pipe during
laying shall be removed. Any annular space between the faying
surfaces of the bell and spigot shall be equally distributed around
the circumference of the joint by shimming, jacking, or other
suitable means. The weld shall then be made in accordance with AWWA
C206. Where more than one pass is required, each pass except the
first and final one shall be peened to relieve shrinkage stresses;
and all dirt, slag, and flux shall be removed before the succeeding
bead is applied.
G. Qualifications of Procedures and
Welders: All welding procedures used to install pipe shall be
prequalified under provisions of AWS D1.1. Welding procedures shall
be required for field attachments and field welded joints.
H. Joints: The pipe ends shall be
cut straight on joints where butt straps are used for realignment,
adjustment, or deflection, and fillet welds shall be made as shown
on the Drawings.
I. Unless double fillet welds are
shown on the Drawings, field-welded lap joints may, at the
CONTRACTOR's option, be made on either the inside or the outside of
the pipe.
3.4 GROOVED MECHANICAL JOINTS
A. ASTM A53B/A106B, roll or cut
grooved as appropriate to pipe material, wall thickness,
pressures and size. Pipe ends to be grooved conforming to
ANSI/AWWA C606.
1. Couplings, 2 Inches to 12
Inches: Two ASTM A536 ductile iron housing segments,
pressure-responsive synthetic rubber gasket (Grade to suit the
intended service) and plated steel bolts and nuts.
a. Style HP-70 Rigid coupling is for
use in high pressure service applications.
b. Rigid Type: Housings shall be
cast to provide system support and hanging in accordance with ASME
B31.1 and B31.9,
1) 2 Inches through 8 Inches:
“Installation Ready” stab-on coupling designed for direct
‘stab’ installation onto grooved end pipe without prior field
disassembly and no loose parts.
2) 1 Inch through 12 Inches:
Standard rigid coupling.
c. Flexible Type: Use in locations
where vibration isolation and stress relief are required.
Flexible couplings may be used in lieu of flexible connectors
for vibration isolation at equipment connections. A minimum of
three couplings, for each connector, shall be placed in close
proximity to the vibration source.
1) 2 Inches through 8 Inches:
Coupling designed for direct installation onto grooved end pipe
without prior field disassembly and no loose parts.
2) 1 Inch through 24 Inches:
Standard flexible couplings.
3) 24 Inches to 42 Inches: Standard
flexible multi-segment couplings.
4) Couplings, 14 Inches to 60
Inches: Two ASTM A536 ductile iron housing segments with a
pressure-responsive synthetic rubber gasket of a Flush Seal design
(Grade to suit the intended service) and plated steel bolts and
nuts.
a) Rigid Type: Provides a rigid
joint that corresponds with support spacing as defined by ASMB B31.1
and B31.9,
b) Flexible Type: Allows for
linear and angular movement, vibration isolation and stress relief.
d. Flange Adapters, 2 Inches through
24 Inches: ASTM A536 ductile iron casting, flat faced, designed
for incorporating flanged components with ANSI Class 125, 150, or
300 bolt-hole patterns to a grooved piping system.
3.5 JOINT COATING AND LINING
A. General: The interior and
exterior joint recesses shall be thoroughly wiped clean and all
water, loose scale, dirt and other foreign material shall be removed
from the inside surface of the pipe. The cement for joint grout
shall be non-shrink grout as specified in Section 03600, Grout.
B. Joint Coating: After the pipe
has been laid and after sufficient backfill has been placed between
the joints to hold the pipe securely in place, the outside annular
space between pipe sections shall be completely filled with
non-shrink grout formed by the use of polyethylene foam-lined fabric
bands. The grout shall be thoroughly mixed with water to a
consistency of thick cream. The grout space prior to filling shall
be flushed with water so that the surface of the joint to be in
contact with the grout will be thoroughly moistened when the grout
is poured. The joint shall be filled with grout by pouring from one
side only, and shall be rodded with a wire or other flexible rod or
vibrated so that the grout completely fills the joint recess by
moving down one side of the pipe, around the bottom of the pipe and
up the opposite side. Pouring and rodding the grout shall be
continued to allow completion of the filling of the entire joint
recess in one operation. Care shall be taken to leave no unfilled
space. Grouting of the outside joint spaces shall be kept as close
behind the laying of the pipe as possible except that in no case
shall grouting be closer than three joints of the pipe being laid.
C. Grout Bands (Diapers): The grout
bands or heavy-duty diapers shall be polyethylene foam-lined fabric
with steel strapping of sufficient strength to hold the fresh
mortar, resist rodding of the mortar and allow excess water to
escape. The foam plastic shall be 100 percent closed cell,
chemically inert, insoluble in water and resistant to acids alkalis
and solvents, and shall be BASF Sonneborn Sonolastic, Monmouth
Rubber & Plastics Corp. Durafoam, Or Equal.
D. The fabric backing shall be cut
and sewn into 9-inch-wide strips with slots for the steel strapping
on the outer edges. The polyethylene foam shall be cut into strips
6 inches wide and slit to a thickness
of 1/4 inch, which will expose a hollow or open cell surface on one
side. The foam liner shall be attached to the fabric backing with
the open or hollow cells facing towards the pipe. The foam strip
shall cover the full interior circumference of the grout band with
sufficient length to permit an 8-inch overlap of the foam at or near
the top of the pipe joint. Splices to provide continuity of the
material will be permitted. The polyethylene foam material shall be
protected from direct sunlight.
E. The polyethylene foam-lined grout
band shall be centered over the joint space with approximately equal
widths extending over each pipe end and securely attached to the
pipe with the steel straps. After filling the exterior joint space
with non-shrink grout, the flaps shall be closed and overlapped in a
manner that fully encloses the grout with polyethylene foam. The
grout band shall remain in position on the pipe joint.
F. Joint Lining: After the backfill
has been completed to final grade, the interior joint recess shall
be filled with non-shrink grout of stiff consistency. The mortar
shall be tightly packed into the joint recess and troweled flush
with the interior surface, and all excess shall be removed. At no
point shall there be an indentation or projection of the mortar
exceeding 1/16 inch. With pipe smaller than 24 inches in diameter,
before the spigot is inserted into the bell, the bell shall be
daubed with non-shrink grout. The spigot end then shall be forced
to the bottom of the bell and excess mortar on the inside of the
joint shall be swabbed out.
3.6 INSTALLATION OF PIPE
APPURTENANCES
A. Protection of Appurtenances:
Where the joining pipe is concrete or coated with cement mortar,
buried appurtenances shall be coated with a minimum thickness of one
(1) inch of cement mortar having one part cement to not more than
two (2) parts plaster sand. Following coating with cement mortar,
the appurtenances shall be coated with coal- tar epoxy in accordance
with Paragraph entitled "Coal-Tar Epoxy Protective Coating"
of Part 2 herein.
B. Installation of Valves: All
valves shall be handled in a manner to prevent any injury or damage
to any part of the valve. All joints shall be thoroughly cleaned and
prepared prior to installation. The CONTRACTOR shall adjust all
stem packing and operate each valve prior to installation to insure
proper operation.
C. All buried valves shall be coated
and protected in accordance with Section 09800, Protective Coating.
D. All valves shall be installed so
that the valve stems are plumb and in the location shown.
E. Installation of Flanged Joints:
Before the joint is assembled, the flange faces shall be thoroughly
cleaned of all foreign material with a power wire brush. The gasket
shall be centered and the connecting flanges drawn up watertight
without unnecessarily stressing the flanges. All bolts shall be
tightened in a progressive diametrically opposite sequence and
torqued with a suitable, approved and calibrated torque wrench. All
clamping torque shall be applied to the nuts only.
F. All buried flanges shall be
coated and protected in accordance with Section 09800, Protective
Coating.
G. Insulated Joints: Insulated
joints and appurtenant features shall be made by the CONTRACTOR, as
shown on the Drawings. The CONTRACTOR shall exercise special care
when installing these joints to prevent electrical conductivity
across the joint. After the insulated joint is completed, an
electrical resistance test will be performed by the ENGINEER. Should
the resistance test indicate a short circuit, the CONTRACTOR shall
remove the insulating units to inspect for damages, replace all
damaged portions, and reassemble the insulating joint. The
insulated joint shall then be retested to assure proper insulation.
H. Flexible Coupled Joints: When
installing flexible couplings, care shall be taken that the
connecting pipe ends, couplings and gaskets are clean and free of all
dirt and foreign matter with special attention being given to the
contact surfaces of the pipe, gaskets and couplings. The
couplings shall be assembled and installed in conformity with
the recommendation and instruction of the coupling manufacturer.
I. Wrenches used in bolting
couplings shall be of a type and size recommended by the coupling
manufacturer. Coupling bolts shall be tightened so as to secure a
uniform annular space between the follower rings and the body of the
pipe with all bolts tightened approximately the same amount.
Diametrically opposite bolts shall be tightened progressively and
evenly. Final tightening shall be done with a suitable, approved and
calibrated torque wrench set for the torque recommended by the
coupling manufacturer. All clamping torque shall be applied to the
nut only.
J. Upon completion of the coupled
joint, the coupling and bare metal of the pipe shall be cleaned,
primed and protected in accordance with Section 09800, Protective
Coating.
No comments:
Post a Comment